Province | Subbasin | % |
---|---|---|
Lower Columbia | Willamette | 100.00% |
Previous: | Next: |
---|---|
n/a |
* Expenditures data includes accruals and are based on data through 31-Mar-2025.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Successful completion of project. | B: 119. Project management | 03/31/2018 | 03/31/2018 | |
Approved | C: 165. Environmental compliance | 03/31/2018 | 03/31/2018 | |
Successful implementation of aquatic weed treatments. | D: 199. Treatment of aquatic invasive weeds at two sites upstream of Snag Boat Bend | 03/31/2018 | 03/31/2018 | |
Successful completion of restoration solutions at all sites. | E: 180. Floodplain grading and water control structure removal at 10 sites to re-connect floodplain | 03/31/2018 | 03/31/2018 | |
Lower road berm, install rocked crossing. | F: 184. Replace existing road berm crossing on high flow channel with rocked crossing | 03/31/2018 | 03/31/2018 | |
Installation of native plants on 48 acres of floodplain. | G: 47. Reforestation of 48 acres of historic floodplain forest | 03/31/2018 | 03/31/2018 | |
Progress reports | H: 132. Submit Progress Report for the period (Apr 2017) to (Mar 2018) | 03/31/2018 | 03/31/2018 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Upper Willamette River ESU (Threatened) |
|
Cutthroat Trout, Coastal (O. c. clarkii) - Upper Willamette River ESU |
|
Chub, Oregon (Oregonichthys crameri) (Endangered through FY2015) |
|
Trout, Rainbow (Oncorhynchus mykiss) |
|
Wildlife |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 185 | Periodic Status Reports for BPA | 03/01/2017 | ||||||
B | 119 | Project management | 03/01/2017 | ||||||
C | 165 | Environmental compliance | 03/01/2017 | ||||||
D | 199 | Treatment of aquatic invasive weeds at two sites upstream of Snag Boat Bend | 07/25/2017 | ||||||
E | 180 | Floodplain grading and water control structure removal at 10 sites to re-connect floodplain | 09/04/2017 | ||||||
F | 184 | Replace existing road berm crossing on high flow channel with rocked crossing | 09/04/2017 | ||||||
G | 47 | Reforestation of 48 acres of historic floodplain forest | 09/04/2017 | ||||||
H | 132 | Submit Progress Report for the period (Apr 2017) to (Mar 2018) | 03/01/2017 |