Obtain all necessary permits. Work with BPA EC lead, Invasive species management and prevention |
A: 165. Environmental Compliance |
|
05/29/2016 |
05/27/2016 |
All administrative tasks fulfilled with timely quality products |
B: 119. Administrative Oversight of the Chief Joseph Hatchery M&E Program |
|
04/30/2017 |
|
A dataset for rotary screw trap operations on the Okanogan River. |
D: 157. Monitor Juvenile Chinook Emigration With Rotary Screw Trap |
|
01/31/2017 |
03/24/2017 |
Present juvenile outmigration results at the APR and update status and trends in annual report |
E: 162. Analyze Juvenile Chinook Emigration |
|
04/30/2017 |
03/22/2017 |
Upload PIT tag files to PTAGIS |
F: 158. PIT Tag Subyearling NOR Juvenile Chinook |
|
08/14/2016 |
07/07/2016 |
Update key assumptions in ISIT, presentation at APR and section of annual report. |
G: 162. Analyze PIT Tag Data |
|
04/30/2017 |
04/20/2017 |
Produce datasets, present at the APR and a section of the annual report for the weir |
H: 157. Okanogan River Temporary Weir Operations |
|
04/30/2017 |
03/24/2017 |
Present results at the APR and generate a section of the annual report for weir monitoring. |
I: 162. Analyze Results of Weir Monitoring |
|
04/30/2017 |
03/22/2017 |
Produce datasets for spawning ground surveys |
J: 157. Conduct Spawning Ground Surveys for Summer/Fall Chinook |
|
04/30/2017 |
03/24/2017 |
Spawning ground survey summary and analysis for APR presentations, ISIT, and the annual report |
K: 162. Analyze Data for Summer/Fall Chinook Spawning Ground Surveys |
|
04/30/2017 |
03/24/2017 |
Produce accessible, error-checked datasets for eDNA |
L: 157. Collect Water for eDNA |
|
04/30/2017 |
03/24/2017 |
APR presentation and section of the annual report |
M: 162. Analysis of Water Samples for eDNA |
|
04/30/2017 |
03/23/2017 |
Tissue samples from hatchery broodstock and archived with CRITFC's PBT program |
N: 157. Collect Tissue Samples for PBT |
|
12/15/2016 |
12/05/2016 |
Otolth samples from hatchery broodstock and sent to WDFW otolith lab |
O: 157. Collect Otolith Samples from CJH Summer/Fall Broodstock |
|
11/30/2016 |
11/14/2016 |
Scale samples from hatchery broodstock and sent to WDFW scale lab |
P: 157. Collect Scales from CJH Spring and Summer/Fall Broodstock |
|
11/30/2016 |
11/30/2016 |
Produce error-checked dataset and archived in CJH database |
Q: 157. Process CWT Snouts at CJH Lab |
|
03/31/2017 |
03/31/2017 |
Produce accessible, error-checked datasets for tribal harvest of summer/fall Chinook |
R: 157. Estimate Tribal Harvest for Summer/Fall Chinook |
|
02/28/2017 |
12/13/2016 |
Data summary and analysis input to ISIT, presented at APR and a section of the annual report |
S: 162. Retrieve and Analyze CWT Information |
|
04/30/2017 |
03/31/2017 |
Maintenance and enhancement of the database, reporting tools and desktop applications |
T: 160. Database and Module Maintenance and Enhancement-Summit (contractor) |
|
04/30/2017 |
02/28/2017 |
CJHP Annual Program Review Tool Updates and Maintenance |
U: 162. Assimilate and Analyze ISIT Input Parameters |
|
04/30/2017 |
04/20/2017 |
2017 Annual Program Review (APR) and section of the annual report |
V: 161. Annual Program Review |
|
04/30/2017 |
03/24/2017 |
Completed 2015 Annual Report |
W: 132. 2015 Annual Report- Finalize Annual Report from Previous Contract |
|
04/30/2017 |
|
Complete on line BiOp report for calendar year 2016 |
Y: 202. Biop RPA Reporting |
|
04/14/2017 |
04/14/2017 |