Province | Subbasin | % |
---|---|---|
Columbia Plateau | Walla Walla | 100.00% |
* Expenditures data includes accruals and are based on data through 31-Dec-2024.
Full Name | Organization | Write Permission | Contact Role | Work Phone | |
---|---|---|---|---|---|
Brian Burns | Tri-State Steelheaders | Yes | Contract Manager | brian.burns@tristatesteelheaders.com | (509) 529-3543 |
Jay Chong | Bonneville Power Administration | Yes | Contracting Officer | jxchong@bpa.gov | (503) 230-4007 |
Gary James | Umatilla Confederated Tribes (CTUIR) | No | Supervisor | garyjames@ctuir.org | (541) 429-7285 |
Andre L'Heureux | Bonneville Power Administration | Yes | Interested Party | allheureux@bpa.gov | (503) 230-4482 |
Cory McCaffrey | Tri-State Steelheaders | No | Technical Contact | cory@tristatesteelheaders.com | (509) 529-3543 |
Claire McClory | Bonneville Power Administration | Yes | Env. Compliance Lead | cdmcclory@bpa.gov | (503) 230-5922 |
John Skidmore | Bonneville Power Administration | Yes | F&W Approver | jtskidmore@bpa.gov | (503) 230-5494 |
Corrie Veenstra | Bonneville Power Administration | Yes | COR | cxveenstra@bpa.gov | (503) 230-3503 |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Effective implementation management and timely contract administration | B: 119. Project Administration will be completed in a timely manner | 06/30/2021 | 06/29/2021 | |
Completed Annual Report | C: 132. Submit Progress Report for the period (July 1, 2020 to June 30, 2021) | 06/30/2021 | 06/30/2021 | |
Environmental Compliance Documentation | D: 165. Environmental Compliance Documentation | 06/30/2021 | 06/29/2021 | |
Pre Fabricated roughness panels | E: 184. Pre-fabrication of roughness panels. | 06/30/2021 | 06/29/2021 |
Primary Focal Species | Work Statement Elements |
---|---|
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 185 | Periodic Status Reports for BPA | |||||||
B | 119 | Project Administration will be completed in a timely manner | |||||||
C | 132 | Submit Progress Report for the period (July 1, 2020 to June 30, 2021) | |||||||
D | 165 | Environmental Compliance Documentation | |||||||
E | 184 | Pre-fabrication of roughness panels. | 07/02/2020 |