Contract 84044 REL 58: 2002-072-00 EXP RED RIVER WATERSHED RESTORATION
Project Number:
Title:
Red River/Newsome Creek Watershed Restoration
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Clearwater 100.00%
Contract Number:
84044 REL 58
Contract Title:
2002-072-00 EXP RED RIVER WATERSHED RESTORATION
Contract Continuation:
Previous: Next:
84044 REL 39: 2002-072-00 EXP RED RIVER WATERSHED RESTORATION
Contract Status:
Issued
Contract Description:
Red River & Newsome Creek are main tributaries to the South Fork Clearwater River and have historically been strongholds for steelhead, bull trout, and Chinook salmon. Past land management activities have severely degraded spawning and rearing habitat for these species. This project proposes to restore degraded habitats through a comprehensive restoration program focusing primarily on the mainstem channels, floodplains, and riparian corridors.

The Nez Perce Tribe ("Tribe") proposes to address the primary limiting factors to abundance and productivity of the focal species within the focal tributaries. The Tribe and Forest Service have prioritized restoration projects to address these limiting factors based on the Clearwater Subbasin Plan (NPCC 2005), South Fork Clearwater River Landscape Assessment (USDA 1998), Newsome Creek Ecosystem Analysis at the Watershed Scale ((EAWS), USDA 2002), Red River EAWS (USDA 2003), and the 2016 Clearwater Expert Panel process.

The resulting habitat improvements will increase survival for the following fish populations: Snake River Steelhead (O. mykiss) - ESA Threatened and Designated Critical Habitat, Snake River spring/summer Chinook (O. tshawytscha), bull trout (S. confluentus) - ESA Threatened and Designated Critical Habitat, Westslope cutthroat trout (O.c. lewisi), rainbow trout (O. mykiss), and Pacific lamprey (Lampetra tridentata).

This project is part of the Nez Perce Clearwater National Forest, Nez Perce Tribe, and BPA Watershed Restoration Partnership.  Since the project’s inception, we have shared project planning, costs, and implementation responsibilities.  This contract period's work will consist of plant maintenance on the past larger riparian planting efforts in the Lower Red River Meadow & Newsome Creek project areas, as well as annual fence maintenance on the Red River Meadow Conservation Easement. There has also been interest from several other landowners within Red River to look at their meadow properties for potential restoration activities. We will be working towards partnerships with interested landowners as their properties are key components to restoring river processes both within the Red River Watershed and South Fork Clearwater River subbasin.

Focal projects for 2025 & 2026 are: the implementation of the Newsome Large Wood & Boulder Placement Project -Phase I (approx. 7.2 miles of mainstem stream habitat complexity through large wood and boulder placement) and/or Red River Large Wood Placement Project - Phase I (approx. 6.8 miles of large wood placement on mainstem Red River); annual riparian planting within the Red River Meadow; preparation of a conceptual design & basis of design report for the larger Red River Meadow (including private property, IDFG RR WMA, USFS lands).  This project is envisioned to be a larger, comprehensive restoration of the Red River Meadow including mainstem river channel, side channels, tributary inputs, wetlands & floodplain.  Additional project activities include annual maintenance of cattle exclosure fencing and plant maintenance on past planting projects as well as maintenance on the construction access route for Upper Newsome Creek.
Account Type(s):
Expense
Contract Start Date:
02/01/2025
Contract End Date:
01/31/2027
Current Contract Value:
$1,983,600
Expenditures:

* Expenditures data includes accruals and are based on data through 31-Dec-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Stephanie Bransford Nez Perce Tribe Yes Contract Manager stephanieb@nezperce.org (208) 983-0675
Anthony Broncheau Nez Perce Tribe No Technical Contact anthonyb@nezperce.org (208) 843-7317
Marcie Carter Nez Perce Tribe Yes Supervisor marciec@nezperce.org (208) 621-3534
Thomas Delorenzo Bonneville Power Administration Yes Env. Compliance Lead tdelorenzo@bpa.gov (503) 230-4419
Arleen Henry Nez Perce Tribe No Administrative Contact arleenh@nezperce.org (208) 621-3833
David Kaplowe Bonneville Power Administration Yes Supervisor djkaplowe@bpa.gov (503) 230-5365
Eric Leitzinger Bonneville Power Administration Yes F&W Approver ejleitzinger@bpa.gov (503) 230-3534
Jessica Power Bonneville Power Administration No Administrative Contact jdpower@bpa.gov (503) 230-4023
Virginia Preiss Bonneville Power Administration Yes COR vdpreiss@bpa.gov (503) 230-3619
Emmit Taylor, Jr. Nez Perce Tribe No Supervisor emmitt@nezperce.org (208) 621-3544
Karen Wolfe Bonneville Power Administration Yes Contracting Officer ktwolfe@bpa.gov (503) 230-3448


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Environmental Compliance Completed A: 165. Submit Environmental Compliance Documentation to BPA 01/31/2027
Newsome Large Wood Placement - Phase I is complete B: 29. Newsome Creek Large Wood & Boulder Placement - Phase 1 of 3 10/30/2026
Red River Large Wood Placement - Phase I complete C: 29. Red River Large Wood Placement - Phase 1 of 3 08/29/2026
Conceptual Design for the Red River Meadow Complex completed D: 175. Comprehensive Red River Meadow River/Floodplain Conceptual Design 07/31/2026
Construction Management Complete E: 100. Large Wood/Boulder Placement Construction Management & Oversight 08/31/2026
Upper Newsome Access Route Maintenance Complete F: 38. Newsome Construction Access Route Maintenance 08/28/2025
Annual Red River Meadow Planting Complete G: 47. Annual Red River Meadows Planting - 2025 & 2026 01/31/2027
Plants in Red River & Newsome Creek Maintained H: 198. Red River & Newsome Plant Maintenance 09/14/2026
Red River Meadows Fence Maintained I: 186. Red River Meadows Fence Maintenance (Private Property) 07/31/2026
Develop or update (out-year) prioritized Habitat Project list: Upload to CBFish J: 114. Red River/Newsome Project Selection 01/31/2027
Effective implementation management and timely contract administration K: 119. Management and Administration of FY25/26 Contract 01/31/2027
Multi-agency watershed projects coordinated L: 191. Coordinate with partner agencies in restoration planning in the Red River basin 01/31/2027
Proposed projects reviewed M: 122. Review of Proposed Partner Actions 01/31/2027
Completed Progress (Annual) Report O: 132. Submit Progress Report for the period February 1, 2025 to January 31, 2027 01/31/2027

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (Oncorhynchus tshawytscha) - All Populations
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed)
  • 1 instance of WE 198 Maintain Vegetation
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 38 Improve Road for Instream Habitat Benefits
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 100 Construction Management
Steelhead (Oncorhynchus mykiss) - All Populations
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 198 Maintain Vegetation
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 38 Improve Road for Instream Habitat Benefits
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 100 Construction Management
Lamprey, Pacific (Entosphenus tridentata)
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 38 Improve Road for Instream Habitat Benefits
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 100 Construction Management
Trout, Bull (S. confluentus) (Threatened)
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 47 Plant Vegetation

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Submit Environmental Compliance Documentation to BPA
B 29 Newsome Creek Large Wood & Boulder Placement - Phase 1 of 3
C 29 Red River Large Wood Placement - Phase 1 of 3
D 175 Comprehensive Red River Meadow River/Floodplain Conceptual Design
E 100 Large Wood/Boulder Placement Construction Management & Oversight
F 38 Newsome Construction Access Route Maintenance
G 47 Annual Red River Meadows Planting - 2025 & 2026
H 198 Red River & Newsome Plant Maintenance
I 186 Red River Meadows Fence Maintenance (Private Property)
J 114 Red River/Newsome Project Selection
K 119 Management and Administration of FY25/26 Contract
L 191 Coordinate with partner agencies in restoration planning in the Red River basin
M 122 Review of Proposed Partner Actions
N 185 Periodic Status Reports for BPA
O 132 Submit Progress Report for the period February 1, 2025 to January 31, 2027