Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 84051 REL 24: 2023-001-00 EXP CCT METHOW RESTORATION
Project Number:
Title:
Upper Columbia Habitat Improvement Project (UCHIP)
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Cascade Entiat 33.30%
Okanogan 33.40%
Wenatchee 33.30%
Contract Number:
84051 REL 24
Contract Title:
2023-001-00 EXP CCT METHOW RESTORATION
Contract Continuation:
Previous: Next:
93495: 2023-001-00 EXP CCT METHOW RESTORATION
Contract Status:
Issued
Contract Description:
This contract is to conduct aquatic habitat improvement projects in the Methow, Wenatchee, and Entiat Sub-basin.  Projects to be implemented will primarily emphasize benefits to ESA listed spring Chinook, summer steelhead, and bull trout and secondarily to other salmonids and Pacific lamprey.  Work will include regular attendance of coordination meetings with project sponsors and oversight groups to ensure that work is conducted consistent with established needs and in coordination with other existing restoration efforts.

Projects prioritization is based on the 2014 EDT model run for the Methow Sub-basin, the 2021 Regional Technical Team Biological Strategy and the Upper Columbia Salmon Recovery Boards prioritization.    

Work under this contract cycle will include:

•    Twisp River Road and Campsite Decommission
•    HWY 20 Methow River:  Implementation
•    Peshastin creek confluence project:  Implementation
•    Chewuch Ramsey (Hummingbird):   Design
•    Lower Chewuch LW and complexity:   Design
•    Upper Chewuch floodplain enhancement:   Design
•    Pope Entiat River Restoration:   Design
•    Little Wenatchee River floodplain restoration:   Design
•    Peshastin RM 3.2:   Design
•    White River restoration:   Design

Additionally, CTCR will continue supporting public outreach and educate for local students and the general public about the importance of salmon recovery and habitat improvement in the Methow Valley.

Cultural resource surveys as required under Section 106 of the NHPA, unless previously completed prior to this contract period, will be completed by the Colville Confederated Tribes Cultural Resource staff.
  
The contractor (CTCR), its designated agents, sub-consultants and project stakeholders will be available, responsive and will collaboratively address contract related issues during the term of the contract. Contract issues include but are not limited to technical, policy, regulatory, project management and associated elements related to the project. Successful execution of this contract is contingent on alignment of the preceding contract issues with the BPI and BPA contracting processes, project management plans, design review protocols (including but not limited to BPA RRT design review, and integration of input and comments from BPA).

CTCR Contract Manager and design consultants will cooperate, coordinate, collaborate, and maintain effective communication with BPA PM/COR, EC Lead, and BPA ETS, during the entire length of this design contract. CTCR and its subcontractors will address BPA comments and concerns, and the two entities will arrive at a mutual beneficial consensus.  
Account Type(s):
Expense
Contract Start Date:
11/01/2024
Contract End Date:
10/31/2025
Current Contract Value:
$3,086,874
Expenditures:
$422,325

* Expenditures data includes accruals and are based on data through 31-Dec-2024.

BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Produce Environmental Compliance Documentation B: 165. Produce Compliance Documentation 10/31/2025
Effective implementation management and timely contract administration C: 119. Project Management 10/31/2025
Develop or update (out-year) prioritized Habitat Project list: Upload to CBFish D: 114. Project Identification and Selection Process & Coordination w/BPA 06/10/2025
Complete Coordination E: 191. Subbasin Coordination 10/31/2025
Complete Hwy 20 Construction F: 29. Methow River Hwy 20 10/31/2025
Complete assistance of Peshastin Creek project G: 29. Peshastin creek confluence project 10/31/2025
Submit Final Design H: 175. Chewuch Ramsey (Hummingbird) 10/31/2025
Submit Final Design I: 175. Lower Chewuch LW and complexity 10/31/2025
Submit Final Design J: 175. Upper Chewuch floodplain enhancement 10/31/2025
Complete Pope Entiat River Restoration Design K: 175. Pope Entiat River Restoration 10/31/2025
Submit Final Design L: 175. Little Wenatchee River floodplain restoration 10/31/2025
Submit 30% Designs M: 175. Peshastin RM 3.2 10/31/2025
Submit 30% Designs N: 175. White River Restoration 10/31/2025
Provide outreach and education to support upper Columbia salmon restoration efforts. O: 99. Upper Columbia education and outreach 10/31/2025
Project Complete Q: 33. Decommission Roads End Camp Ground on the Upper Twisp River 08/15/2025
Planting Complete R: 47. Decommission Roads End Camp Ground on the Upper Twisp River 10/31/2025

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 33 Decommission Road/Relocate Road
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 114 Identify and Select Projects
  • 7 instances of WE 175 Produce Design
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 33 Decommission Road/Relocate Road
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 114 Identify and Select Projects
  • 7 instances of WE 175 Produce Design
Lamprey, Pacific (Entosphenus tridentata)
  • 1 instance of WE 175 Produce Design
Trout, Bull (S. confluentus) (Threatened)
  • 2 instances of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA
B 165 Produce Compliance Documentation
C 119 Project Management
D 114 Project Identification and Selection Process & Coordination w/BPA
E 191 Subbasin Coordination
F 29 Methow River Hwy 20
G 29 Peshastin creek confluence project 10/16/2024
H 175 Chewuch Ramsey (Hummingbird)
I 175 Lower Chewuch LW and complexity
J 175 Upper Chewuch floodplain enhancement
K 175 Pope Entiat River Restoration
L 175 Little Wenatchee River floodplain restoration
M 175 Peshastin RM 3.2
N 175 White River Restoration
O 99 Upper Columbia education and outreach
P 132 No report is required per COR
Q 33 Decommission Roads End Camp Ground on the Upper Twisp River
R 47 Decommission Roads End Camp Ground on the Upper Twisp River