Province | Subbasin | % |
---|---|---|
Lower Columbia | Willamette | 100.00% |
Previous: | Next: |
---|---|
n/a |
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Full Name | Organization | Write Permission | Contact Role | Work Phone | |
---|---|---|---|---|---|
Michael Ahr | Benton Soil and Water Conservation District | Yes | Contract Manager | michael@bentonswcd.org | (541) 753-7208 |
Eric Andersen | Bonneville Power Administration | Yes | COR | (503) 230-4094 | |
Jay Chong | Bonneville Power Administration | Yes | Contracting Officer | jxchong@bpa.gov | (503) 230-4007 |
Holly Crosson | Benton Soil and Water Conservation District | Yes | Supervisor | hcrosson@bentonswcd.org | (541) 753-7208 |
John Skidmore | Bonneville Power Administration | Yes | F&W Approver | jtskidmore@bpa.gov | (503) 230-5494 |
Shawn Skinner | Bonneville Power Administration | Yes | Env. Compliance Lead | srskinner@bpa.gov | (503) 230-3727 |
Rose Wallick | US Geological Survey (USGS) | Yes | Technical Contact | rosewall@usgs.gov | (503) 251-3219 |
Allan Whiting | Bonneville Power Administration | Yes | Backup COR | AHWhiting@bpa.gov | (503) 230-3786 |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Deliverable: Environmental and Cultural Compliance Completed | B: 165. Environmental compliance | 08/31/2021 | 08/17/2021 | |
Effective implementation management and timely contract administration | C: 119. Project management | 08/31/2021 | 08/31/2021 | |
Monitoring Plan for 2021 data collection | D: 174. Create monitoring plan for 2021. | 08/31/2021 | 03/31/2021 | |
Water temperature data from 3 sites is collected, processed and archived | E: 157. Collect water temperature data | 08/31/2021 | 03/31/2021 | |
Published water temperatures in National Water Information System. | F: 161. Publish water temperature data collected under the contract. | 08/31/2021 | 08/31/2021 | |
Database of all locations where gravel pit restoration has occurred in the Willamette Basin | G: 160. Create a database of all gravel pit restoration sites in the Willamette Basin | 08/31/2021 | 08/31/2021 | |
Presentation on fish sampling data from specific gravel pit locations | H: 159. Compile existing information on fish sampling data from specific gravel pit locations | 08/31/2021 | 03/31/2021 | |
Presentation to Habitat Technical Team, Willamette Focused Investment Partnership partners, and OWEB summarizing preliminary finds from the monitoring program. | I: 161. Present summary of all BPA WE to Habitat Technical Team, Willamette Focused Investment Partnership partners, and OWEB. | 08/31/2021 | 03/31/2021 | |
Completed Annual Report | J: 132. Submit Progress Report for the period (June 2020) to (May 2021) | 08/31/2021 | 08/31/2021 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Upper Willamette River ESU (Threatened) |
|
Steelhead (O. mykiss) - Upper Willamette River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 185 | Periodic Status Reports for BPA | |||||||
B | 165 | Environmental compliance | |||||||
C | 119 | Project management | |||||||
D | 174 | Create monitoring plan for 2021. | 05/09/2020 | ||||||
E | 157 | Collect water temperature data | 05/09/2020 | ||||||
F | 161 | Publish water temperature data collected under the contract. | |||||||
G | 160 | Create a database of all gravel pit restoration sites in the Willamette Basin | |||||||
H | 159 | Compile existing information on fish sampling data from specific gravel pit locations | |||||||
I | 161 | Present summary of all BPA WE to Habitat Technical Team, Willamette Focused Investment Partnership partners, and OWEB. | |||||||
J | 132 | Submit Progress Report for the period (June 2020) to (May 2021) |