84044 REL 41: 2010-086-00 EXP CROOKED/AMERICAN RIVER WATERSHED RESTORATION |
* Expenditures data includes accruals and are based on data through 31-Dec-2024.
Full Name | Organization | Write Permission | Contact Role | Work Phone | |
---|---|---|---|---|---|
Brenda Aguirre | Bonneville Power Administration | Yes | Env. Compliance Lead | baguirre@bpa.gov | (503) 230-5928 |
Anthony Broncheau | Nez Perce Tribe | No | Interested Party | anthonyb@nezperce.org | (208) 843-7317 |
Marcie Carter | Nez Perce Tribe | Yes | Supervisor | marciec@nezperce.org | (208) 621-3534 |
Jenifer Harris | Nez Perce Tribe | Yes | Contract Manager | jeniferh@nezperce.org | (208) 983-1290 |
Arleen Henry | Nez Perce Tribe | No | Administrative Contact | arleenh@nezperce.org | (208) 621-3833 |
Eric Leitzinger | Bonneville Power Administration | Yes | F&W Approver | ejleitzinger@bpa.gov | (503) 230-3534 |
Jessica Power | Bonneville Power Administration | No | CO Assistant | jdpower@bpa.gov | (503) 230-4023 |
Matthew Schwartz | Bonneville Power Administration | Yes | COR | mdschwartz@bpa.gov | (503) 230-4225 |
Emmit Taylor, Jr. | Nez Perce Tribe | No | Interested Party | emmitt@nezperce.org | (208) 621-3544 |
Karen Wolfe | Bonneville Power Administration | Yes | Contracting Officer | ktwolfe@bpa.gov | (503) 230-3448 |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Complete all EC requirements | A: 165. Submit Environmental Compliance Documentation to BPA | 01/31/2027 | ||
Effective implementation management and timely contract administration | B: 119. Project Management, Coordination, and Administration | 01/31/2027 | ||
Plant up to 2,000 plant sprigs | C: 47. Plant Elk Creek | 10/31/2026 | ||
Install AOP structure | D: 184. Install Open Bottom Culvert on Big Elk Creek | 10/01/2025 | ||
Complete BDA construction on up to 20 BDAs | E: 29. Install up to 20 beaver dam analogs in Elk Creek | 10/20/2026 | ||
Conduct UAV Flights to Document Watershed Condition in the Amercian River and Crooked River Watersheds | F: 186. Inspect Habitat Projects- Crooked River and American River | 01/31/2026 | ||
Outplant salmon carcasses in American and Crooked River | G: 44. Outplant salmon carcasses | 09/29/2026 | ||
Provide education for up to 160 students | H: 99. Salmon in the Classroom | 01/31/2026 | ||
Attend meetings for coordination and outreach | I: 191. Attend meetings and trainings associated with the Protect and Restore Crooked and American River contract | 01/31/2026 | ||
Review and comment on Federal projects | J: 122. Review of Proposed Partner Actions | 01/31/2026 | ||
Replace Elk Creek Bridge | K: 184. Remove and Replace Elk Creek Bridge | 01/31/2027 | ||
Contract Implementation of a 46 foot span bridge | L: 186. Remove and replace Orogrande Bridge | 10/30/2026 | ||
Completed Progress (Annual) Report | M: 132. Submit Annual Report for 2/1/2025-1/31/2027 | 01/31/2027 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed) |
|
Coho (O. kisutch) - Unspecified Population |
|
Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
Lamprey, Pacific (Entosphenus tridentata) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | Submit Environmental Compliance Documentation to BPA | |||||||
B | 119 | Project Management, Coordination, and Administration | |||||||
C | 47 | Plant Elk Creek | |||||||
D | 184 | Install Open Bottom Culvert on Big Elk Creek | |||||||
E | 29 | Install up to 20 beaver dam analogs in Elk Creek | |||||||
F | 186 | Inspect Habitat Projects- Crooked River and American River | |||||||
G | 44 | Outplant salmon carcasses | |||||||
H | 99 | Salmon in the Classroom | |||||||
I | 191 | Attend meetings and trainings associated with the Protect and Restore Crooked and American River contract | |||||||
J | 122 | Review of Proposed Partner Actions | |||||||
K | 184 | Remove and Replace Elk Creek Bridge | |||||||
L | 186 | Remove and replace Orogrande Bridge | |||||||
M | 132 | Submit Annual Report for 2/1/2025-1/31/2027 | |||||||
N | 185 | Periodic Status Reports for BPA |