Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 85716: 2010-001-00 EXP ICICLE BOULDER FIELD
Project Number:
Title:
Upper Columbia Programmatic Habitat
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Cascade Entiat 25.00%
Methow 25.00%
Okanogan 25.00%
Wenatchee 25.00%
Contract Number:
85716
Contract Title:
2010-001-00 EXP ICICLE BOULDER FIELD
Contract Continuation:
Previous: Next:
n/a
  • 88379: 2010-001-00 EXP ICICLE BOULDER FIELD
Contract Status:
Closed
Contract Description:
Funding for construction and completion of the Boulder Field Fish Passage Project on Icicle Creek. The project will provide access to 23.4 miles of mainstem habitat and dozens of miles of tributary habitat. Project design criteria includes passage of a 14-in (or larger) steelhead/bull trout during 90% of March, 70% of April flows, 15% of May flows, and 90% of August/September natural flows.  The window for passage will range from approximately 50-1000 cfs in Icicle Creek, with a potential for passage at a high flow channel at up to around 3000 cfs.

Icicle Creek is described by the Upper Columbia Regional Technical Team (RTT) as a priority 2 watershed in the Wenatchee Subbasin. Per the 2020 UC RTT Revised Biological Strategy, Habitat Quantity (Anthropogenic Barriers) is the number 2 priority Ecological Concern for the Icicle Creek AU. Implementation of this project will address a high priority ecological concern in a high priority AU.

In the context of Wenatchee River subbasin restoration, Lower Icicle Creek is the number 3 scoring assessment unit (AU) for Steelhead (SH), and Spring Chinook (SPCH) & Steelhead, and Total Restoration. It is the number 5 scoring AU for SH in the UC Region and number 15 for Total Restoration in the UC region which indicating its significance for SH, SPCH, and Bull Trout. Furthermore, the UCRTT Biological Strategy specifically lists passage at the boulder field as a priority action type and notes that “EDT and ICRT intrinsic potential models predict very large increases in capacity for steelhead with access to Upper Icicle”. This project directly improves/provides access to upper Icicle Creek.
Account Type(s):
Expense
Contract Start Date:
09/01/2020
Contract End Date:
08/31/2021
Current Contract Value:
$325,000
Expenditures:
$325,000

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

Contract(s):

85716

Dimensions: 1280 x 960

Contract(s):

85716

Dimensions: 1024 x 768


Full Name Organization Write Permission Contact Role Email Work Phone
Theo Burgoon Trout Unlimited (TU) Yes Contract Manager theo.burgoon@tu.org (509) 630-6858
Jamie Cleveland Bonneville Power Administration Yes Interested Party jacleveland@bpa.gov (503) 230-3160
Joseph Connor Bonneville Power Administration Yes COR jwconnor@bpa.gov (503) 230-3172
Edward Gresh Bonneville Power Administration Yes Env. Compliance Lead esgresh@bpa.gov (503) 230-5756
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Lisa Pelly Trout Unlimited (TU) No Supervisor lpelly@tu.org (509) 888-0970
Aaron Penvose Trout Unlimited (TU) Yes Technical Contact apenvose@tu.org (509) 888-0970
Sarah Walker Upper Columbia Salmon Recovery Board No Interested Party sarah.walker@ucsrb.org (509) 630-8226
Karen Wolfe Bonneville Power Administration Yes Contracting Officer ktwolfe@bpa.gov (503) 230-3448


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Environmental compliance requirements complete A: 165. Obtain Required Permits, Authorizations, and Documentation for the Icicle Boulder Field Project 08/31/2021 09/01/2020
Effective implementation management and timely contract administration B: 119. Manage BPA Contracting Requirements 08/31/2021 06/30/2021
Complete Soil and Rock Excavation for Step-Pool Channel C: 85. Remove material and prepare site 10/01/2020 10/01/2020
Complete New Channel Construction D: 30. Construct Step Pool Channel 10/01/2020 10/01/2020
Construction Management Complete E: 100. Conduct project coordination and oversight of construction 08/31/2021 08/27/2021

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 85 Remove/Breach Fish Passage Barrier
  • 1 instance of WE 100 Construction Management

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Obtain Required Permits, Authorizations, and Documentation for the Icicle Boulder Field Project
B 119 Manage BPA Contracting Requirements
C 85 Remove material and prepare site 12/02/2020
D 30 Construct Step Pool Channel 12/02/2020
E 100 Conduct project coordination and oversight of construction
F 185 Periodic Status Reports for BPA
G 132 No Report Required Per COR