Contract 73982 REL 35: 1996-046-01 EXP WALLA WALLA BASIN FISH HABITAT ENHANCEMENT
Project Number:
Title:
Walla Walla River Basin Fish Habitat Enhancement
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Walla Walla 100.00%
Contract Number:
73982 REL 35
Contract Title:
1996-046-01 EXP WALLA WALLA BASIN FISH HABITAT ENHANCEMENT
Contract Continuation:
Previous: Next:
73982 REL 12: 1996-046-01 EXP WALLA WALLA BASIN: ENHANCE & RESTORE FISH HABITAT
  • 73982 REL 61: 1996-046-01 EXP WALLA WALLA BASIN FISH HABITAT ENHANCEMENT
Contract Status:
Closed
Contract Description:
The CTUIR Walla Walla River Basin Fish Habitat Enhancement Project, initiated in 1996, is an ongoing effort to monitor, protect, enhance, and restore the natural form and function of rivers, floodplains, and native fish habitat. Restoration project location and selection criteria is derived from various managerial guidance documents and based upon identification and addressing factors limiting salmonid production. The Project is responsible for improving physical habitat conditions for ESA-Listed salmonid species.  

Major tasks to be completed by the project in this funding cycle include:  

2018 Project Focus and Deliverable Summary;

1 South Fork Walla Walla River Hutchison Project Final Designs, Imp Plan, Staking, Implementation, Oversight:                                                                             Restoration in Chinook Salmon and Bull Trout priority reach based on designs initiated in FY17. Restoring proper riverine function and process via reinvigoration of the floodplain and instream complexity.
              
2 Walla Walla River Nursery Bridge Project Phase 2 Final & Phase 3 30% designs, Imp & Mon. Plans, Staking, Oversight, As-Built, Implementation Plan:               FY 18 restoration activities focus upon reducing annual, long-term riverbed/channel disturbance and dysfunction to improve passage conditions at Eastside Ditch and fishway infrastructure based on FY 17 designs.

3              North Fork Walla Walla River Confluence Final Design:                                                                                                                                                                  Develop designs for priority reach established for ESA-Listed salmonid species. Project involves reactivating floodplain, improving passage and complexity, and restoring river into historic channel.

4              North Fork Touchet River RM 1, Warren Project, Design Completion                                                                                                                                             Advance designs that were initiated in FY 17 and take to completion. Implement phase of project if permitting entities and process is successfully navigated. Use of grant dollars expected to fund implementation in FY 19.    

5              NF Touchet River RM 3, Wolf Fork Project Final Design Development                                                                                                                                           Advance designs that were initiated in FY 17 to completion stage. Formulate implementation plan in preparation for FY19 implementation.  

6              Couse Creek Final Design Development. Provide technical review and input throughout design process                                                                                       Partnership with Lead sponsor, WWBWC to work on a collaborative approach to improve passage, increase stream length and complexity, reduce erosion and negative impacts at the confluence with the Walla River.
Account Type(s):
Expense
Contract Start Date:
01/01/2018
Contract End Date:
12/31/2018
Current Contract Value:
$1,400,051
Expenditures:
$1,400,051

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Julie Burke Umatilla Confederated Tribes (CTUIR) Yes Administrative Contact julieburke@ctuir.org (541) 429-7292
Alexandra Fitzgerald Umatilla Confederated Tribes (CTUIR) No Technical Contact alexandrafitzgerald@ctuir.org (541) 429-7549
Jonathan Goodman Bonneville Power Administration No Interested Party jdgoodman@bpa.gov (503) 230-4764
Ethan Green Umatilla Confederated Tribes (CTUIR) Yes Contract Manager ethangreen@ctuir.org (541) 429-7555
Heidi Haak Bonneville Power Administration No Interested Party hlhaak@bpa.gov (541) 922-6856
Eric Hoverson Umatilla Confederated Tribes (CTUIR) Yes Contract Manager erichoverson@ctuir.org (541) 429-7555
Gary James Umatilla Confederated Tribes (CTUIR) No Supervisor garyjames@ctuir.org (541) 429-7285
Travis Kessler Bonneville Power Administration No Interested Party tdkessler@bpa.gov (503) 230-5468
Michael Lambert Umatilla Confederated Tribes (CTUIR) Yes Supervisor mikelambert@ctuir.org (541) 429-7240
Andre L'Heureux Bonneville Power Administration No Interested Party allheureux@bpa.gov (503) 230-4482
Russell Marlowe Umatilla Confederated Tribes (CTUIR) Yes Technical Contact russellmarlow@ctuir.org (541) 429-7556
Claire McClory Bonneville Power Administration Yes Env. Compliance Lead cdmcclory@bpa.gov (503) 230-5922
Gerald Middel Umatilla Confederated Tribes (CTUIR) Yes Technical Contact geraldmiddel@ctuir.org (541) 969-9925
Christopher Roper Bonneville Power Administration No CO Assistant cproper@bpa.gov (503) 230-3514
Dana Sheedy Umatilla Confederated Tribes (CTUIR) Yes Technical Contact danasheedy@ctuir.org (541) 429-7549
Tybee Sheidler Bonneville Power Administration No CO Assistant tasheidler@bpa.gov (503) 230-3820
John Skidmore Bonneville Power Administration Yes F&W Approver jtskidmore@bpa.gov (503) 230-5494
Michelle Thompson Umatilla Confederated Tribes (CTUIR) No Administrative Contact michellethompson@ctuir.org (541) 429-7227
Jesse Wilson Bonneville Power Administration Yes COR jcwilson@bpa.gov (503) 230-4506
Elham Zolmajd-Haghighi Bonneville Power Administration Yes Contracting Officer ezolmajd-haghighi@bpa.gov (503) 230-7414


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Project administration activities managed effectively B: 119. Conduct all project management activities 12/31/2018 12/31/2018
Environmental compliance C: 165. Produce environmental compliance for on the ground work 12/31/2018 06/20/2018
Projects identified and prioritize; short and long term D: 114. Identify and select habitat projects that benefit salmonids 12/31/2018 12/31/2018
Provide technical support through interagency coordination and public forum E: 122. Provide technical support on related resource topics, specifically Couse Creek partnership with WWBWC 12/31/2018 12/31/2018
Improve riparian vegetative components and physical habitat metrics F: 47. Enhance riparian vegetative components at restoration project sites 12/31/2018 12/14/2018
Upload designs, basis of design report, and construction sequence plan G: 175. Walla Walla River, Nursery Bridge Design 12/31/2018
Produce and review design report, construction site plan, and/or cost-estimate H: 175. North Touchet Rm 1.3-3.3 Restoration Designs 12/31/2018 03/09/2018
Develop100% Final restoration designs for NF Touchet RM 3.3-Wolf Fork Reach I: 175. North Fork Touchet RM 3.3-Wolf Fork Restoration Designs 12/31/2018 09/27/2018
Produce alternative designs and analysis for potential POD change for Eastside Ditch, within Nursery Bridge New/East Fish Ladder Infrastructure K: 175. Walla Walla River, Eastside Ditch POV Design Change 12/31/2018 03/09/2018
Upload designs, basis of design report, and construction sequence plan L: 175. South Fork Walla Walla River, Hutchison Design 06/30/2018 06/15/2018
Approach historic riverine conditions and function M: 29. South Fork Walla Walla River Hutchison Project Implementation 09/30/2018 09/30/2018
Create secondary channels with associated habitat improvements for salmonids N: 30. South Fork Walla Walla River, Hutchison Project implementation 08/15/2018 08/15/2018
Stockpiled material removed P: 201. CCR-41135 Remove excess material from Hutchinson 12/31/2018 10/31/2018

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 114 Identify and Select Projects
  • 6 instances of WE 175 Produce Design
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 114 Identify and Select Projects
  • 6 instances of WE 175 Produce Design
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 01/01/2018
B 119 Conduct all project management activities 01/01/2018
C 165 Produce environmental compliance for on the ground work 01/01/2018
D 114 Identify and select habitat projects that benefit salmonids 01/01/2018
E 122 Provide technical support on related resource topics, specifically Couse Creek partnership with WWBWC 01/01/2018
F 47 Enhance riparian vegetative components at restoration project sites 10/16/2018
G 175 Walla Walla River, Nursery Bridge Design 07/06/2018
H 175 North Touchet Rm 1.3-3.3 Restoration Designs 07/06/2018
I 175 North Fork Touchet RM 3.3-Wolf Fork Restoration Designs 07/06/2018
J 175 North Fork Walla Walla River Confluence Design 07/06/2018
K 175 Walla Walla River, Eastside Ditch POV Design Change 07/06/2018
L 175 South Fork Walla Walla River, Hutchison Design 05/01/2018
M 29 South Fork Walla Walla River Hutchison Project Implementation 06/28/2018
N 30 South Fork Walla Walla River, Hutchison Project implementation 07/12/2018
O 132 Annual Progress Report (1/1/18) to (12/31/18) 01/01/2018
P 201 CCR-41135 Remove excess material from Hutchinson 08/30/2018