SOW Report
Contract 78579: 2016-001-00 EXP BPA PROJ ACTION EFFECTIVENESS MONITORING
Project Number:
Title:
BPA Project Action Effectiveness Monitoring (AEM) Programmatic
BPA PM:
Stage:
Complete
Area:
Province Subbasin %
Basinwide - 100.00%
Contract Number:
78579
Contract Title:
2016-001-00 EXP BPA PROJ ACTION EFFECTIVENESS MONITORING
Contract Continuation:
Previous: Next:
n/a
Contract Status:
Closed
Contract Description:
In November of 2017, BPA solicited competitive bids for the continued implementation of BPA's Programmatic Action Effectiveness Monitoring Program (AEM) to ensure the procurement of the best professional services at the best price.  BPA issued a formal Request for Offers (RFO) Number 4201 and several proposals were reviewed and evaluated by an interdisciplinary BPA Fish and Wildlife Program team.

Cramer Fish Sciences (CFS) was selected to continue implementation of the AEM Program in January of 2018 (formal award notification letter attached to the project and contract). In January of 2018 contract 78579 was awarded to CFS for FY 2018 as the base year with the potential to exercise option years for up to five years, if peformance is satisfactory, through FY 2023.  The initial contract and all potential option years are firm fixed price contracts which demonstrate predictable and stable spending each fiscal year.

The FY 2019 contract represented the first option year as described in the CFS business proposal that is attached to this project and contract.  The FY 2020 contract represents the second option year.  Option years must be exercised as contract amendments (CCRs) instead of new contracts (CRs) based on the structure established in the competitive contract bidding and award process.  The initial FY 2018 contract 78579 is the base contract that may be extended for up to five years without further competition if performance remains satisfactory.  

Contract Objectives
•Implement and adaptively manage BPA’s Programmatic Action Effectiveness Monitoring Program (AEM) to evaluate the effectiveness of habitat improvement actions implemented under the Northwest Power and Conservation Council (NPCC) Fish and Wildlife Program for the benefit of steelhead (Oncorhynchus mykiss) and Chinook salmon (O. tshawytscha) within the Upper Columbia, Middle Columbia, and Snake River Chinook Evolutionary Significant Units (ESU) and steelhead Distinct Population Segments (DPS)
•Serve as an independent third party to evaluate project level effectiveness in an efficient, standardized, and statistically valid manner instead of monitoring the hundreds of individual habitat improvement projects that are implemented throughout the Columbia Basin each year
•Quantify localized habitat and fish abundance and distribution changes that may result from the implementation of habitat improvement actions
•Cramer Fish Sciences will provide written answers to the following questions:
o What is the effect of different action types on habitat at the reach or project scale?
o What is the effect of different action types on fish and other aquatic organisms, such as macroinvertebrates, at the reach or project scale?
o For each action type, why do some projects result in greater habitat and biological changes than others?
o Are greater habitat and biological changes detected in some geographic areas (ESU or DPS)?
•Continuously inform habitat improvement action prioritization based on annual results


Under the initial 2018 contract Cramer Fish Sciences (CFS) completed the following:

1. Identify and conduct site visits to confirm MBACI and EPT sites to be monitored in the 2018 field season
2. Monitor and collect fish and habitat data, in summer and potentially winter, for up to 15 riparian planting, invasive plant removal, floodplain reconnection, and partial barrier projects funded by BPA
3. Summarize, analyze, and report on the effectiveness of the above projects evaluated in the 2018 field season
4. Begin site reconnaissance for riparian projects to be evaluated in 2019
5. Participate in meetings to coordinate AEM activities and assure consistency of monitoring protocols

Under the 2019 option year one contract extension Cramer Fish Sciences (CFS) completed the following:

1. Identify and conduct site visits to confirm MBACI and EPT sites to be monitored in the 2019 field season
2. Monitor and collect fish and habitat data, in summer and potentially winter, for up to 15 riparian planting, invasive plant removal, floodplain reconnection, and partial barrier projects funded by BPA
3. Summarize, analyze, and report on the effectiveness of the above projects evaluated in the 2019 field season
4. Begin site reconnaissance for floodplain reconnection projects to be evaluated in 2020
5. Participate in meetings to coordinate AEM activities and assure consistency of monitoring protocols

Under the 2020 option year two contract extension Cramer Fish Sciences (CFS) completed the following:

1. Identify and conduct site visits to confirm MBACI and EPT sites to be monitored in the 2020 field season
2. Monitor and collect fish and habitat data for floodplain reconnection, and partial barrier projects funded by BPA
3. Summarize, analyze, and report on the effectiveness of the above projects evaluated in the 2020 field season
4. Begin site reconnaissance for floodplain reconnection projects to be evaluated in 2021
5. Participate in meetings to coordinate AEM activities and assure consistency of monitoring protocols

Under the 2021 option year three contract extension Cramer Fish Sciences (CFS) completed the following:
1. Identify and conduct site visits to confirm MBACI and EPT sites to be monitored in the 2021 field season
2. Monitor and collect fish and habitat data for floodplain reconnection, and partial barrier projects funded by BPA
3. Summarize, analyze, and report on the effectiveness of the above projects evaluated in the 2021 field season
4. Begin site reconnaissance for floodplain reconnection projects to be evaluated in 2022
5. Participate in meetings to coordinate AEM activities and assure consistency of monitoring protocols

Under this 2022 option year four contract extension Cramer Fish Sciences (CFS) will:
1. Identify and conduct site visits to confirm MBACI and EPT sites to be monitored in the 2022 field season
2. Participate in meetings to coordinate AEM activities and assure consistency of monitoring protocols
3. Finish monitoring and the collection of fish and habitat data for floodplain reconnection, and partial barrier projects funded by BPA
4. Summarize, analyze, and report on the effectiveness of the above projects evaluated in the 2022 field season
5. Complete a final synthesis and lessons learned report to conclude Phase I of the AEM Program
Account Type(s):
Expense
Contract Start Date:
02/23/2018
Contract End Date:
09/30/2023
Current Contract Value:
$2,071,926
Expenditures:
$2,071,926

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract
Pricing Method:
Firm Fixed Price
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Shelby Burgess Cramer Fish Sciences No Supervisor shelby.burgess@fishsciences.net (206) 905-6600
Jay Chong Bonneville Power Administration Yes Contracting Officer jxchong@bpa.gov (503) 230-4007
Minda Donnelly Department of Energy - IGE No Interested Party minda.donnelly@doe.gov (702) 295-0874
Israel Duran Bonneville Power Administration Yes Env. Compliance Lead induran@bpa.gov (503) 230-3967
Desmond Gelman Bonneville Power Administration No CO Assistant dxgelman@bpa.gov (503) 230-4960
Lael Gorsek Cramer Fish Sciences No Administrative Contact lael.gorsek@fishsciences.net (503) 850-9041
Kay Holzweissig Cramer Fish Sciences No Contract Manager kayh@fishsciences.net (503) 850-9065
David Kaplowe Bonneville Power Administration Yes COR djkaplowe@bpa.gov (503) 230-5365
Crystal Miller Department of Energy - IGE No Interested Party crystal.miller@doe.gov (702) 295-0779
Phil Roni Cramer Fish Sciences Yes Contract Manager phil.roni@fishsciences.net (206) 612-6560
Dorothy Welch Bonneville Power Administration Yes F&W Approver dwwelch@bpa.gov (503) 230-5479
Emily Wiegert Department of Energy - IGE No Interested Party emily.wiegert@doe.gov (123) 456-7890
Jae Woo Department of Energy - IGE No Interested Party jae.woo@doe.gov (702) 295-0874


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
EC Documentation Approved by BPA EC Lead A: 165. 2018: Environmental Compliance and Permitting 04/30/2018 06/11/2018
Coordination for BPA AEM Program B: 189. 2018: Coordination with BPA Partners 01/31/2019 01/31/2019
Protocol Development and Training C: 156. 2018: Study Design, Methods, and Training 09/30/2018 06/30/2018
Physical Habitat and Fish Data D: 157. 2018: Fish and Habitat Data Collection for AEM Program 10/31/2018 12/31/2018
Data Analysis and Interpretation E: 162. 2018: Summary and Analysis of AEM Fish and Habitat Data 11/30/2018 12/31/2018
Contract Management and Administration F: 119. 2018: Contract Management and Administration 01/31/2019 01/31/2019
2018 AEM Annual Report G: 132. 2018: Annual Report for 2/1/18 - 1/31/19 01/31/2019 01/31/2019
EC Documentation Approved by BPA EC Lead I: 165. 2019: Environmental Compliance and Permitting 06/01/2019 06/30/2019
Coordination for BPA AEM Program J: 189. 2019: Coordination with BPA Partners 02/28/2020 02/28/2020
Protocol Development and Training K: 156. 2019: Study Design, Methods, and Training 07/19/2019 07/12/2019
Physical Habitat and Fish Data L: 157. 2019: Fish and Habitat Data Collection for AEM Program 11/29/2019 11/29/2019
Data Analysis and Interpretation M: 162. 2019: Summary and Analysis of AEM Fish and Habitat Data 02/02/2020 02/28/2020
Effective implementation management and timely contract administration N: 119. 2019: Contract Management and Administration 02/28/2020 02/28/2020
2019 AEM Annual Report O: 132. 2019: Annual Report for 3/1/19 - 2/28/20 02/28/2020 02/28/2020
EC Documentation Approved by BPA EC Lead P: 165. 2020: Environmental Compliance and Permitting 02/15/2021 02/15/2021
Coordination for BPA AEM Program Q: 189. 2020: Coordination with BPA Partners 02/28/2021 02/28/2021
Protocol Development and Training R: 156. 2020: Study Design, Methods, and Training 05/31/2020 05/29/2020
Physical Habitat and Fish Data S: 157. 2020: Fish and Habitat Data Collection for AEM Program 10/31/2020 09/23/2020
Data Analysis and Interpretation T: 162. 2020: Summary and Analysis of AEM Fish and Habitat Data 01/15/2021 01/01/2021
Effective implementation management and timely contract administration U: 119. 2020: Contract Management and Administration 02/28/2021 02/28/2021
2020 AEM Annual Report V: 132. 2020: Annual Report for 3/1/2020 - 2/28/2021 02/28/2021 02/28/2021
EC Documentation Approved by BPA EC Lead W: 165. 2021 Environmental Compliance and Permitting 02/15/2022 02/22/2022
Coordination for BPA AEM Program X: 189. 2021 Coordination with BPA Partners 02/22/2022 02/22/2022
Protocol Development and Training Y: 156. 2021 Study Design, Methods, and Training 05/31/2021 05/18/2021
Physical Habitat and Fish Data Z: 157. 2021 Fish and Habitat Data Collection for AEM Program 10/31/2021 10/31/2021
Data Analysis and Interpretation AA: 162. 2021 Summary and Analysis of AEM Fish and Habitat Data 01/15/2022 02/22/2022
Effective implementation management and timely contract administration AB: 119. 2021 Contract Management and Administration 02/22/2022 02/01/2022
2021 AEM Annual Report AC: 132. 2021 Annual Report for 3/1/2021 - 2/28/2022 02/22/2022 02/22/2022
Develop R-Shiny app and database completed and available online (6/30/21) AD: 160. Develop Web-Based App to Provide Access to Current and Historic AEM Data 02/22/2022 02/22/2022
Final environmental compliance documentation AE: 165. 2022 Environmental Compliance and Permitting 08/31/2023 08/31/2023
Final communication with partners AF: 189. 2022 Coordination with BPA Partners 09/30/2023
Update study plan AG: 156. 2022 Study Design, Methods, and Training 05/31/2022 05/31/2022
Produce accessible, error-checked datasets AH: 157. 2022 Fish and Habitat Data Collection for AEM Program 10/31/2022 10/31/2022
Deliverable: An accessible, error-checked data set with metadata AI: 162. 2022 Summary and Analysis of AEM Fish and Habitat Data 02/15/2023 03/15/2023
AEM Database Maintained and Hosted AJ: 160. 2022 Maintain and Host AEM Database 09/30/2023 09/30/2023
Effective implementation management and timely contract administration AK: 119. 2022 Contract Management and Administration 02/22/2023 02/22/2023
Completed Annual Report and Draft Manuscript AL: 132. 2022 Annual Report for 3/1/2022 - 2/28/2023 09/01/2023 09/30/2023
Final AEM Program Phase I Synthesis Report AM: 141. 2022 AEM Program Phase I Synthesis Report 09/30/2023 09/30/2023

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 5 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 5 instances of WE 162 Analyze/Interpret Data
Chinook (O. tshawytscha) - Snake River Fall ESU (Threatened)
  • 5 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 5 instances of WE 162 Analyze/Interpret Data
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 5 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 5 instances of WE 162 Analyze/Interpret Data
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 5 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 5 instances of WE 162 Analyze/Interpret Data
Chinook (O. tshawytscha) - Upper Columbia River Summer/Fall ESU
  • 5 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 5 instances of WE 162 Analyze/Interpret Data
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 5 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 5 instances of WE 162 Analyze/Interpret Data
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 5 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 5 instances of WE 162 Analyze/Interpret Data
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 5 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 5 instances of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 2018: Environmental Compliance and Permitting 01/01/2018
B 189 2018: Coordination with BPA Partners 01/01/2018
C 156 2018: Study Design, Methods, and Training 03/01/2018
D 157 2018: Fish and Habitat Data Collection for AEM Program 03/01/2018
E 162 2018: Summary and Analysis of AEM Fish and Habitat Data 01/01/2018
F 119 2018: Contract Management and Administration 01/01/2018
G 132 2018: Annual Report for 2/1/18 - 1/31/19 01/01/2018
H 185 Periodic Status Reports for BPA 01/01/2018
I 165 2019: Environmental Compliance and Permitting
J 189 2019: Coordination with BPA Partners
K 156 2019: Study Design, Methods, and Training 03/01/2019
L 157 2019: Fish and Habitat Data Collection for AEM Program 03/01/2019
M 162 2019: Summary and Analysis of AEM Fish and Habitat Data
N 119 2019: Contract Management and Administration
O 132 2019: Annual Report for 3/1/19 - 2/28/20
P 165 2020: Environmental Compliance and Permitting
Q 189 2020: Coordination with BPA Partners
R 156 2020: Study Design, Methods, and Training 06/02/2020
S 157 2020: Fish and Habitat Data Collection for AEM Program 06/02/2020
T 162 2020: Summary and Analysis of AEM Fish and Habitat Data
U 119 2020: Contract Management and Administration
V 132 2020: Annual Report for 3/1/2020 - 2/28/2021
W 165 2021 Environmental Compliance and Permitting
X 189 2021 Coordination with BPA Partners
Y 156 2021 Study Design, Methods, and Training 03/29/2021
Z 157 2021 Fish and Habitat Data Collection for AEM Program 03/29/2021
AA 162 2021 Summary and Analysis of AEM Fish and Habitat Data
AB 119 2021 Contract Management and Administration
AC 132 2021 Annual Report for 3/1/2021 - 2/28/2022
AD 160 Develop Web-Based App to Provide Access to Current and Historic AEM Data
AE 165 2022 Environmental Compliance and Permitting
AF 189 2022 Coordination with BPA Partners
AG 156 2022 Study Design, Methods, and Training 03/01/2022
AH 157 2022 Fish and Habitat Data Collection for AEM Program 03/01/2022
AI 162 2022 Summary and Analysis of AEM Fish and Habitat Data
AJ 160 2022 Maintain and Host AEM Database
AK 119 2022 Contract Management and Administration
AL 132 2022 Annual Report for 3/1/2022 - 2/28/2023
AM 141 2022 AEM Program Phase I Synthesis Report