Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 74017 REL 61: 2002-072-00 EXP RED RIVER WATERSHED RESTORATION
Project Number:
Title:
Red River/Newsome Creek Watershed Restoration
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Clearwater 100.00%
Contract Number:
74017 REL 61
Contract Title:
2002-072-00 EXP RED RIVER WATERSHED RESTORATION
Contract Continuation:
Previous: Next:
74017 REL 32: 2002-072-00 EXP RED RIVER & NEWSOME CREEK RESTORATION 2019
  • 74017 REL 80: 2002-072-00 EXP RED RIVER WATERSHED RESTORATION
Contract Status:
Closed
Contract Description:
Red River & Newsome Creek are main tributaries to the South Fork Clearwater River and have historically been strongholds for steelhead, bull trout, and Chinook salmon. Past land management activities have severely degraded spawning and rearing habitat for these species. This project proposes to restore degraded habitats through a comprehensive restoration program focusing primarily on the mainstem channels, floodplains, riparian corridors, and other needs within these watershed drainages.

The Tribe proposes to address the primary limiting factors to abundance and productivity of the focal species. The Tribe and Forest Service have prioritized restoration projects to address these limiting factors based on the Clearwater Subbasin Plan (NPCC 2005), South Fork Clearwater River Landscape Assessment (USDA 1998), Newsome Creek Ecosystem Analysis at the Watershed Scale ((EAWS), USDA 2002), Red River Ecosystem Analysis at the Watershed Scale ((EAWS), USDA 2003), and the 2016 Clearwater Expert Panel process.

The resulting habitat improvements will increase survival for the following fish populations: Snake River Steelhead (O. mykiss) - ESA Threatened and Designated Critical Habitat, Snake River spring/summer Chinook (O. tshawytscha), bull trout (S. confluentus) - ESA Threatened and Designated Critical Habitat, Westslope cutthroat trout (O.c. lewisi), rainbow trout (O. mykiss), and Pacific lamprey (Lampetra tridentata).

This project is part of the Nez Perce Clearwater National Forest, Nez Perce Tribe, and BPA Watershed Restoration Partnership.  Since the project’s inception, we have shared project planning, costs, and implementation responsibilities.  This contract period's work will consist of replacing an undersized fish barrier culvert on Little Moose Creek (a tributary to Red River) and implementing a larger riparian planting effort in the  Lower Red River Meadow project area.  Work will continue on the Red River Corrals Conservation Easement (planning of future potential projects). We have also had interest from several other landowners within Red River to look at their meadow properties for potential restoration activities. We will be working towards partnerships with those landowners as their properties are key components to restoring river processes both within the Red River Watershed and South Fork Clearwater River subbasin.

Projects for 2020 that are entering the planning phase are: Newsome Phase II (covers up to seven miles of mainstem stream habitat complexity through LWD and boulder placement; Lower Red River LWD (up to 12 miles of river habitat complexity through addition of LWD); Red River private property restoration; Red River Corrals riparian planting; re-visiting Siegel Creek Culvert replacement; and road improvement projects within Red River and Newsome Creek Watersheds.
Account Type(s):
Expense
Contract Start Date:
02/01/2020
Contract End Date:
01/31/2021
Current Contract Value:
$675,574
Expenditures:
$675,574

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Stephanie Bransford Nez Perce Tribe Yes Contract Manager stephanieb@nezperce.org (208) 983-0675
Kara Campbell Bonneville Power Administration No Interested Party KMCampbell@bpa.gov (503) 230-4031
Marcie Carter Nez Perce Tribe Yes Supervisor marciec@nezperce.org (208) 621-3534
Desmond Gelman Bonneville Power Administration No CO Assistant dxgelman@bpa.gov (503) 230-4960
Heidi Haak Bonneville Power Administration No Interested Party hlhaak@bpa.gov (541) 922-6856
Heidi Haserot Bonneville Power Administration No Interested Party hmhaserot@bpa.gov (503) 230-3115
Arleen Henry Nez Perce Tribe No Administrative Contact arleenh@nezperce.org (208) 621-3833
Kelly Hope Bonneville Power Administration No Env. Compliance Lead kahope@bpa.gov (503) 230-4738
David Kaplowe Bonneville Power Administration Yes F&W Approver djkaplowe@bpa.gov (503) 230-5365
Jennifer Lord Bonneville Power Administration Yes COR jklord@bpa.gov (503) 230-5192
Michele Palmer Bonneville Power Administration Yes Interested Party mlpalmer@bpa.gov (503) 230-5351
Emmit Taylor, Jr. Nez Perce Tribe No Supervisor emmitt@nezperce.org (208) 621-3544
Frederick Walasavage Bonneville Power Administration No Interested Party fwalasavage@bpa.gov (541) 296-3615
Karen Wolfe Bonneville Power Administration Yes Contracting Officer ktwolfe@bpa.gov (503) 230-3448


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Environmental compliance documentation submitted to BPA B: 165. Submit Environmental Compliance Documentation to BPA 10/30/2020 09/30/2020
Little Moose Creek Culvert Replaced C: 184. Little Moose Creek Culvert Replacement 10/09/2020 08/14/2020
Complete Riparian Planting on Red River Meadows D: 47. Plant Red River Meadows 12/20/2020 11/12/2020
Red River Corrals Conservation Easement E: 172. Red River Corrals Conservation Easement 01/31/2021
Red River Fence Maintained F: 186. Red River Meadows Fence Maintenance (Private Property) 06/19/2020 06/12/2020
Develop or update (out-year) prioritized Habitat Project list for the Red River and Newsome Creek basins G: 114. Red River/Newsome Project Selection 01/31/2021 09/25/2020
Successful Project/Contract Management H: 119. Management, Coordination, and Communication 01/31/2021 01/31/2021
Provide periodic review of proposed partner actions. I: 122. Review of Proposed Partner Actions 01/31/2021 01/31/2021
Completed Annual Report J: 132. Submit Progress Report for the period February 2019 to January 2020 04/30/2020 03/31/2020
2020 Annual Report K: 132. Red River/Newsome Creek Annual Report - February 2020 - January 2021 01/31/2021 01/31/2021

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed)
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 184 Install Fish Passage Structure
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 114 Identify and Select Projects
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 184 Install Fish Passage Structure
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 114 Identify and Select Projects
Lamprey, Pacific (Entosphenus tridentata)
  • 1 instance of WE 114 Identify and Select Projects
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 114 Identify and Select Projects

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA
B 165 Submit Environmental Compliance Documentation to BPA
C 184 Little Moose Creek Culvert Replacement 05/12/2020
D 47 Plant Red River Meadows 08/17/2020
E 172 Red River Corrals Conservation Easement
F 186 Red River Meadows Fence Maintenance (Private Property) 05/12/2020
G 114 Red River/Newsome Project Selection
H 119 Management, Coordination, and Communication
I 122 Review of Proposed Partner Actions
J 132 Submit Progress Report for the period February 2019 to January 2020
K 132 Red River/Newsome Creek Annual Report - February 2020 - January 2021