Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 66397: 2010-001-00 EXP TWISP RIVER FLOODPLAIN
Project Number:
Title:
Upper Columbia Programmatic Habitat
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Cascade Entiat 25.00%
Methow 25.00%
Okanogan 25.00%
Wenatchee 25.00%
Contract Number:
66397
Contract Title:
2010-001-00 EXP TWISP RIVER FLOODPLAIN
Contract Continuation:
Previous: Next:
62758: 2010-001-00 EXP TWISP RIVER FLOODPLAIN
Contract Status:
Closed
Contract Description:
Methow Salmon Recovery Foundation (MSRF) and its partners, including Bureau of Reclamation (Reclamation), Methow Conservancy, and Trout Unlimited (TU), plan to implement a reach-scale salmon habitat enhancement project in the Lower Twisp River between 2014 and 2017. The Twisp River Floodplain Project will conduct project development and environmental compliance activities in advance of the implementation contract for the Twisp River Floodplain Project funded through the UCSRB targeted solicitation process.

Project development activities for this project include on-site vegetation surveys, topographic surveys, hydrologic monitoring and data collection, geotechnical investigations and analysis, wetland delineation, fish surveys (presence/absence/use), photo points, pre-implementation weed removal and riparian plantings, design development, landowner/stakeholder outreach and coordination, and related project coordination activities.

Environmental compliance for this pre-implementation phase of the project has largely been completed under the previous contract.  Additional possible EC for pre-implementation activities includes additional Section 106 cultural consultation as needed, limited federal Section 7 ESA consultation (USFWS and NOAA) as needed for pre-implementation activities such as geotechnical investigation and analysis and decommissioning irrigation infrastructure.  Additional EC for the follow-on implementation contract will be completed under this contract once a sufficient design is completed.  This additional EC will include Section 7 ESA consultation for follow-on construction activities and  other environmental permitting processes completed through the JARPA, including the WDFW Hydraulic Project Authorization, SEPA, Corps of Engineers Nationwide permits, county shorelines and floodplain development, and water quality permits.  

The goal of this Twisp River Floodplain pre-implementation contract would be to work with BPA, UCSRB, and the Bureau of Reclamation to develop the preferred alternative into a full design for implementation at the site and to complete state, local, and BPA's federal EC requirements as early in the process as feasible in order to ensure completion of these requirements within the respective timelines to allow construction to proceed in the summer 2015-17 work windows.

-------------------------------------------------------------
Two additional Work Elements have been added to this contract to include activities planned for the M2 WDFW Floodplain project area.  The purpose of these Work Elements is to meet the conditions of the Right of Entry with the Washington Department of Fish and Wildlife by assessing and maintaining the plantings installed in the M2 Implementation contract and by assessing, monitoring, and repairing as needed the installed habitat elements from the M2 Implementation Contract.
Account Type(s):
Expense
Contract Start Date:
09/22/2014
Contract End Date:
09/21/2015
Current Contract Value:
$154,299
Expenditures:
$154,299

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Brenda Aguirre Bonneville Power Administration Yes Env. Compliance Lead baguirre@bpa.gov (503) 230-5928
Roy Beaty Bonneville Power Administration Yes F&W Approver rebeaty@bpa.gov (503) 230-5213
Joseph Connor Bonneville Power Administration Yes COR jwconnor@bpa.gov (503) 230-3172
Chris Eliassen Methow Salmon Recovery Foundation Yes Administrative Contact chrise@methowsalmon.org (509) 996-2787
Brian Fisher Methow Salmon Recovery Foundation Yes Technical Contact brian@methowsalmon.org (509) 387-1716
Jessica Goldberg Methow Salmon Recovery Foundation Yes Contract Manager jessica@methowsalmon.org (360) 624-3592
Chris Johnson Methow Salmon Recovery Foundation Yes Supervisor chrisj@methowsalmon.org (509) 996-2787
Deb Nickell Methow Salmon Recovery Foundation Yes Interested Party deb@methowsalmon.org (509) 996-2787
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605
Katy Williams Methow Salmon Recovery Foundation No Administrative Contact katy@methowsalmon.org (509) 996-2787


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Complete Environmental Compliance permitting processes A: 165. Obtain Required Permits, Authorizations, and Documentation for the Twisp River Floodplain project 09/21/2015 09/21/2015
All administrative tasks fulfilled with timely quality products B: 119. Manage BPA Contracting Requirements 09/21/2015 09/21/2015
Obtain Data to Support Final Design Final Design and Materials Balance C: 115. Obtain data to inform development of final design 09/15/2015 09/21/2015
Weed management / removal D: 199. Remove weeds prior to implementation 09/21/2015 09/21/2015
Alternate Water Supply, Abandonment and Decommissioning of Existing Surface Supply E: 82. Install irrigation well 09/21/2015 09/18/2015
Plant and maintain native riparian vegetation F: 47. Establish native riparian plantings 09/21/2015 09/21/2015
Final Design and Specifications G: 175. Complete final design and specs 09/21/2015 09/21/2015
Pre-construction Contracting and Management H: 100. Conduct pre-construction bid and contracting process 09/21/2015 09/21/2015
Acquisition of construction materials for implementation contract I: 180. Acquire Complexity Restoration Materials 09/21/2015 09/21/2015
Seasonal maintenance - native riparian vegetation J: 198. Assess and maintain restoration vegetation (WDFW Floodplain) 09/21/2015 09/21/2015
Assessment and Adaptive Management K: 186. Assess, monitor, and repair installed habitat elements (WDFW Floodplain) 09/21/2015 09/21/2015
Maintain, Repair, Install and/or Remove L: 186. Construction Services (WDFW Floodplain) 09/21/2015 09/21/2015

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 1 instance of WE 199 Remove Vegetation
  • 1 instance of WE 198 Maintain Vegetation
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 82 Install Well
  • 1 instance of WE 100 Construction Management
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 1 instance of WE 199 Remove Vegetation
  • 1 instance of WE 198 Maintain Vegetation
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 82 Install Well
  • 1 instance of WE 100 Construction Management

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Obtain Required Permits, Authorizations, and Documentation for the Twisp River Floodplain project 09/22/2014
B 119 Manage BPA Contracting Requirements 09/22/2014
C 115 Obtain data to inform development of final design 04/14/2015
D 199 Remove weeds prior to implementation 04/15/2015
E 82 Install irrigation well 04/15/2015
F 47 Establish native riparian plantings 04/15/2015
G 175 Complete final design and specs
H 100 Conduct pre-construction bid and contracting process 09/22/2014
I 180 Acquire Complexity Restoration Materials 04/14/2015
J 198 Assess and maintain restoration vegetation (WDFW Floodplain) 09/22/2014
K 186 Assess, monitor, and repair installed habitat elements (WDFW Floodplain) 09/22/2015
L 186 Construction Services (WDFW Floodplain) 09/22/2014
M 185 Periodic Status Reports for BPA 09/22/2014
N 132 Submit Progress Report for the period (Sep 2014) to (Sep 2015) - funded through a separate contract 09/22/2014