Province | Subbasin | % |
---|---|---|
Mountain Snake | Salmon | 100.00% |
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Complete all required EC and obtain site specific permits prior to implementation of project | A: 165. Environmental Compliance | 02/15/2017 | 03/22/2017 | |
Construction Management Complete | B: 100. Construction management for West Fork Yankee Fork Phase I restoration project | 03/31/2017 | 12/30/2016 | |
As built record drawings submitted to BPA. | C: 29. Increase complexity on West Fork Yankee Fork Phase I restoration project | 01/31/2017 | 10/21/2016 | |
Obtain and stage trees and stage spawning gravel | D: 29. Obtain and stage trees and stage spawning gravel | 09/30/2016 | 07/29/2016 | |
As Built Map of Channel | E: 30. Construct new channel | 01/31/2017 | 10/21/2016 | |
Create, Restore, and Enhance wetlands | F: 181. Create, Restore, and Enhance wetlands | 11/01/2016 | 09/14/2016 | |
As built record drawings submitted. | G: 55. Construction Site Best Management Practices | 01/31/2017 | 12/30/2016 | |
Enhance Floodplain | H: 180. Enhance Floodplain | 11/30/2016 | 09/30/2016 | |
Remove mine tailings | I: 52. Remove Mine Tailings | 11/01/2016 | 09/14/2016 | |
Plant vegetation at West Fork Yankee Fork Phase II restoration project | J: 47. Plant vegetation at West Fork Yankee Fork Phase I restoration project | 12/15/2016 | 12/15/2016 | |
All administrative tasks fulfilled with timely quality products | K: 119. Manage and Administer Project | 05/31/2017 | 05/31/2017 | |
Completed Annual Report | M: 132. Submit Progress Report for the period June 2016 thru May 2017 | 05/31/2017 | 05/18/2017 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | Environmental Compliance | 06/01/2016 | ||||||
B | 100 | Construction management for West Fork Yankee Fork Phase I restoration project | 06/01/2016 | ||||||
C | 29 | Increase complexity on West Fork Yankee Fork Phase I restoration project | 06/01/2016 | ||||||
D | 29 | Obtain and stage trees and stage spawning gravel | 06/01/2016 | ||||||
E | 30 | Construct new channel | 06/01/2016 | ||||||
F | 181 | Create, Restore, and Enhance wetlands | 06/01/2016 | ||||||
G | 55 | Construction Site Best Management Practices | 06/01/2016 | ||||||
H | 180 | Enhance Floodplain | 06/01/2016 | ||||||
I | 52 | Remove Mine Tailings | 06/01/2016 | ||||||
J | 47 | Plant vegetation at West Fork Yankee Fork Phase I restoration project | 06/01/2016 | ||||||
K | 119 | Manage and Administer Project | 06/01/2016 | ||||||
L | 185 | Periodic Status Reports for BPA | 06/01/2016 | ||||||
M | 132 | Submit Progress Report for the period June 2016 thru May 2017 | 06/01/2016 |