Province | Subbasin | % |
---|---|---|
Basinwide | - | 100.00% |
* Expenditures data includes accruals and are based on data through 28-Feb-2025.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
All administrative tasks fulfilled with timely quality products | B: 119. Manage and Administer Project | 10/31/2015 | 11/15/2014 | |
Technical Support and Training Materials | C: 160. Technical Support and Training | 10/31/2015 | 10/31/2015 | |
Accurate and timely watershed, site, site visit, measurement, and metric data | D: 160. Operational Support | 10/31/2015 | 10/31/2015 | |
Ensure champmonitoring.org remains operational during FY 2015 | E: 160. Host and Manage Applications and Elastic Cloud Services | 10/31/2015 | 10/31/2015 | |
Functional and usability improvements to champmonitoring.org | F: 160. General and Operational System Improvements | 10/31/2015 | 10/31/2015 | |
Better support for analysis and synthesis of CHaMP data | G: 160. Modeling, Analysis, and Synthesis System Improvements | 10/31/2015 | 10/31/2015 | |
Improved software application that runs on field laptops | H: 160. Laptop Data Broker Improvements | 06/01/2015 | 06/01/2015 | |
Improved iPad Data Logger Application | I: 160. iOS Data Logger Application Improvements | 10/31/2015 | 10/31/2015 | |
Properly managed inventory of data loggers available to field crews when needed | J: 160. iOS Data Logger Hardware Maintenance | 10/31/2015 | 10/31/2015 | |
Integrated Metric Database and Web Application | K: 160. Construct Integrated CHaMP-PIBO Metric Database and Web Application | 12/31/2014 | 12/31/2014 | |
Submit Data Management Content for CY14 | L: 202. BiOp RPA Report for CY 2014 | 07/01/2015 | 07/01/2015 |
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 185 | Periodic Status Reports for BPA | 10/01/2014 | ||||||
B | 119 | Manage and Administer Project | 10/01/2014 | ||||||
C | 160 | Technical Support and Training | 10/01/2014 | ||||||
D | 160 | Operational Support | 10/01/2014 | ||||||
E | 160 | Host and Manage Applications and Elastic Cloud Services | 10/01/2014 | ||||||
F | 160 | General and Operational System Improvements | 10/01/2014 | ||||||
G | 160 | Modeling, Analysis, and Synthesis System Improvements | 10/01/2014 | ||||||
H | 160 | Laptop Data Broker Improvements | 10/01/2014 | ||||||
I | 160 | iOS Data Logger Application Improvements | 10/01/2014 | ||||||
J | 160 | iOS Data Logger Hardware Maintenance | 10/01/2014 | ||||||
K | 160 | Construct Integrated CHaMP-PIBO Metric Database and Web Application | 10/01/2014 | ||||||
L | 202 | BiOp RPA Report for CY 2014 | |||||||
M | 132 | Data Management Progress Report for 2014 Lessons Learned Report | 10/01/2014 |