Province | Subbasin | % |
---|---|---|
Blue Mountain | Grande Ronde | 100.00% |
Previous: | Next: |
---|---|
72551: 1996-083-00 EXP BIOP CTUIR GRANDE RONDE SUBBASIN RESTORATION 16 |
|
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Receipt of environmental compliance clearance from BPA. | A: 165. Complete and/or initiate Environmental Permitting for Project Activities | 04/30/2019 | 04/30/2019 | |
Effective implementation management and timely contract administration | B: 119. Phase 3 Rock Creek Project Administration | 04/30/2019 | 11/09/2018 | |
Construct meandering stream channel | C: 30. Construct Rock Creek Restoration Channel | 10/30/2018 | 10/31/2018 | |
Install large wood complexes and habitat boulders to increase habitat complexity and diversity | D: 29. Install Large Wood Complexes and habitat boulders along Rock Creek | 10/30/2018 | 11/02/2018 | |
Conduct Fish Salvage Operations | E: 28. Conduct Fish Salvage Operations on the Rock Creek Phase III Project | 10/15/2018 | 10/15/2018 | |
Remove draw bottom road | F: 33. Obliterate draw bottom road along Rock Creek | 10/30/2018 | 11/09/2018 | |
Plant native trees, shrubs, and grass on the Rock Creek Phase III Project | G: 47. Plant native trees, shrubs, and grasses on the Rock Creek Project | 04/30/2019 | 04/30/2019 | |
Effective implementation management and timely contract administration | H: 119. Bird Track Springs Fish Habitat Enhancement Project Administration | 04/30/2019 | 04/30/2019 | |
Conduct Fish Salvage Operations | I: 28. Conduct Fish Salvage Operations on the Bird Track Springs Project | 10/15/2018 | 10/15/2018 | |
Plant native trees, shrubs, and grass on the Bird Track Springs Project | J: 47. Plant native trees, shrubs, and grasses on the Bird Track Springs Project | 04/30/2019 | 11/30/2018 | |
Effective implementation management and timely contract administration | K: 119. Middle Upper Grande Ronde (MUGRR) Fish Habitat Enhancement Project Administration | 04/30/2019 | 04/30/2019 | |
Conduct maintenance on McCoy, Dark Canyon, Meadow, Willow, Rock, and Catherine Creek Projects | N: 186. Maintain instream structures, fences, and off-channel water developments | 04/30/2019 | 04/30/2019 | |
Maintain vegetation and control weeds on conservation projects | O: 198. Maintain Vegetation and Control Weeds on conservation projects | 04/30/2019 | 04/30/2019 | |
Complete outreach & education activities | P: 99. Public Outreach and Education | 04/30/2019 | 04/30/2019 | |
Conduct ongoing project development and coordination activities | Q: 114. CTUIR Grande Ronde Subbasin Restoration Coordination | 04/30/2019 | 04/30/2019 | |
BiOp Fish Habitat Project Opportunity Development and Review | R: 114. Solicit, review and select BiOp expense & capital projects | 04/30/2019 | 04/30/2019 | |
Develop project design plan sets. | S: 174. Develop project designs and produce plans | 04/30/2019 | 04/30/2019 | |
Administer Project | T: 119. Manage and Administer CTUIR GR Subbasin Restoration Project | 04/30/2019 | 04/30/2019 | |
Upload 2018 Annual Report | U: 132. 2018 Annual Report - May 2018 - April 2019 | 04/30/2019 | 04/30/2019 | |
Completed bridge installation | W: 184. Replace -5500 Sheep Creek Culvert on USFS Lands | 10/15/2018 | 10/15/2018 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered) |
|
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened) |
|
Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
Trout, Interior Redband (O. mykiss gairdnerii) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | Complete and/or initiate Environmental Permitting for Project Activities | 05/01/2018 | ||||||
B | 119 | Phase 3 Rock Creek Project Administration | 05/01/2018 | ||||||
C | 30 | Construct Rock Creek Restoration Channel | 08/15/2018 | ||||||
D | 29 | Install Large Wood Complexes and habitat boulders along Rock Creek | 08/15/2018 | ||||||
E | 28 | Conduct Fish Salvage Operations on the Rock Creek Phase III Project | 08/15/2018 | ||||||
F | 33 | Obliterate draw bottom road along Rock Creek | 08/15/2018 | ||||||
G | 47 | Plant native trees, shrubs, and grasses on the Rock Creek Project | 08/15/2018 | ||||||
H | 119 | Bird Track Springs Fish Habitat Enhancement Project Administration | 05/01/2018 | ||||||
I | 28 | Conduct Fish Salvage Operations on the Bird Track Springs Project | 09/18/2019 | ||||||
J | 47 | Plant native trees, shrubs, and grasses on the Bird Track Springs Project | 08/15/2018 | ||||||
K | 119 | Middle Upper Grande Ronde (MUGRR) Fish Habitat Enhancement Project Administration | 05/01/2018 | ||||||
L | 47 | Plant native trees, shrubs, and grasses on the Middle Upper Grande Ronde Project | 08/15/2018 | ||||||
M | 28 | Conduct Fish Salvage Operations on the Middle Upper Grande Ronde Project | 09/18/2019 | ||||||
N | 186 | Maintain instream structures, fences, and off-channel water developments | 08/15/2018 | ||||||
O | 198 | Maintain Vegetation and Control Weeds on conservation projects | 09/18/2019 | ||||||
P | 99 | Public Outreach and Education | 05/01/2018 | ||||||
Q | 114 | CTUIR Grande Ronde Subbasin Restoration Coordination | 05/01/2018 | ||||||
R | 114 | Solicit, review and select BiOp expense & capital projects | 05/01/2018 | ||||||
S | 174 | Develop project designs and produce plans | 08/15/2018 | ||||||
T | 119 | Manage and Administer CTUIR GR Subbasin Restoration Project | 05/01/2018 | ||||||
U | 132 | 2018 Annual Report - May 2018 - April 2019 | 05/01/2018 | ||||||
V | 185 | Quarterly Status Reports | 05/01/2018 | ||||||
W | 184 | Replace -5500 Sheep Creek Culvert on USFS Lands | 09/18/2019 |