Contract 86056: 2010-073-00 EXP COLUMBIA LAND TRUST ESTUARINE RESTORATION (CLT)
Project Number:
Title:
Columbia Land Trust Estuarine Restoration
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia River Estuary Columbia Estuary 50.00%
Elochoman 5.00%
Grays 5.00%
Lower Columbia Columbia Lower 30.00%
Kalama 5.00%
Sandy 5.00%
Contract Number:
86056
Contract Title:
2010-073-00 EXP COLUMBIA LAND TRUST ESTUARINE RESTORATION (CLT)
Contract Continuation:
Previous: Next:
83076: 2010-073-00 EXP COLUMBIA LAND TRUST ESTUARINE RESTORATION (CLT)
  • 88632: 2010-073-00 EXP COLUMBIA LAND TRUST ESTUARINE RESTORATION (CLT)
Contract Status:
Closed
Contract Description:
The recovery of Columbia River salmonids requires that a sufficient amount and diversity of habitat opportunity is provided in the estuary to accommodate the full spectrum of stocks and life history types in the basin. To accomplish this, the primary objective of this contract is to increase the diversity, extent, and spatial distribution of habitats capable of supporting multiple salmon ESUs and life history types. With this contract Columbia Land Trust will increase the development, design and construction of on-the-ground habitat restoration actions in the Columbia River Estuary that benefit threatened and endangered salmonid species and help meet biological objectives required under the Columbia River System (CRS) Biological Opinion (BiOp).

All restoration actions conceived of and implemented within this project are intended to benefit threatened and endangered salmonid species rearing and migrating in mainstem and tidal habitats of the Columbia River Estuary.  As a principle implementer of restoration in the Columbia Estuary, Columbia Land Trust has conserved over four thousand acres of Columbia Estuary floodplain over the last nine years.  Columbia Land Trust accomplished this by permanently securing a land base from willing land owners through fair market processes.  These lands now serve as a platform from which on-the-ground restoration projects are able to be implemented.  Columbia Land Trust restoration projects result in some of the highest survival benefits for threatened and endangered salmon in the estuary (Johnson et al. 2007).  

Columbia Land Trust will assist the Action Agencies in achieving their specific estuary land protection and restoration goals by working closely with land owners, local, state and federal agencies, providing risk capital through a revolving transaction fund, negotiation capacity, legal expertise and an ability to leverage significant sources of project funding. This approach enables Columbia Land Trust to act quickly and effectively to meet estuary habitat restoration goals and allows Columbia Land Trust to accomplish restoration where other practitioners may find more challenges.  Columbia Land Trust has identified and is developing numerous estuary habitat acquisition and restoration projects within priority areas that this project will support.

The project types and actions developed within this contract are largely related to tidal reconnection actions that restore full or near full tidal influence to areas that have been historically disconnected from tidal and fluvial hydrologic processes by levees, roads, dredge material and railroad causeways.  These restoration actions intend to restore such natural habitat forming processes as tidal hydrology, sediment accretion, and the movement of macro-detritus that shape and maintain estuarine wetland habitats.  Specific restoration objectives are:

1) Restore connectivity between river and floodplain, as well as in-river habitats
2) Increase shallow water peripheral and side channel habitats toward historic levels.  

Columbia Land Trust will coordinate with, and utilize the Lower Columbia River Estuary Partnership' s Project Review Committee (PRC) for the initial level of scientific review for on-the-ground habitat projects.  The second level of scientific review will be done by the Expert Regional Technical Group (ERTG).
Account Type(s):
Expense
Contract Start Date:
10/01/2020
Contract End Date:
09/30/2021
Current Contract Value:
$1,268,775
Expenditures:
$1,268,775

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Anne Creason Bonneville Power Administration Yes COR amcreason@bpa.gov (503) 230-3859
Jason Karnezis Bonneville Power Administration Yes F&W Approver jpkarnezis@bpa.gov (503) 230-3098
Glenn Lamb Columbia Land Trust No Supervisor glamb@columbialandtrust.org
Dan Roix Columbia Land Trust Yes Contract Manager droix@columbialandtrust.org (360) 213-1211
Ian Sinks Columbia Land Trust Yes Technical Contact isinks@columbialandtrust.org (503) 799-9505
Shawn Skinner Bonneville Power Administration No Env. Compliance Lead srskinner@bpa.gov (503) 230-3727
Karen Wolfe Bonneville Power Administration Yes Contracting Officer ktwolfe@bpa.gov (503) 230-3448


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Produce the Necessary Environmental Compliance B: 165. Ensure All Environmental Compliance is Complete 09/30/2021 09/30/2021
All administration tasks fulfilled with timely, quality products C: 119. Provide Management and Administration of Projects 09/30/2021 09/30/2021
Documentation Describing Priority Projects D: 114. Identify Priority Land Acquisition and Restoration Projects 09/30/2021 09/30/2021
Final Realty Package for Priority Acquisitions E: 172. Conduct All Necessary Due Diligence Related to Land Acquisition 09/30/2021 09/30/2021
2020 Annual Stewardship Report F: 141. Other Reports for BPA 04/15/2021 04/15/2021
SUBMIT Elochoman 3 LMP to BPA G: 193. LAND MANAGEMENT PLAN--ELOCHOMAN III 09/30/2021 09/30/2021
Submit Annual Progress Report to BPA H: 132. Submit Progress Report for the period Jan 2020 to Dec 2020 04/30/2021 05/03/2021
Floodplain Re-vegetation on CSR J: 47. COLUMBIA STOCK RANCH -- CWTD RESTORATION -- Planting 09/30/2021 09/30/2021
Exclusion Fencing on CSR K: 40. COLUMBIA STOCK RANCH -- CWTD RESTORATION -- Fencing 09/30/2021 09/30/2021
Alternative Water Source on CSR L: 34. COLUMBIA STOCK RANCH -- CWTD RESTORATION -- Livestock Watering Source 09/30/2021 09/30/2021
Floodplain Habitat In-Fill Planting on LE2 M: 47. LOWER ELOCHOMAN II -- RESTORATION -- Plant Vegetation 09/30/2021
100% Design for Lower Elochoman 3 project N: 175. LOWER ELOCHOMAN III-- DESIGN 08/31/2021 09/30/2021
Vegetation Control O: 199. LOWER ELOCHOMAN III -- RESTORATION -- Vegetation Control 09/30/2021 09/30/2021
Risk Road bridge P: 184. LOWER ELOCHOMAN III -- RESTORATION -- Bridge Installation 09/30/2021
Channel obstruction debris removed Q: 27. LOWER ELOCHOMAN III -- RESTORATION -- Debris Removal 09/30/2021
Completed channel construction R: 30. LOWER ELOCHOMAN III -- RESTORATION -- Channel creation 09/30/2021
Floodplain Contouring S: 181. LOWER ELOCHOMAN III -- RESTORATION -- Floodplain contouring & reconnection 09/30/2021
Produce accessible, error-checked datasets T: 157. RESTORATION DESIGN CHALLENGES PROJECT 09/30/2021 09/30/2021
Level 3 AEMR data-- Lower Elochoman 3 PRE-construction data U: 157. LOWER ELOCHOMAN III - Collect PRE-Construction Year 0 AEMR Level 3 Data 09/30/2021 09/30/2021
Level 3 AEMR data-- Lower Elochoman 2 POST-construction data--Year 1 V: 157. LOWER ELOCHOMAN II - Collect POST-Construction Year 2 AEMR Level 3 data 09/30/2021 09/30/2021
Level 3 AEMR data-- Wallacut POST-construction Year 3 W: 157. WALLACUT - Collect POST-Construction Year 5 AEMR Level 3 data 09/30/2021 09/30/2021
Level 3 AEMR data-- Kerry Island POST-Construction Year 3 X: 157. KERRY ISLAND - Collect POST-Construction Year 5 AEMR Level 3 data 09/30/2021 09/30/2021
Level 3 AEMR data-- Mill Road POST-Construction Year 10 Y: 157. MILL ROAD -- Collect POST-Construction Year 10 AEMR Level 3 data 09/30/2021 09/30/2021
Translocate and monitor up to 30 deer Z: 190. *CR-45053: Translocate CWTD from Tenasillahe Island to Columbia Stock Ranch 09/30/2021 09/30/2021

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (Oncorhynchus tshawytscha) - All Populations
  • 1 instance of WE 199 Remove Vegetation
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 114 Identify and Select Projects
  • 5 instances of WE 157 Collect/Generate/Validate Field and Lab Data
Chinook (O. tshawytscha) - Lower Columbia River ESU (Threatened)
  • 1 instance of WE 193 Produce Land Management Plan
  • 1 instance of WE 27 Remove Debris
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 181 Create, Restore, and/or Enhance Wetland
  • 1 instance of WE 184 Install Fish Passage Structure
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Chum (Oncorhynchus keta) - Columbia River ESU (Threatened)
  • 1 instance of WE 27 Remove Debris
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 114 Identify and Select Projects
Coho (Oncorhynchus kisutch) - Lower Columbia River ESU (Threatened)
  • 1 instance of WE 199 Remove Vegetation
  • 1 instance of WE 193 Produce Land Management Plan
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 184 Install Fish Passage Structure
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 175 Produce Design
  • 6 instances of WE 157 Collect/Generate/Validate Field and Lab Data
Coho (O. kisutch) - Unspecified Population
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 114 Identify and Select Projects
Steelhead (Oncorhynchus mykiss) - All Populations
  • 1 instance of WE 199 Remove Vegetation
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 114 Identify and Select Projects
  • 5 instances of WE 157 Collect/Generate/Validate Field and Lab Data
Steelhead (O. mykiss) - Lower Columbia River DPS (Threatened)
  • 1 instance of WE 193 Produce Land Management Plan
  • 1 instance of WE 27 Remove Debris
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 181 Create, Restore, and/or Enhance Wetland
  • 1 instance of WE 184 Install Fish Passage Structure
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Wildlife
  • 1 instance of WE 190 Remove, Exclude and/or Relocate Animals
  • 1 instance of WE 34 Develop Alternative Water Source
  • 1 instance of WE 40 Install Fence
  • 1 instance of WE 47 Plant Vegetation

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA
B 165 Ensure All Environmental Compliance is Complete
C 119 Provide Management and Administration of Projects
D 114 Identify Priority Land Acquisition and Restoration Projects
E 172 Conduct All Necessary Due Diligence Related to Land Acquisition
F 141 Other Reports for BPA
G 193 LAND MANAGEMENT PLAN--ELOCHOMAN III
H 132 Submit Progress Report for the period Jan 2020 to Dec 2020
I 132 Submit Data for estuary 2020 RME Report
J 47 COLUMBIA STOCK RANCH -- CWTD RESTORATION -- Planting 07/17/2020
K 40 COLUMBIA STOCK RANCH -- CWTD RESTORATION -- Fencing 07/17/2020
L 34 COLUMBIA STOCK RANCH -- CWTD RESTORATION -- Livestock Watering Source 08/18/2021
M 47 LOWER ELOCHOMAN II -- RESTORATION -- Plant Vegetation 07/17/2020
N 175 LOWER ELOCHOMAN III-- DESIGN
O 199 LOWER ELOCHOMAN III -- RESTORATION -- Vegetation Control 07/14/2021
P 184 LOWER ELOCHOMAN III -- RESTORATION -- Bridge Installation 07/14/2021
Q 27 LOWER ELOCHOMAN III -- RESTORATION -- Debris Removal 07/14/2021
R 30 LOWER ELOCHOMAN III -- RESTORATION -- Channel creation 07/14/2021
S 181 LOWER ELOCHOMAN III -- RESTORATION -- Floodplain contouring & reconnection 07/14/2021
T 157 RESTORATION DESIGN CHALLENGES PROJECT 10/21/2020
U 157 LOWER ELOCHOMAN III - Collect PRE-Construction Year 0 AEMR Level 3 Data 10/21/2020
V 157 LOWER ELOCHOMAN II - Collect POST-Construction Year 2 AEMR Level 3 data 10/21/2020
W 157 WALLACUT - Collect POST-Construction Year 5 AEMR Level 3 data 10/21/2020
X 157 KERRY ISLAND - Collect POST-Construction Year 5 AEMR Level 3 data 10/21/2020
Y 157 MILL ROAD -- Collect POST-Construction Year 10 AEMR Level 3 data 10/21/2020
Z 190 *CR-45053: Translocate CWTD from Tenasillahe Island to Columbia Stock Ranch 10/21/2020