Province | Subbasin | % |
---|---|---|
Mountain Snake | Clearwater | 100.00% |
Previous: | Next: |
---|---|
74017 REL 20: 2010-003-00 EXP LOWER SOUTH FORK CLEARWATER RIVER WATERSHED |
|
* Expenditures data includes accruals and are based on data through 31-Oct-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Environmental compliance documentation submitted to BPA | B: 165. Provide environmental compliance information to BPA for projects | 01/31/2020 | 01/30/2020 | |
Fence Replaced- McComas Meadows | D: 40. Replace Fence - McComas Meadows | 10/01/2019 | 11/07/2019 | |
Floodplain Restoration Design | E: 175. South Fork Clearwater River Floodplain Restoration Design | 01/31/2020 | 01/30/2020 | |
Rock Breaking Final Design | F: 175. SF Clearwater MP 28 Fish Passage Rock Breaking Design | 01/31/2020 | 01/30/2020 | |
Final Study Design and Cost Estimate | G: 115. SF Clearwater MP 28 Fish Passage Mitigation Effectiveness Monitoring Design | 01/31/2020 | 09/19/2019 | |
Riparian Vegetation Planted | H: 47. Plant Riparian Vegetation - Previous Restoration Projects | 11/01/2019 | 12/02/2019 | |
Exclosure Fence Maintained | I: 186. Maintain Exclosure Fences - Mill Creek | 07/31/2019 | 07/01/2019 | |
Exclosure fence maintained | J: 186. Maintain Exclosure Fences - McComas Meadows | 07/31/2019 | 07/01/2019 | |
Potential Passage Barrier Inventory | K: 115. Assess and Inventory Potential Passage Barriers | 01/31/2020 | 01/30/2020 | |
Manage Projects and Administrative duties | L: 119. Management, Coordination, and Communication | 01/31/2020 | 01/30/2020 | |
Upload 2019 Annual Report to Pisces | M: 132. 2019 Annual Report - 2/1/2019 - 1/31/2020 | 01/31/2020 | 01/30/2020 | |
Upload 2018 Annual Report to Pisces | N: 132. Finalize 2018 Annual Report - 2/1/2018 - 1/31/2019 | 01/31/2020 | 09/26/2019 | |
Replacement Final Designs | O: 175. Sally Ann/ Sill Creek Culvert Replacement Design | 01/31/2020 | 01/28/2020 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed) |
|
Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 185 | Periodic Status Reports for BPA | 02/01/2019 | ||||||
B | 165 | Provide environmental compliance information to BPA for projects | 02/01/2019 | ||||||
C | 184 | Replace Whiskey Creek Culvert | 04/18/2019 | ||||||
D | 40 | Replace Fence - McComas Meadows | 11/19/2018 | ||||||
E | 175 | South Fork Clearwater River Floodplain Restoration Design | 04/18/2019 | ||||||
F | 175 | SF Clearwater MP 28 Fish Passage Rock Breaking Design | 04/18/2019 | ||||||
G | 115 | SF Clearwater MP 28 Fish Passage Mitigation Effectiveness Monitoring Design | 11/20/2018 | ||||||
H | 47 | Plant Riparian Vegetation - Previous Restoration Projects | 11/20/2018 | ||||||
I | 186 | Maintain Exclosure Fences - Mill Creek | 11/20/2018 | ||||||
J | 186 | Maintain Exclosure Fences - McComas Meadows | 11/20/2018 | ||||||
K | 115 | Assess and Inventory Potential Passage Barriers | 11/20/2018 | ||||||
L | 119 | Management, Coordination, and Communication | 02/01/2019 | ||||||
M | 132 | 2019 Annual Report - 2/1/2019 - 1/31/2020 | 02/01/2019 | ||||||
N | 132 | Finalize 2018 Annual Report - 2/1/2018 - 1/31/2019 | 02/01/2019 | ||||||
O | 175 | Sally Ann/ Sill Creek Culvert Replacement Design | 08/05/2019 |