Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 84069 REL 10: 2007-246-00 EXP RESTORATION OF BULL TROUT PASS
Project Number:
Title:
Restoration of Bull Trout Passage at Albeni Falls Dam
Stage:
Implementation
Area:
Province Subbasin %
Intermountain Pend Oreille 100.00%
Contract Number:
84069 REL 10
Contract Title:
2007-246-00 EXP RESTORATION OF BULL TROUT PASS
Contract Continuation:
Previous: Next:
74488 REL 29: 2007-246-00 EXP RESTORATION OF BULL TROUT PASS
  • 84069 REL 20: 2007-246-00 EXP RESTORATION OF BULL TROUT PASS
Contract Status:
Closed
Contract Description:

Project 200724600 was initiated in 2007 in response to recommendations of Geist et al. (2004) and Scholz et al. (2005a). Albeni Falls Dam interferes with natural migration of adfluvial Bull Trout in the Lake Pend Oreille/Pend Oreille River system and has contributed to the extirpation of populations originating downstream of the dam. Genetically isolated populations originating upstream routinely pass the dam on their own volition or through entrainment and cannot return to natal tributaries to spawn or access thermal refuge and forage in Lake Pend Oreille. Mortality rates of migratory Bull Trout and Westslope Cutthroat Trout blocked from passing Albeni Falls Dam are extremely high due to summer water temperatures exceeding 24 °C. Reconnecting the fragmented Pend Oreille/Clark Fork system is thought to be the best way to restore local Bull Trout populations and has been required at 5 out of 6 existing mainstem dams in the U.S. through FERC license negotiations. Albeni Falls Dam is the only Federally owned and operated dam in the system and the USACE was required by the U.S. Fish and Wildlife Service to study the feasibility of restoring passage by October 1, 2004. Albeni Falls Dam upstream fish passage is the single most important conservation action that can be undertaken to recover and conserve native migratory salmonids to the lower Pend Oreille watershed.

The goals of this project are to: 1) provide temporary upstream passage for Bull Trout at Albeni Falls Dam; 2) investigate long-term fish passage solutions at Albeni Falls Dam; and 3) fill data gaps identified through this and related projects on Bull Trout and Westslope Cutthroat Trout associated with mainstem habitat connectivity in the Pend Oreille/ Clark Fork system. Our focuses since the last categorical review in 2012 have been:

•Improving safe and timely passage at AFD with a temporary upstream trap.

•Studying the feasibility of improving the attractiveness of fish trap and ladder entrances with the introduction of: 1) natal stream water; 2) conspecific pheromones; and 3) cold water.

•Collaborating with the Corps and Bonneville Power Administration (BPA) to finalize studies related to the feasibility of restoring passage for subadult and adult Bull Trout at AFD.

Throughout the historic range of Westslope Cutthroat Trout, few of the remaining stocks have been genetically classified on the basis of chromosome counts, biochemical characteristics, or molecular genetic information (USFWS 2000).  Although Westslope Cutthroat Trout stocks with varying degrees of genetic purity are known to occur across the subspecies' range, there is currently little definitive information on the genetic characteristics of most stocks (U.S. Fish and Wildlife Service 1999).  The genetic cataloging portion of this project will investigate the genetic characteristics and degree of genetic purity of Westslope Cutthroat Trout in the upper Pend Oreille Subbasin and provide a means to identify fish of unknown origin to a most-probable region and natal tributary.  These results will greatly improve the probability of Westslope Cutthroat Trout passage at Albeni Falls Dam in the future.
Account Type(s):
Expense
Contract Start Date:
05/01/2021
Contract End Date:
04/30/2022
Current Contract Value:
$490,681
Expenditures:
$490,681

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Amber Allman Pacific Northwest National Laboratory No Interested Party amber.allman@pnnl.gov (509) 375-2039
Brian Bellgraph Pacific Northwest National Laboratory Yes Technical Contact brian.bellgraph@pnnl.gov (509) 371-7185
Jason Connor Kalispel Tribe Yes Contract Manager jconnor@knrd.org (509) 447-7285
Thomas Delorenzo Bonneville Power Administration Yes Env. Compliance Lead tdelorenzo@bpa.gov (503) 230-4419
David Kaplowe Bonneville Power Administration Yes F&W Approver djkaplowe@bpa.gov (503) 230-5365
Timothy Ludington Bonneville Power Administration Yes COR tsludington@bpa.gov (503) 230-4988
Joe Maroney Kalispel Tribe Yes Supervisor jmaroney@knrd.org (509) 447-7272
Jennifer McKenna Bonneville Power Administration No CO Assistant jmmckenna@bpa.gov (503) 314-8915
Jason Olson Kalispel Tribe Yes Interested Party jolson@knrd.org (509) 447-7290
Raymond Ostlie Kalispel Tribe Yes Technical Contact Rostlie@kalispeltribe.com (509) 447-7243
Jolene Seymour Kalispel Tribe Yes Contract Manager jseymour@kalispeltribe.com (509) 445-1147
John Stephenson Pacific Northwest National Laboratory No Interested Party john.stephenson@pnnl.gov (509) 371-7219
Janie Vickerman Pacific Northwest National Laboratory Yes Interested Party janie.vickerman@pnnl.gov (509) 371-7260
Virgil Watts III Bonneville Power Administration Yes Technical Contact vlwatts@bpa.gov (503) 230-4625
Elham Zolmajd-Haghighi Bonneville Power Administration Yes Contracting Officer ezolmajd-haghighi@bpa.gov (503) 230-7414


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Idaho and Washington scientific collection, transportation, and federal permits B: 165. Obtain necessary permits 04/30/2022 04/30/2022
Bull Trout Collection below Albeni Falls Dam by boat electrofishing C: 157. Electrofishing to collect bull trout below Albeni Falls Dam 04/30/2022 04/30/2022
Bull Trout implanted with PIT tags prior to release D: 158. Implant PIT tags into bull trout for detection on PIT tags arrays upstream of Albeni Falls Dam 04/30/2022 04/30/2022
Bull trout transported above Albeni Falls Dam. E: 28. Transport bull trout above Albeni Falls Dam 04/30/2022 04/30/2022
Genetic Analysis F: 157. Genetic analysis of bull trout biopsy samples 04/30/2022 04/30/2022
Produce accessible, error-checked datasets G: 157. Tributary electrofishing 04/30/2022 04/30/2022
Produce accessible, error-checked datasets H: 157. Determine the origin of Westslope Cutthroat Trout collected below Albeni Falls Dam 04/30/2022 04/30/2022
Electrofishing data entry I: 157. Compile electronic spreadsheet database of electrofishing data 04/30/2022 04/30/2022
Data analysis J: 162. Data reduction and analysis 04/30/2022 04/30/2022
Completed Annual Report K: 132. Submit Annual Report for the period (5/1/2020) to (4/30/2021) 04/30/2022 04/30/2022
Improvements to the Indian Creek storage barn L: 186. Improve boat and equipment storage in the Indian Creek Community Forest and KNRD satellite office barn. 11/04/2021 10/28/2021
Project coordination among stakeholders M: 189. Project coordination among all stakeholders 04/30/2022 04/30/2022
Effective implementation management and timely contract administration N: 119. Manage Project 04/30/2022 04/30/2022

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Cutthroat Trout, Westslope (O. c. lewisi)
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 28 Trap and Haul
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 3 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 158 Mark/Tag Animals
  • 1 instance of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA
B 165 Obtain necessary permits
C 157 Electrofishing to collect bull trout below Albeni Falls Dam 05/18/2021
D 158 Implant PIT tags into bull trout for detection on PIT tags arrays upstream of Albeni Falls Dam 05/18/2021
E 28 Transport bull trout above Albeni Falls Dam 05/18/2021
F 157 Genetic analysis of bull trout biopsy samples 05/18/2021
G 157 Tributary electrofishing 05/18/2021
H 157 Determine the origin of Westslope Cutthroat Trout collected below Albeni Falls Dam 05/18/2021
I 157 Compile electronic spreadsheet database of electrofishing data 04/15/2021
J 162 Data reduction and analysis
K 132 Submit Annual Report for the period (5/1/2020) to (4/30/2021)
L 186 Improve boat and equipment storage in the Indian Creek Community Forest and KNRD satellite office barn. 05/18/2021
M 189 Project coordination among all stakeholders
N 119 Manage Project