Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 69226: 2007-224-00 CAP OKANOGAN SUBBASIN HABITAT IMPL
Project Number:
Title:
Okanogan Subbasin Habitat Implementation Program (OSHIP)
Stage:
Complete
Area:
Province Subbasin %
Columbia Cascade Okanogan 100.00%
Contract Number:
69226
Contract Title:
2007-224-00 CAP OKANOGAN SUBBASIN HABITAT IMPL
Contract Continuation:
Previous: Next:
64895: 2007-224-00 CAP IMPLEMENT OKANOGAN SUBBASIN PLAN
Contract Status:
Closed
Contract Description:
The goal of this project is to implement the Okanogan Sub-Basin Plan.  The Sub-Basin Plan was developed to describe in detail the current state of the Okanogan Basin and then describe what are the limiting factors for anadromous salmonid production and survival.  Implementing the Sub-Basin Plan will require a sequenced set of key habitat restoration and protective actions.  The Okanogan River, Similkameen River and associated tributaries have several factors that limit salmonid production and rearing.  These factors include but are not limited to:  temperature, flow, habitat complexity, barriers, sedimentation and substrate.  We will be addressing limiting factors throughout the Okanogan River Basin, (main-stem and tributary portions)  by implementing a list of stream habitat restoration projects and developing feasibility plans on future projects.  This contract is for implementation of Capital projects, primarily diversion screen installations and upgrades to improve fish passage and a pump upgrade to improve irrigation efficiency.
Account Type(s):
Capital
Contract Start Date:
07/01/2015
Contract End Date:
06/30/2016
Current Contract Value:
$206,612
Expenditures:
$206,612

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Applicable permits and other environmental clearances received A: 165. Environmental Compliance 04/30/2016 04/30/2016
All administrative tasks fulfilled with timely quality products B: 119. Manage and Administer Project 06/30/2016 06/30/2016
Johnson Creek culvert replacement D: 85. Johnson Creek Culvert replacement 11/30/2015
Loup Loup Creek Flow, turbidity and snow pack monitoring E: 148. Loup Loup Creek watershed monitoring 11/30/2015 11/30/2015

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 1 instance of WE 203 Install Water Conservation Measure
  • 2 instances of WE 85 Remove/Breach Fish Passage Barrier
  • 1 instance of WE 148 Install Flow Measuring Device

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Environmental Compliance 05/01/2015
B 119 Manage and Administer Project 05/01/2015
C 85 Johnson Creek Gabion removal
D 85 Johnson Creek Culvert replacement
E 148 Loup Loup Creek watershed monitoring 07/01/2015
F 203 Johnson Creek irrigation canal lining
G 185 Periodic Status Reports for BPA 05/01/2015
H 132 Annual Reporting for this project is done under the EXP contract 07/01/2015