Contract 83531: 1991-019-01 EXP HUNGRY HORSE MITIGATION/FLATHEAD
Project Number:
Title:
Hungry Horse Mitigation/Flathead Lake Restoration and Research, Monitoring and Evaluation (RM&E)
Stage:
Implementation
Area:
Province Subbasin %
Mountain Columbia Flathead 100.00%
Contract Number:
83531
Contract Title:
1991-019-01 EXP HUNGRY HORSE MITIGATION/FLATHEAD
Contract Continuation:
Previous: Next:
80590: 1991-019-01 EXP HUNGRY HORSE MITIGATION/FLATHEAD
  • 86330: 1991-019-01 EXP HUNGRY HORSE MITIGATION/FLATHEAD
Contract Status:
Closed
Contract Description:
The Confederated Salish and Kootenai Tribes (CSKT) and Montana Fish Wildlife and Parks (MFWP) wrote "Fisheries  Mitigation Plan for Losses Attributable to the Construction and Operation of Hungry Horse Dam" in March 1991 to define the fisheries losses, mitigation alternatives and recommendations to protect, mitigate and enhance resident fish and aquatic habitat affected by Hungry Horse Dam. On November 12, 1991, the Northwest Power and Conservation Council (NPCC) approved the mitigation plan with minor modifications, called for a detailed implementation plan, and amended measures 903(h)(1) through (7). A long-term mitigation plan was submitted in August 1992, was approved by the Council in 1993, and the first contract for this project was signed on November 11, 1993. The problem this project
addresses is the loss of habitat, both in quality and quantity, in the interconnected Flathead Lake and River basin resulting from the construction and operation of Hungry Horse Dam, and the inundation of 72 miles of the South Fork of the Flathead River and its tributaries upstream of the dam.

This project addresses basin-level objectives of the 2000 Fish and Wildlife Program of (1) maintenance and restoration of healthy ecosystems and watersheds, (2) protection and expansion of habitat and ecosystem functions, and (3) the achievement of desired population characteristics of resident fish species. The project mitigates the blockage of spawning runs by Hungry Horse Dam by restoring and creating spawning habitats within Flathead Lake tributaries. The project also addresses the unstable shoreline habitat within Flathead Lake and shifts in species composition within the lake and consequent dominance of introduced species that might restrict the success of mitigation measures. Monitoring of the experimental kokanee reintroduction in Flathead Lake was a primary activity of this project between
1992 and 1997. Lake trout, whose high densities have precluded successful mitigation of losses of other species in Flathead Lake, have been monitored since 1996 and suppressed since 2002. Recently this project has partially funded a major incentivized angling effort that has successfully engaged the public in the suppression of lake trout and conservation of native fishes.

Since 1995 the restoration component of the project has addressed several stream channel, riparian, and fish passage problems. Since 2011 restoration of acquired riparian lands has dominated the project workload. The CSKT have acquired title or easement to 59 riparian properties since 2005 which has placed enormous demands on the project for access development, weed control, trespass restrictions, structure and debris removal, and vegetative restoration. The research component of the project began in FY 2000 and measured trophic links between Mysis diluviana, lake trout and Daphnia thorata, investigated bull trout and lake trout life history parameters, and evaluated causes of shoreline erosion. Results of the research have assisted in guiding future mitigation strategies.

The Tribes obtain cost share funds from other sources for the majority of the objectives within this workplan, while at the same time this project assists with the implementation of projects conducted with Tribal dollars.  This project also incorporates the watershed coordination project. The watershed coordinator was previously a stand alone project but was merged into this project at the request of BPA. The watershed coordinator helps to coordinate private landowners and agencies for addressing the issues mentioned above. For recovery of the fisheries resources to be successful in the drainage, local involvement is necessary. This project is a coordinated effort toward addressing resource concerns and limiting factors within the Flathead River basin from a watershed perspective. Pilot projects and all other restoration or enhancement projects coordinated and implemented under this project will help address the fisheries losses from Hungry Horse Dam construction and operation. This project coordinates agencies, landowners, funding sources, and contractors to facilitate on-the-ground actions which benefit resident fish and wildlife.

The primary focus of work in FY2020 is the restoration and maintenance of lands acquired by CSKT to mitigate fisheries losses caused by Hungry Horse Dam. These activities include writing of land management plans to identify problems and prioritize solutions. Subsequent work prescribed in these plans consists of such activities as weed management, debris removal, fencing, access development, preventing trespass and habitat restoration. This project complements and coordinates closely with other projects such as Secure and Restore Critical Resident Fish Habitat (200200300), Hungry Horse Mitigation/Habitat Improvements (9101903), Hungry Horse Mitigation
(9101904) and its sister project in the Kootenai River system (9608702).
Account Type(s):
Expense
Contract Start Date:
10/01/2019
Contract End Date:
09/30/2020
Current Contract Value:
$995,742
Expenditures:
$995,742

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

BPA CO:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Brenda Aguirre Bonneville Power Administration Yes Env. Compliance Lead baguirre@bpa.gov (503) 230-5928
Amanda Bourdon Salish and Kootenai Confederated Tribes Yes Administrative Contact amanda.bourdon@cskt.org (406) 883-2888
Cecilia Brown Bonneville Power Administration Yes COR ckbrown@bpa.gov (503) 230-3462
Jay Chong Bonneville Power Administration Yes Contracting Officer jxchong@bpa.gov (503) 230-4007
Lynn DuCharme Salish and Kootenai Confederated Tribes Yes Technical Contact lynn.ducharme@cskt.org (406) 883-2888x7279
Les Evarts Salish and Kootenai Confederated Tribes Yes Supervisor les.evarts@cskt.org (406) 675-2700
Heidi Haak Bonneville Power Administration No Technical Contact hlhaak@bpa.gov (541) 922-6856
Barry Hansen Salish and Kootenai Confederated Tribes Yes Contract Manager barry.hansen@cskt.org (406) 883-2888
David Kaplowe Bonneville Power Administration Yes F&W Approver djkaplowe@bpa.gov (503) 230-5365
Tybee Sheidler Bonneville Power Administration No Administrative Contact tasheidler@bpa.gov (503) 230-3820


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Effective implementation management and timely contract administration A: 119. Manage and administer projects 09/30/2020 09/30/2020
All applicable EC documents B: 165. NEPA and ESA documents, & other cultural or environmental clearance 05/15/2020 09/30/2020
Removal of 10,000 - 20,000 lake trout from Flathead Lake by incentivized angling C: 190. Remove lake trout from Flathead Lake by fishing events 05/30/2020 09/30/2020
Construction of a new boundary fence on Ravalli property totaling 1,000 feet. D: 40. Install and maintain fence on Ravalli property (fencing subcontract) 06/30/2020 06/30/2020
Construction of a new boundary fence totaling 3,500 feet. E: 40. Install and maintain fence on Scott property (fencing subcontract) 08/30/2020
Construction of a new boundary fence on Printz property totaling 2,500 feet. F: 40. Install and maintain fence on Printz property (fencing subcontract) 08/30/2020 08/30/2020
Construction of a new boundary fence on Morton property totaling 4,000 feet. G: 40. Install and maintain fence on Valley Creek 1&2 property (fencing subcontract) 08/30/2020 08/30/2020
Construction of a new boundary fence totaling 1,000 feet. H: 40. Install and maintain fence on Hoff/Ravalli curves property (fencing subcontract) 07/30/2020 08/27/2020
Control noxious weeds on 300 acres of acquired properties I: 198. Control noxious weeds and/or re-seed acquired properties 07/30/2020 07/30/2020
Monitoring results on up to 51 acquired properties for trespass and unforeseen problems J: 26. Monitor acquired properties for trespass and unforeseen problems 09/30/2020 09/30/2020
Maintenance of access points and parking areas on Elk Creek and Hoff/Ravalli properties K: 188. Construct new access points and parking areas on newly acquired properties 09/30/2020 09/30/2020
Seed about 8 acres with cuttings and nursery-grown native plants. L: 47. Install dormant willow cuttings and nursery plants and seed native grasses on Ravalli property 06/30/2020
Remove structures and debris Valley Creek 1& 2 property M: 27. Remove structures/debris from Valley Creek 1&2 property 09/30/2020 09/30/2020
Complete all planned debris removal on Ravalli Curves property N: 27. Remove structures/debris from Ravalli Curves property 09/30/2020
Remove debris on Pitts property O: 27. Remove structures/debris from Pitts property 09/30/2020 09/30/2020
Land management plans for up to three newly acquired properties P: 193. Produce land management plans on newly acquired properties 09/30/2020 09/30/2020
Coordination meetings and new project/cost share opportunities Q: 191. New and ongoing coordination activities 09/30/2020 09/30/2020
List of projects for FY2020 and beyond R: 114. Identify problems and coordinate solutions 09/30/2020 09/30/2020
Appraisal reports, NEPA documents, surveys, and title reports S: 172. Work with project 200200300 on acquisitions & easements 09/30/2020 09/30/2020
Completed Annual Report T: 132. Submit Progress Report for the period (10/1/2017) to (9/30/2018) 06/01/2020 06/01/2020
Remove structures/debris from Upper Demonstration Reach property V: 27. CARRY FORWARD FROM FY19: Remove old structures and miscellaneous debris from the Upper Demonstration Reach property. 09/30/2020
Remove old structures and miscellaneous debris from Upper Demonstration Reach property W: 27. CARRY FORWARD FROM FY19: Remove old structures and miscellaneous debris from the Bird’s Eye View property. 09/30/2020 09/30/2020

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Cutthroat Trout, Westslope (O. c. lewisi)
  • 1 instance of WE 190 Remove, Exclude and/or Relocate Animals
  • 1 instance of WE 198 Maintain Vegetation
  • 1 instance of WE 193 Produce Land Management Plan
  • 1 instance of WE 26 Investigate Trespass
  • 5 instances of WE 27 Remove Debris
  • 5 instances of WE 40 Install Fence
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 114 Identify and Select Projects
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 190 Remove, Exclude and/or Relocate Animals
  • 1 instance of WE 198 Maintain Vegetation
  • 1 instance of WE 193 Produce Land Management Plan
  • 1 instance of WE 26 Investigate Trespass
  • 5 instances of WE 27 Remove Debris
  • 5 instances of WE 40 Install Fence
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 114 Identify and Select Projects
Trout, Lake (S. namaycush) [OBSOLETE]
  • 1 instance of WE 190 Remove, Exclude and/or Relocate Animals

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Manage and administer projects
B 165 NEPA and ESA documents, & other cultural or environmental clearance
C 190 Remove lake trout from Flathead Lake by fishing events 10/01/2019
D 40 Install and maintain fence on Ravalli property (fencing subcontract) 09/25/2020
E 40 Install and maintain fence on Scott property (fencing subcontract) 07/30/2020
F 40 Install and maintain fence on Printz property (fencing subcontract) 09/25/2020
G 40 Install and maintain fence on Valley Creek 1&2 property (fencing subcontract) 09/25/2020
H 40 Install and maintain fence on Hoff/Ravalli curves property (fencing subcontract) 09/25/2020
I 198 Control noxious weeds and/or re-seed acquired properties 09/25/2020
J 26 Monitor acquired properties for trespass and unforeseen problems
K 188 Construct new access points and parking areas on newly acquired properties 09/25/2020
L 47 Install dormant willow cuttings and nursery plants and seed native grasses on Ravalli property 07/30/2020
M 27 Remove structures/debris from Valley Creek 1&2 property 09/25/2020
N 27 Remove structures/debris from Ravalli Curves property 07/30/2020
O 27 Remove structures/debris from Pitts property 09/25/2020
P 193 Produce land management plans on newly acquired properties
Q 191 New and ongoing coordination activities
R 114 Identify problems and coordinate solutions
S 172 Work with project 200200300 on acquisitions & easements
T 132 Submit Progress Report for the period (10/1/2017) to (9/30/2018)
U 185 Periodic Status Reports for BPA
V 27 CARRY FORWARD FROM FY19: Remove old structures and miscellaneous debris from the Upper Demonstration Reach property. 07/30/2020
W 27 CARRY FORWARD FROM FY19: Remove old structures and miscellaneous debris from the Bird’s Eye View property. 07/30/2020