Province | Subbasin | % |
---|---|---|
Columbia Plateau | Walla Walla | 100.00% |
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Projects identified for out-years | B: 114. Identify and select projects in Walla Walla Basin | 10/31/2015 | 10/30/2015 | |
All project admin activities managed | C: 119. Conduct all management activities | 01/31/2016 | 01/29/2016 | |
Environmental compliance complete | D: 165. Compliance for on-the-ground work | 01/31/2016 | 01/29/2016 | |
Provide technical support through interagency coordination and public forum | E: 122. Provide technical support | 01/31/2016 | 12/31/2015 | |
Fences maintained at full functionality | F: 186. Maintain Fences | 01/31/2016 | 12/31/2015 | |
Attach Progress Report in Pisces | G: 132. Annual Progress Report (1-1-15) to (12-31-15) | 01/31/2016 | ||
Maintain riparian vegetation | H: 198. Maintain riparian vegetation | 01/31/2016 | 12/31/2015 | |
Upload designs, basis of design report, and construction sequence plan | I: 175. Lower Walla Walla Phase Two Design Development | 01/31/2016 | 12/31/2015 | |
Complete environmental compliance | J: 165. Lower Walla Walla Phase Two Environmental Compliance | 01/31/2016 | 11/27/2015 | |
Upload complete Assessment and Action Plan | K: 115. Lower Mill Creek Assessment | 01/31/2016 | 12/31/2015 | |
Habitat improved on mainstem South Fork Walla Walla River | L: 29. Habitat restoration at Kentch, South Fork Walla Walla River | 08/31/2015 | 08/14/2015 | |
Progress Report has been published | P: 132. Submit Progress Report for the period (1-1-14) to (12-31-14) | 03/31/2015 | 03/31/2015 | |
Further advance design of Kentch Project, Phase 2 to be used for 2015 implementation | Q: 175. Kentch Project: Design change relative to BPA technical team input to project | 06/30/2015 | 06/29/2015 | |
Have engineer representative on-site to assure implementation meets approved design | R: 100. Kentch Project: Increased engineering construction oversight as recommended by BPA | 08/31/2015 | 08/14/2015 | |
Remove earthen levee sections/plugs to re-activate historic secondary channels | S: 180. Kentch Project: Reconnect floodplain, perforate historic levee, reactivate archaic channel | 08/31/2015 | 08/14/2015 | |
Improve vegetative components and physical habitat metrics at Kentch restoration site | T: 47. Kentch Project: Enhance vegetative components | 10/31/2015 | 09/25/2015 | |
Modify inlet existing of side channel made in 2011 to enhance flow, reduce risk; salmonid mortality | U: 186. Lampson Project: Side-channel maintenance; re-connect inlet of secondary channel | 09/30/2015 | 08/03/2015 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU |
|
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened) |
|
Trout, Bull (S. confluentus) (Threatened) |
|
Trout, Rainbow (Oncorhynchus mykiss) |
|
Trout, Interior Redband (O. mykiss gairdnerii) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 185 | Periodic Status Reports for BPA | 02/01/2015 | ||||||
B | 114 | Identify and select projects in Walla Walla Basin | 02/01/2015 | ||||||
C | 119 | Conduct all management activities | 02/01/2015 | ||||||
D | 165 | Compliance for on-the-ground work | 02/01/2015 | ||||||
E | 122 | Provide technical support | 02/01/2015 | ||||||
F | 186 | Maintain Fences | 02/01/2015 | ||||||
G | 132 | Annual Progress Report (1-1-15) to (12-31-15) | 02/01/2015 | ||||||
H | 198 | Maintain riparian vegetation | 05/19/2015 | ||||||
I | 175 | Lower Walla Walla Phase Two Design Development | 02/01/2015 | ||||||
J | 165 | Lower Walla Walla Phase Two Environmental Compliance | 02/01/2015 | ||||||
K | 115 | Lower Mill Creek Assessment | 02/01/2015 | ||||||
L | 29 | Habitat restoration at Kentch, South Fork Walla Walla River | 06/01/2015 | ||||||
M | 175 | Complete Design for South Touchet RM 7.5 | 02/01/2015 | ||||||
N | 29 | North Fork Touchet Instream Habitat Restoration RM 8.5 | |||||||
O | 115 | Upper South Fork WW River Assessment and Action Plan | 02/01/2015 | ||||||
P | 132 | Submit Progress Report for the period (1-1-14) to (12-31-14) | 02/01/2015 | ||||||
Q | 175 | Kentch Project: Design change relative to BPA technical team input to project | 06/01/2015 | ||||||
R | 100 | Kentch Project: Increased engineering construction oversight as recommended by BPA | 02/01/2015 | ||||||
S | 180 | Kentch Project: Reconnect floodplain, perforate historic levee, reactivate archaic channel | 06/01/2015 | ||||||
T | 47 | Kentch Project: Enhance vegetative components | 06/01/2015 | ||||||
U | 186 | Lampson Project: Side-channel maintenance; re-connect inlet of secondary channel | 06/01/2015 | ||||||
V | 175 | Lampson Project: Long term design development for side-channel |