Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 73354 REL 23: 2008-503-00 EXP STUDIES LIMITING ABUND OKAN/WENAT SOCKEYE
Project Number:
Title:
Studies into Factors Limiting the Abundance of Okanagan and Wenatchee Sockeye Salmon
Stage:
Implementation
Area:
Province Subbasin %
Columbia Cascade Entiat 1.00%
Methow 1.00%
Okanogan 49.00%
Wenatchee 49.00%
Contract Number:
73354 REL 23
Contract Title:
2008-503-00 EXP STUDIES LIMITING ABUND OKAN/WENAT SOCKEYE
Contract Continuation:
Previous: Next:
73354 REL 3: 2008-503-00 EXP MID-COLUMBIA SOCKEYE STUDIES
  • 73354 REL 42: 2008-503-00 EXP STUDIES LIMITING ABUND OKAN/WENAT SOCKEYE
Contract Status:
Closed
Contract Description:
This project seeks to expand our knowledge on the factors limiting production of Okanogan and Wenatchee sockeye salmon stocks. A primary factor affecting the Okanogan stock is believed to be survival upstream of Wells Dam. To quantify this mortality, this project has funded PIT and acoustic tagging of sockeye salmon at Wells Dam with additional sockeye PIT tagged at Bonneville Dam as part of the Upstream Migration Timing Accords project).
The project has also funded PIT tag antenna arrays at Zosel (ZSL at PTAGIS), McIntyre, and Skaha (SKA) dams as well as an instream arrays at Oliver, BC (OKC) and Penticton, BC (OKP).

Acoustic tagging was conducted at Wells Dam since this project commenced through 2016 when it was dropped due to the expense of this tagging and the fact that recent PIT tag array installations, many funded by this project, provide much of the passage/survival data provided by acoustic tags.  One place where acoustic tagging was useful was to determine survival to the North Basin of Osoyoos Lake which is a cold water refuge for migrating sockeye salmon.  This is located immediately upstream of the Osoyoos Narrows in Osoyoos, BC.  These narrows could possibly be monitored with PIT tag antennas if we can determine where in the narrows the fish pass, thus we are again going to seek to use DIDSON to determine the feasibility of so monitoring this area.  Efforts in both 2017 and 2018 were adversely affected by high flows so we will try again in 2019.  

We will continue to PIT tag adults at Wells Dam to augment the number of PIT tagged sockeye in the Okanagan Basin used for estimating survival through our PIT tag network in the basin.  (Some sampling and tagging may also be conducted at Priest Rapids Dam if the Bonneville trap is shut down due to high temperatures as was the case in 2015.)  This data may allow for the development of different river management actions to reduce this mortality.  It is hoped that, depending on where mortality is occurred, better flow management techniques to optimize adult survival can be developed. The PIT tag network we develop as part of this project may also improve data on steelhead and Chinook use of the Canadian portion of the Okanogan Basin.

This project also seeks to standardize smolt abundance estimation methodologies between the two stocks by conducting annual hydroacoustic surveys of Lake Wenatchee to compare with those being conducted in Osoyoos  Lake.  Costs of the Wenatchee acoustic surveys are shared with DFO, while Osoyoos and Skaha lake surveys are funded by DFO, the ONA, and Grant and Chelan PUDs.  

This project is also annually supports PIT tagging of juvenile Okanagan sockeye in 2019 to assess assess downstream mortality of these fish through the Okanagan River and the Columbia Basin hydrosystem.  Additional funding for the PIT tagging is provided by the Fish Passage Center through the Comparative Survival Study, DFO, and Grant and Chelan PUDs.  

Much of the work for this contract will be conducted by contractors and subrecipients:

Contractor/subrecipient      Task

Yakama Nation                  B, D,G,
Okanagan Nation              B, E, F, G, H, I, J, K, L, M, N, O, P
Biomark (or other qualified contractor):  F, I (pre-loading PIT tags from CSS)
Account Type(s):
Expense
Contract Start Date:
05/01/2019
Contract End Date:
04/30/2020
Current Contract Value:
$226,186
Expenditures:
$226,186

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Brenda Aguirre Bonneville Power Administration Yes Env. Compliance Lead baguirre@bpa.gov (503) 230-5928
Ryan Benson Columbia River Inter-Tribal Fish Commission (CRITFC) No Interested Party rbenson@syilx.org (250) 490-9779
Victoria Bohlen Bonneville Power Administration Yes COR vlbohlen@bpa.gov (503) 230-3506
Richard Bussanich Okanagan Nation Alliance No Interested Party rbussanich@syilx.org (250) 490-9779
Skyeler Folks Okanagan Nation Alliance No Interested Party sfolks@syilx.org (250) 490-9779
Jeffrey Fryer Columbia River Inter-Tribal Fish Commission (CRITFC) Yes Contract Manager fryj@critfc.org (503) 731-1266
Desmond Gelman Bonneville Power Administration No CO Assistant dxgelman@bpa.gov (503) 230-4960
Christine Golightly Columbia River Inter-Tribal Fish Commission (CRITFC) No Interested Party golc@critfc.org (503) 731-1288
Douglas Hatch Columbia River Inter-Tribal Fish Commission (CRITFC) No Supervisor hatd@critfc.org (503) 731-1263
Kim Hyatt Department of Fisheries and Oceans Canada No Interested Party kim.hyatt@dfo-mpo.gc.ca (250) 756-7217
David Kaplowe Bonneville Power Administration Yes F&W Approver djkaplowe@bpa.gov (503) 230-5365
Denise Kelsey Columbia River Inter-Tribal Fish Commission (CRITFC) No Interested Party keld@critfc.org (503) 731-1280
Zachary Penney Columbia River Inter-Tribal Fish Commission (CRITFC) No Interested Party zpenney@critfc.org (503) 731-1301
Christine Petersen Bonneville Power Administration No Interested Party chpetersen@bpa.gov (503) 230-4695
Chris Roe Columbia River Inter-Tribal Fish Commission (CRITFC) No Interested Party chris.roe@critfc.org (503) 731-1274
Dan Selbie Department of Fisheries and Oceans Canada No Interested Party daniel.selbie@dfo-mpo.gc.ca (604) 824-4702
John Whiteaker Columbia River Inter-Tribal Fish Commission (CRITFC) No Interested Party whij@critfc.org (503) 238-3562
Elham Zolmajd-Haghighi Bonneville Power Administration Yes Contracting Officer ezolmajd-haghighi@bpa.gov (503) 230-7414


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Ensure environmental compliance requirements are completed. B: 165. Complete environmental compliance requirements 04/30/2020 04/30/2020
Effective implementation management and timely contract administration C: 119. Project administration 04/30/2020 04/30/2020
Wells Dam PIT tagging completed D: 158. Tag adult sockeye salmon at Wells Dam 11/30/2019 09/27/2019
Sockeye migration mortality and timing analysis completed E: 162. Adult Sockeye migration mortality and timing (PIT tag data) 04/30/2020 04/30/2020
Collect PIT tag detection data F: 157. Collect PIT tag detection data from PTAGIS from Accords project funded sites (OKC, SKA, ZSL, OKC, OKP, McIntyre) 04/30/2020 04/30/2020
Wenatchee and Okanagan lake nerka abundance and limnology data G: 157. Conduct acoustic trawl surveys and collect limnology data and nerka samples 04/30/2020 04/30/2020
Over-winter smolt abundance of Okanogan and Wenatchee sockeye salmon data compared H: 162. Compare Wenatchee and Osoyoos Lake ATS and limnology data 04/30/2020 04/30/2020
PIT tag approximately 10,000 juvenile sockeye salmon in March-April 2020 I: 158. PIT tag juvenile Osoyoos and Skaha Lake sockeye salmon 04/30/2020 04/30/2020
Analysis of Okanagan juvenile PIT tag data J: 162. Analyze juvenile PIT tag data 04/30/2020 04/30/2020
Collection of data from DIDSON K: 157. Deploy Didson at Osoyoos Lake Highway 3 bridge to determine distribution of adult sockeye salmon 04/30/2020
Analyze Didson to estimate spatial distribution of sockeye passing under the Osoyoos Lake bridge L: 162. Analysis of Didson data collected at Highway 3 bridge over Osoyoos Lake 04/30/2020
Report results M: 161. Share project information 04/30/2020 04/30/2020
2018 progress report N: 132. Submit Progress Report for data collected January 2018 to December 2018 04/30/2020 04/30/2020

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Sockeye (Oncorhynchus nerka) - All Populations
  • 1 instance of WE 161 Disseminate Raw/Summary Data and Results
Sockeye (O. nerka) - Lake Wenatchee ESU
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 162 Analyze/Interpret Data
Sockeye (O. nerka) - Okanogan River ESU
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 2 instances of WE 158 Mark/Tag Animals
  • 4 instances of WE 162 Analyze/Interpret Data
Sockeye (O. nerka) - Snake River ESU (Endangered)
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 05/01/2019
B 165 Complete environmental compliance requirements 05/01/2019
C 119 Project administration 05/01/2019
D 158 Tag adult sockeye salmon at Wells Dam 02/20/2019
E 162 Adult Sockeye migration mortality and timing (PIT tag data) 05/01/2019
F 157 Collect PIT tag detection data from PTAGIS from Accords project funded sites (OKC, SKA, ZSL, OKC, OKP, McIntyre) 02/12/2019
G 157 Conduct acoustic trawl surveys and collect limnology data and nerka samples 02/12/2019
H 162 Compare Wenatchee and Osoyoos Lake ATS and limnology data 05/01/2019
I 158 PIT tag juvenile Osoyoos and Skaha Lake sockeye salmon 02/12/2019
J 162 Analyze juvenile PIT tag data 05/01/2019
K 157 Deploy Didson at Osoyoos Lake Highway 3 bridge to determine distribution of adult sockeye salmon 02/12/2019
L 162 Analysis of Didson data collected at Highway 3 bridge over Osoyoos Lake 05/01/2019
M 161 Share project information 05/01/2019
N 132 Submit Progress Report for data collected January 2018 to December 2018 05/01/2019