Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Environmental Compliance Completed | A: 165. Environmental Compliance | 08/15/2018 | 08/15/2018 | |
Complete Construction of all 25 woody material structures prior to the end of the instream work window. | B: 29. Install engineered log jam (ELJ) structures | 10/15/2018 | 09/28/2018 | |
Complete Fish Salvage | C: 28. Fish Salvage | 10/15/2018 | 09/12/2018 | |
Completed channel construction | D: 30. New Channel Excavation | 10/15/2018 | 09/28/2018 | |
Bridge Abutments installed | E: 33. Bridge Abutment Installation | 10/15/2018 | 10/15/2018 | |
Complete Willow Planting | F: 47. Willow Trenching | 10/15/2018 | 10/15/2018 | |
Effective implementation management and timely contract administration | G: 119. Project/Contract Administration | 07/31/2020 | 02/06/2019 | |
Completed Annual Report | H: 132. Completion Report | 07/31/2020 | 02/06/2019 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | Environmental Compliance | 08/01/2018 | ||||||
B | 29 | Install engineered log jam (ELJ) structures | 06/18/2018 | ||||||
C | 28 | Fish Salvage | 06/18/2018 | ||||||
D | 30 | New Channel Excavation | 07/18/2018 | ||||||
E | 33 | Bridge Abutment Installation | 08/01/2018 | ||||||
F | 47 | Willow Trenching | 06/18/2018 | ||||||
G | 119 | Project/Contract Administration | 08/01/2018 | ||||||
H | 132 | Completion Report | 08/01/2018 | ||||||
I | 185 | Quarterly Status Reports | 08/01/2018 |