Province | Subbasin | % |
---|---|---|
Intermountain | Pend Oreille | 100.00% |
Previous: | Next: |
---|---|
71919: 1995-001-00 EXP KALISPEL RESIDENT FISH HATCHERY |
|
* Expenditures data includes accruals and are based on data through 30-Sep-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Completed Environmental Documentation | B: 165. Obtain required environmental clearance to implement affected Work Elements | 06/15/2017 | 06/15/2017 | |
Maintain Hatchery Operations | C: 61. Maintain day-to-day hatchery operations | 02/01/2018 | 02/01/2018 | |
Produce TRBT | D: 176. Produce KTFH raised TRBT for Kalispel Member harvest | 02/01/2018 | 02/01/2018 | |
Maintain fish health | E: 60. Maintain fish health of hatchery raised fish | 02/01/2018 | 02/01/2018 | |
Put and Take Fishery | F: 187. Tribal Member harvest of KTFH raised TRBT | 02/01/2018 | ||
Kalispel Tribal Fish Hatchery Production Plan | G: 174. Kalispel Tribal Fish Hatchery Production Plan | 02/01/2018 | ||
Design, Specifications, and permits for modifications and upgrades to existing hatchery facili | H: 175. Design and specifications for modifications and upgrades to existing hatchery facilities | 02/01/2018 | 02/01/2018 | |
Improvements and Modifications to Existing Hatchery Facilities | I: 171. Implement modifications and upgrades to existing hatchery facilities. | 02/01/2018 | ||
Reconstruction of upper pond on Indian Creek property. | J: 35. Reconstruct the upper pond on Indian Creek property | 09/25/2017 | 09/30/2017 | |
Kalispel Tribal Hatchery and Natural Resource Department Outreach and Education | K: 99. Kalispel Tribal Hatchery and Natural Resource Department Outreach and Education | 02/01/2018 | 02/01/2018 | |
Coordinate with CCT on shared salmon harvest | L: 191. Coordinate with CCT on shared salmon harvest | 02/01/2018 | ||
Attach Progress Report in Pisces | M: 132. Submit Progress Report for the period February 2017 to February 2018 | 01/15/2018 | 02/01/2018 | |
Hatchery Administration and Management | N: 119. Prepare Draft Scope of Work and Budget for FY 18 | 02/01/2018 | 02/01/2018 |
Primary Focal Species | Work Statement Elements |
---|---|
Trout, Rainbow (Oncorhynchus mykiss) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 185 | Periodic Status Reports for BPA | 02/02/2017 | ||||||
B | 165 | Obtain required environmental clearance to implement affected Work Elements | 02/02/2017 | ||||||
C | 61 | Maintain day-to-day hatchery operations | 02/02/2017 | ||||||
D | 176 | Produce KTFH raised TRBT for Kalispel Member harvest | 02/02/2017 | ||||||
E | 60 | Maintain fish health of hatchery raised fish | 02/02/2017 | ||||||
F | 187 | Tribal Member harvest of KTFH raised TRBT | 08/16/2017 | ||||||
G | 174 | Kalispel Tribal Fish Hatchery Production Plan | 02/02/2017 | ||||||
H | 175 | Design and specifications for modifications and upgrades to existing hatchery facilities | 02/02/2017 | ||||||
I | 171 | Implement modifications and upgrades to existing hatchery facilities. | 08/29/2017 | ||||||
J | 35 | Reconstruct the upper pond on Indian Creek property | 08/16/2017 | ||||||
K | 99 | Kalispel Tribal Hatchery and Natural Resource Department Outreach and Education | 02/02/2017 | ||||||
L | 191 | Coordinate with CCT on shared salmon harvest | 02/02/2017 | ||||||
M | 132 | Submit Progress Report for the period February 2017 to February 2018 | 02/02/2017 | ||||||
N | 119 | Prepare Draft Scope of Work and Budget for FY 18 | 02/02/2017 |