Documentation and assistance to support BPA's Environmental Compliance Group. |
A: 165. Obtain Permits and submit copies to BPA NEPA group |
|
12/31/2017 |
12/31/2017 |
2017 Annual Operation Plan |
B: 174. Produce 2017 Annual Operating Plan |
|
12/31/2017 |
03/22/2017 |
Acclimate BY 2015 Upper Grande Ronde River spring chinook |
C: 176. Acclimate BY 2015 juvenile Upper Grande River River spring chinook |
|
04/15/2017 |
04/14/2017 |
Collect and Spawn BY 2017 Upper Grande Ronde spring chinook |
D: 176. Collect and Spawn BY 2017 Upper Grande Ronde River spring chinook |
|
09/20/2017 |
09/11/2017 |
Acclimate BY 2015 Catherine Creek spring chinook |
E: 176. Acclimate BY 2015 juvenile Catherine Creek spring chinook |
|
04/15/2017 |
04/14/2017 |
Collect and Spawn BY 2017 Catherine Creek spring chinook |
F: 176. Collect and Spawn BY 2017 Catherine Creek spring chinook |
|
09/20/2017 |
09/11/2017 |
Environmental conditions, fish numbers, fish condition, PIT tag information, fish spawned |
G: 157. Collection of data at facilities |
|
12/31/2017 |
12/31/2017 |
Data Analysis of Current Data Collection For Management Decisions |
H: 162. Data Analysis For Management |
|
12/31/2017 |
12/31/2017 |
Maintain Upper Grande Ronde facilities |
I: 61. Upper Grande Ronde Facility Maintenance |
|
12/31/2017 |
12/31/2017 |
Maintain Catherine Creek facilities |
J: 61. Catherine Creek Facility Maintenance |
|
12/31/2017 |
12/31/2017 |
Maintain La Grande Shop/Office. |
K: 61. La Grande Office/Shop Maintenance |
|
12/31/2017 |
12/31/2017 |
Send weekly reports to co-managers during periods of acclimation and adult facility operation |
L: 161. Weekly Facility Activities Reports |
|
09/30/2017 |
09/12/2017 |
Attend meetings for project implementation |
M: 191. Coordination of Project Activities |
|
12/31/2017 |
12/31/2017 |
Manage and Administer project |
N: 119. Annual Budget Package/Accrual Reports/Provincial Review |
|
10/01/2017 |
10/01/2017 |
Upload 2016 Annual Report |
O: 132. Submit 2016 Annual Report - January 2016 - December 2016 |
|
03/15/2017 |
01/26/2017 |
Grande Ronde Supplementation RPA/BiOp data submission to M&E contract manager |
P: 202. BiOp RPA Data for CY 2016 Report |
|
02/28/2017 |
02/28/2017 |