Receipt of environmental compliance clearance from BPA. |
A: 165. Complete and/or initiate Environmental Permitting for Project Activities |
|
04/30/2016 |
04/30/2016 |
Receipt of environmental compliance clearance from BPA. |
B: 165. Rock Creek Fish Habitat Enhancement Project EC requirements |
|
04/30/2016 |
04/30/2016 |
All administrative tasks fulfilled with timely quality products |
C: 119. Phase 3 Rock Creek Project Administration |
|
04/30/2016 |
|
Install large wood complexes and habitat boulders to increase habitat complexity and diversity |
D: 29. Install Large Wood Complexes and habitat boulders along Rock Creek |
|
04/30/2016 |
|
Construct meandering stream channel |
E: 30. Construct Rock Creek Restoration Channel |
|
04/30/2016 |
|
Remove draw bottom road |
F: 33. Obliterate draw bottom road along Rock Creek |
|
04/30/2016 |
|
All administrative tasks fulfilled with timely quality products |
G: 119. Assist with managing & admin CREP fencing & planting plans on Rock Creek Project |
|
04/30/2016 |
03/30/2016 |
All administrative tasks fulfilled with timely quality products |
I: 119. Southern Cross Conservation Property Fish Habitat Enhancement Project Administration |
|
04/30/2016 |
04/30/2016 |
All administrative tasks fulfilled with timely quality products |
J: 119. Assist with managing & admin CREP fencing & planting plans on Willow Creek Project |
|
04/30/2016 |
04/30/2016 |
Construct Riparian Conservation Easement Fences |
K: 40. Install Riparian Fences on Cunha Easement along Dark Canyon and Meadow Creeks |
|
04/30/2016 |
|
Construct Riparian and Property Fences |
L: 40. Install Fences on the Southern Cross Conservation Property |
|
04/30/2016 |
|
Plant native trees, shrubs, and grass on the CC43 Southern Cross Project |
M: 47. Plant native trees, shrubs, and grasses along CC44 Project Areas |
|
04/30/2016 |
04/30/2016 |
Conduct Fish Salvage Operations |
N: 28. Conduct Fish Salvage operations on the CC44 Project |
|
04/30/2016 |
08/14/2015 |
Replace undersized culvert on Sheep Creek |
O: 184. Conduct site survey, prepare design and install culvert on Sheep Creek |
|
04/30/2016 |
|
Survey & Design for Limber Creek culverts |
P: 175. Conduct site survey & prepare culvert designs Limber Jim Creek/North Fork Limber Ck |
|
04/30/2016 |
|
Remove culvert on Little Philips Creek |
Q: 184. Remove culvert on Little Phillips Creek and rehabilitate stream |
|
04/30/2016 |
04/30/2016 |
Replace undersized culvert on Graves Creek |
R: 184. Conduct site survey, prepare design and install culvert on Graves Creek |
|
04/30/2016 |
|
Replace undersized culvert on side channel Southern Cross Conservation Property |
S: 184. Install Culvert on the Southern Cross Conservation Property side channel |
|
04/30/2016 |
|
Conduct maintenance on McCoy, Dark Canyon, Meadow, Willow, Rock, Catherine & Wallowa Projects |
T: 186. Maintain instream structures, fences, and off-channel water developments |
|
04/30/2016 |
04/30/2016 |
Maintain vegetation and control weeds on the Willow Creek, CC37, and Southern Cross projects |
U: 198. Maintain Vegetation and Control Weeds on the Willow Creek, CC37, and Southern Cross Projects |
|
04/30/2016 |
04/30/2016 |
Successfully Administer project |
V: 119. Manage and Administer CTUIR GR Subbasin Restoration Project |
|
04/30/2016 |
04/30/2014 |
Complete outreach & education activities |
W: 99. Public Outreach and Education |
|
04/30/2016 |
04/30/2016 |
Conduct ongoing project development and coordination activities |
X: 114. CTUIR Grande Ronde Subbasin Restoration Coordination |
|
04/30/2016 |
04/30/2016 |
BiOp Fish Habitat Project Opportunity Development and Review |
Y: 114. Solicit, review and select BiOp expense & capital projects |
|
04/30/2016 |
04/30/2013 |
Develop project design plan sets. |
Z: 174. Develop project designs and produce plans |
|
04/30/2016 |
04/30/2016 |
Upload 2015 Annual Report |
AA: 132. FY2015 Annual Report - May 2015 - April 2016 |
|
04/30/2016 |
|