Contract 70502: 1992-061-06 EXP ALBENI FALLS WL COUER D'ALENE
Project Number:
Title:
Albeni Falls Wildlife Mitigation-Coeur D'Alene Tribe
Stage:
Implementation
Area:
Province Subbasin %
Intermountain Pend Oreille 100.00%
Contract Number:
70502
Contract Title:
1992-061-06 EXP ALBENI FALLS WL COUER D'ALENE
Contract Continuation:
Previous: Next:
66783: 1992-061-06 EXP ALBENI FALLS WL COUER D'ALENE
  • 74152: 1992-061-06 EXP ALBENI FALLS WLDLF MITIGATION/COUER D'ALENE
Contract Status:
Closed
Contract Description:
Tribes and Agencies that implement the mitigation for Albeni Falls dam due to the construction and inundation are: Idaho Department of Fish and Game, the Kalispel Tribe, the Coeur D'Alene Tribe, the Kootenai Tribe of Idaho and the U. S. Army Corps of Engineers. Once the loss assessments were completed, these agencies and tribes worked collectively to protect, enhance and mitigate wildlife impacts in the Coeur d' Alene and Pend Oreille Subbasins. This contract provides for the enhancement, operations and maintenance, construction and implementation on mitigation properties managed by the Coeur d' Alene Tribe.  In addition, this contract provides the funding for the Tribe to conduct planning and design activities for the potential acquisition of mitigation properties.  Currently the Tribe owns and manages approximately 3,400 acres under the Albeni Falls Wildlife Mitigation Project.

To date, due to budget limitations, implementation has focused mainly on operation and maintenance activities and limited enhancement work (wetland creation, noxious weed control).
Account Type(s):
Expense
Contract Start Date:
10/01/2015
Contract End Date:
09/30/2016
Current Contract Value:
$382,560
Expenditures:
$382,560

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Cameron Heusser Coeur D'Alene Tribe No Supervisor cheusser@cdatribe-nsn.gov (208) 686-5521
Rosemary Mazaika Bonneville Power Administration No Interested Party rxmazaika@bpa.gov (503) 230-5869
Anders Mikkelsen Coeur D'Alene Tribe Yes Contract Manager amikkelsen@cdatribe-nsn.gov (208) 686-8902
Jennifer Snyder Bonneville Power Administration Yes Env. Compliance Lead jasnyder@bpa.gov (503) 230-4187
Chelsea Waddell Bonneville Power Administration No Interested Party cdwaddell@bpa.gov (503) 230-5184
Virgil Watts III Bonneville Power Administration Yes COR vlwatts@bpa.gov (503) 230-4625
Dorothy Welch Bonneville Power Administration Yes F&W Approver dwwelch@bpa.gov (503) 230-5479
Karen Wolfe Bonneville Power Administration Yes Contracting Officer ktwolfe@bpa.gov (503) 230-3448
Elham Zolmajd-Haghighi Bonneville Power Administration No CO Assistant ezolmajd-haghighi@bpa.gov (503) 230-7414


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Environmental Compliance B: 165. NEPA checklist/Compliance 09/30/2016 09/30/2016
Regional Wildlife Program Document Review C: 122. Regional Workgroup Management Plan and Acquisition Review 09/30/2016 09/30/2016
Management Plan Development and Revision D: 174. Produce management plans 09/30/2016 09/30/2016
Debris Removal on Habitat Properties E: 27. Elkhorn Ranch Property Debris Removal 09/30/2016 09/30/2016
Debris Removal on Habitat Properties F: 27. St. Joe River Property Debris Removal 09/30/2016 09/30/2016
Debris Removal on Habitat Properties G: 27. Hepton Lake Property Debris Removal. 09/30/2016 09/30/2016
Maintain perimeter fence and gates on all properties H: 186. Maintain Fence line and Structures 09/30/2016 09/30/2016
Investigate to trespass on all mitigation sites I: 26. Investigate trespass on mitigation properties 09/30/2016 09/30/2016
Vegetation Planting on The Goose Haven Lake Property J: 47. Plant vegetation to restore native habitats within the Goose Haven Lake Property 09/30/2016 09/30/2016
Albeni Falls Project Management K: 119. Albeni Falls Wildlife Mitigation Program 09/30/2016 09/30/2016
Install and maintain boundary signs L: 188. Install and maintain boundary signs on all mitigation properties 09/30/2016 09/30/2016
Fee-title acquisition. M: 172. Conduct Pre-Acquisition Activities for Albeni Falls Mitigation Projects 09/30/2016 09/30/2016
Herbicide application on Hepton Lake Property. N: 198. Noxious Weed Control: Hepton Lake 09/30/2016 09/30/2016
Herbicide application on St. Joe mitigation property O: 198. Noxious Weed Control: St. Joe River 09/30/2016 09/30/2016
Herbicide application on Elkhorn Ranch mitigation property. P: 198. Noxious Weed Control: Elkhorn Ranch 09/30/2016 09/30/2016
Herbicide application on Goose Haven Lake mitigation property. Q: 198. Noxious Weed Control: Goose Haven Lake 09/30/2016 09/30/2016
Herbicide application on Windy Bay mitigation property. R: 198. Noxious Weed Control: Windy Bay 09/30/2016 09/30/2016
Herbicide application on Cougar Creek mitigation property . S: 198. Noxious Weed Control: Cougar Creek 09/30/2016 09/30/2016
Bank stabilization designs/assessment on the St. Joe River Mitigation property U: 175. St. Joe River Bank Stabilization 09/30/2016 09/30/2016

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Wildlife
  • 6 instances of WE 198 Maintain Vegetation
  • 1 instance of WE 26 Investigate Trespass
  • 3 instances of WE 27 Remove Debris
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 10/01/2015
B 165 NEPA checklist/Compliance 10/01/2015
C 122 Regional Workgroup Management Plan and Acquisition Review 10/01/2015
D 174 Produce management plans 10/01/2015
E 27 Elkhorn Ranch Property Debris Removal 10/01/2015
F 27 St. Joe River Property Debris Removal 10/01/2015
G 27 Hepton Lake Property Debris Removal. 10/01/2015
H 186 Maintain Fence line and Structures 10/01/2015
I 26 Investigate trespass on mitigation properties 10/01/2015
J 47 Plant vegetation to restore native habitats within the Goose Haven Lake Property 10/01/2015
K 119 Albeni Falls Wildlife Mitigation Program 10/01/2015
L 188 Install and maintain boundary signs on all mitigation properties 10/01/2015
M 172 Conduct Pre-Acquisition Activities for Albeni Falls Mitigation Projects 10/01/2015
N 198 Noxious Weed Control: Hepton Lake 11/12/2015
O 198 Noxious Weed Control: St. Joe River 11/12/2015
P 198 Noxious Weed Control: Elkhorn Ranch 11/12/2015
Q 198 Noxious Weed Control: Goose Haven Lake 11/12/2015
R 198 Noxious Weed Control: Windy Bay 11/12/2015
S 198 Noxious Weed Control: Cougar Creek 11/12/2015
T 132 Collect and Maintain Project Data 10/01/2015
U 175 St. Joe River Bank Stabilization 10/01/2015