Province | Subbasin | % |
---|---|---|
Mountain Snake | Salmon | 100.00% |
Previous: | Next: |
---|---|
76913 REL 26: 2010-072-00 EXP LEMHI RIVER RESTORATION |
|
* Expenditures data includes accruals and are based on data through 31-Oct-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Effective implementation management and timely contract administration | A: 119. Routine/daily administration of work elements | 02/28/2023 | 02/27/2023 | |
Complete all required EC and obtain permits prior to implementation of project | B: 165. Produce Environmental Compliance Documentation | 02/28/2023 | 02/21/2023 | |
Completed Annual Report | D: 132. Submit Progress Report for the period March 2021 through February 2022 | 08/31/2022 | 09/21/2022 | |
Effective implementation management and timely contract administration | E: 119. IDFG: Manage and Administer Project | 02/28/2023 | 02/15/2023 | |
Develop or update (out-year) prioritized Habitat Project list: upload to Pisces | F: 114. IDFG: Lemhi River Project Development | 02/28/2023 | 02/21/2023 | |
Complete construction on phase 2 & 3 EVR Subreach 1 on lower Lemhi River. | G: 29. IDFG: Lower Lemhi Eagle Valley Ranch Subreach 1 Phase 2 & 3 Implementation | 02/28/2023 | ||
Submit final design and bid documents for Bohannon Diversion 3 pump station | I: 175. IDFG: Bohannon Diversion 3 Pump Station Evaluation | 01/31/2023 | ||
Submit design and bid documents for EVR Subreach 4 on the lower Lemhi River | J: 175. IDFG: Lower Lemhi Eagle Valley Ranch Sub-reach 4 - Complete Sub-reach 4 Design | 02/28/2023 | 02/21/2023 | |
Unscheduled maintenance on habitat/passage/structures completed as needed. | K: 186. IDFG: Perform Unscheduled Maintenance of Habitat Project Sites | 02/28/2023 | 02/21/2023 | |
Effective implementation management and timely contract administration | L: 119. Lemhi SWCD: Project Implementation: Manage and Administer | 02/28/2023 | 02/23/2023 | |
Provide project management and construction oversight | M: 100. Lemhi SWCD Project Implementation: Provide Project Implementation Support & Construction Oversight | 02/28/2023 | 02/23/2023 | |
Develop or update (out-year) prioritized Habitat Project list: upload to Pisces | N: 114. Lemhi SWCD Project Implementation: Identify and Select Projects | 02/28/2023 | 02/23/2023 | |
Vegetation managed through noxious and non-native weed herbicide treatments | O: 199. Lemhi SWCD: Lemhi Vegetation: Initial treatment | 11/30/2022 | 11/30/2022 | |
Vegetation maintenance activities complete | P: 198. Lemhi SWCD: Lemhi Vegetation: Ongoing treatment | 02/28/2023 | 02/23/2023 | |
Planting Completed | Q: 47. Lemhi SWCD: Lemhi Vegetation Management: Rehabilitate Project Sites | 12/30/2022 | 12/21/2022 | |
Final designs completed and submitted to BPA | R: 175. Lemhi SWCD: Middle Lemhi Hayden Reach Phase I - Design | 02/28/2023 | 07/08/2022 | |
2022 construction is complete | S: 29. Lemhi SWCD: Middle Lemhi Hayden Reach Phase I - Implementation | 02/28/2023 | ||
Provide final design | U: 175. Lemhi SWCD: L-45 Diversion and Restoration Design | 02/28/2023 | ||
Fence repair and site demobilization complete | X: 186. TU: Lower Canyon Creek: Repair existing fence and site demobilization | 02/28/2023 | 07/11/2022 | |
Final design completed and uploaded in cbfish. | AF: 175. LRLT: Lemhi River and Kenney Creek Jackson Project | 02/28/2023 | ||
Habitat project imagery and geo referenced maps for use by cooperators. | AG: 161. IDFG: Maintain cloud-based repository for habitat project imagery and geo referenced maps for project planning and cooperator use. | 02/28/2023 | 02/21/2023 | |
Eagle Valley Ranch Subreach 1 phase 1 replanted | AI: 47. IDFG: Fall revegetation of Eagle Valley Ranch sub reach 1 phase 1 and phase 2. | 02/28/2023 | 02/21/2023 | |
Fence installed. | AJ: 40. IDFG: Revegetation fencing | 02/28/2023 | 02/21/2023 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (Oncorhynchus tshawytscha) - All Populations |
|
Chinook (O. tshawytscha) - Snake River Fall ESU (Threatened) |
|
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed) |
|
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened) |
|
Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 119 | Routine/daily administration of work elements | |||||||
B | 165 | Produce Environmental Compliance Documentation | |||||||
C | 185 | Periodic Status Reports for BPA | |||||||
D | 132 | Submit Progress Report for the period March 2021 through February 2022 | |||||||
E | 119 | IDFG: Manage and Administer Project | |||||||
F | 114 | IDFG: Lemhi River Project Development | |||||||
G | 29 | IDFG: Lower Lemhi Eagle Valley Ranch Subreach 1 Phase 2 & 3 Implementation | 08/29/2022 | ||||||
H | 29 | IDFG: Complete Middle Lemhi Henry Reach Phase 2. | 09/20/2022 | ||||||
I | 175 | IDFG: Bohannon Diversion 3 Pump Station Evaluation | 02/11/2022 | ||||||
J | 175 | IDFG: Lower Lemhi Eagle Valley Ranch Sub-reach 4 - Complete Sub-reach 4 Design | 02/11/2022 | ||||||
K | 186 | IDFG: Perform Unscheduled Maintenance of Habitat Project Sites | 06/10/2022 | ||||||
L | 119 | Lemhi SWCD: Project Implementation: Manage and Administer | |||||||
M | 100 | Lemhi SWCD Project Implementation: Provide Project Implementation Support & Construction Oversight | |||||||
N | 114 | Lemhi SWCD Project Implementation: Identify and Select Projects | |||||||
O | 199 | Lemhi SWCD: Lemhi Vegetation: Initial treatment | 04/27/2022 | ||||||
P | 198 | Lemhi SWCD: Lemhi Vegetation: Ongoing treatment | 04/27/2022 | ||||||
Q | 47 | Lemhi SWCD: Lemhi Vegetation Management: Rehabilitate Project Sites | 04/27/2022 | ||||||
R | 175 | Lemhi SWCD: Middle Lemhi Hayden Reach Phase I - Design | 02/11/2022 | ||||||
S | 29 | Lemhi SWCD: Middle Lemhi Hayden Reach Phase I - Implementation | 09/21/2022 | ||||||
T | 208 | Lemhi SWCD: Lemhi River Mile 32 Restoration and Diversion Consolidation | |||||||
U | 175 | Lemhi SWCD: L-45 Diversion and Restoration Design | 02/11/2022 | ||||||
V | 47 | TU: Lower Canyon Creek: Plant Vegetation | |||||||
W | 40 | TU: Lower Canyon Creek: Install Fence | |||||||
X | 186 | TU: Lower Canyon Creek: Repair existing fence and site demobilization | |||||||
Y | 29 | LRLT: Upper Big Springs and Pond Outlet Restoration: In-stream Features | |||||||
Z | 100 | LRLT: Upper Big Springs and Pond Outlet Restoration: Construction Oversight | |||||||
AA | 30 | LRLT- Upper Big Springs and Pond Outlet Restoration: New Channel Construction | |||||||
AB | 35 | LRLT: Upper Big Springs and Pond Outlet Restoration: Pond Outlet Relocation | |||||||
AC | 40 | LRLT: Upper Big Springs and Pond Outlet Restoration: Install Fence | |||||||
AD | 47 | LRLT: Upper Big Springs and Pond Outlet Restoration: Plant Vegetation | |||||||
AE | 188 | LRLT: Lemhi Kiosks | |||||||
AF | 175 | LRLT: Lemhi River and Kenney Creek Jackson Project | 06/13/2022 | ||||||
AG | 161 | IDFG: Maintain cloud-based repository for habitat project imagery and geo referenced maps for project planning and cooperator use. | |||||||
AH | 208 | IDFG: Reconstruct the Bohannon Creek Diversion #3 | 10/26/2022 | ||||||
AI | 47 | IDFG: Fall revegetation of Eagle Valley Ranch sub reach 1 phase 1 and phase 2. | 08/29/2022 | ||||||
AJ | 40 | IDFG: Revegetation fencing | 08/29/2022 |