Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Project administration requirements completed | B: 119. Manage BPA Project | 01/31/2022 | 12/28/2021 | |
All work complies with environmental regulations | C: 165. Work with BPA on Environmental Compliance requirements. | 01/31/2022 | 12/28/2021 | |
Hood River SWCD support and coordination. | D: 191. Coordinate activities with the Hood River Soil and Water Conservation District / Hood River Watershed Group and partners. | 01/31/2022 | 12/28/2021 | |
Develop or update (out-year) prioritized Habitat Project list: upload to Pisces | E: 114. Identify and develop instream fish habitat improvement projects in the Hood River Watershed. | 01/31/2022 | 12/28/2021 | |
East Fork by-pass reach instream flow established and maintained. | F: 154. Complete Instream Flow Agreement for EFID By-Pass Reach | 12/31/2021 | 12/28/2021 | |
0.25 miles of the West Fork Hood River enhanced | G: 29. West Fork Redhill Phase 3 Large Wood Placement Project Implementation | 09/30/2021 | 09/30/2021 | |
Riparian fences maintained. | H: 186. Maintain riparian fences. | 12/31/2021 | 12/28/2021 | |
Deliverable | I: 186. Inspect large wood placement projects | 12/31/2021 | 12/28/2021 | |
Improved water quality in Baldwin Creek | J: 34. Baldwin Creek Water Quality Improvement Project | 12/31/2021 | 12/28/2021 | |
EF Mills LWD Project Area Re-planted. | K: 47. East Fork Hood River Mills LWD Project re-planting | 09/30/2021 | 03/22/2021 | |
Completed design and cultural resource surveys | L: 175. East Fork Irrigation District Whiskey Creek Pipeline Design and Cultural Survey | 12/31/2021 | 12/28/2021 | |
Advance the EFID Whiskey Creek Lateral Pipe Project to the implementation phase. | M: 203. East Fork Irrigation District Whiskey Creek Pipeline Materials purchase and installation | 12/31/2021 | 12/28/2021 | |
Improved fish habitat in 0.6 miles of Neal Creek. | N: 29. Neal Creek: Phase I Large Wood Placement Implementation | 09/30/2021 | 09/30/2021 | |
Neal Creek: Phase II Large Wood Placement Design Complete | O: 175. Neal Creek: Phase II Large Wood Placement Design | 01/31/2022 | 12/28/2021 | |
FY 2020 Annual Progress Report complete | P: 132. Prepare and submit annual progress report for FY 20 work | 04/29/2021 | 02/01/2021 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (Oncorhynchus tshawytscha) - All Populations |
|
Chinook (O. tshawytscha) - Lower Columbia River ESU (Threatened) |
|
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU |
|
Coho (Oncorhynchus kisutch) - Lower Columbia River ESU (Threatened) |
|
Coho (O. kisutch) - Unspecified Population |
|
Steelhead (Oncorhynchus mykiss) - All Populations |
|
Steelhead (O. mykiss) - Lower Columbia River DPS (Threatened) |
|
Lamprey, Pacific (Entosphenus tridentata) |
|
Trout, Bull (S. confluentus) (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 185 | Periodic Status Reports for BPA | |||||||
B | 119 | Manage BPA Project | |||||||
C | 165 | Work with BPA on Environmental Compliance requirements. | |||||||
D | 191 | Coordinate activities with the Hood River Soil and Water Conservation District / Hood River Watershed Group and partners. | |||||||
E | 114 | Identify and develop instream fish habitat improvement projects in the Hood River Watershed. | |||||||
F | 154 | Complete Instream Flow Agreement for EFID By-Pass Reach | |||||||
G | 29 | West Fork Redhill Phase 3 Large Wood Placement Project Implementation | 07/15/2021 | ||||||
H | 186 | Maintain riparian fences. | 11/05/2021 | ||||||
I | 186 | Inspect large wood placement projects | 11/05/2021 | ||||||
J | 34 | Baldwin Creek Water Quality Improvement Project | |||||||
K | 47 | East Fork Hood River Mills LWD Project re-planting | 04/01/2021 | ||||||
L | 175 | East Fork Irrigation District Whiskey Creek Pipeline Design and Cultural Survey | 02/04/2021 | ||||||
M | 203 | East Fork Irrigation District Whiskey Creek Pipeline Materials purchase and installation | |||||||
N | 29 | Neal Creek: Phase I Large Wood Placement Implementation | 07/15/2021 | ||||||
O | 175 | Neal Creek: Phase II Large Wood Placement Design | 02/04/2021 | ||||||
P | 132 | Prepare and submit annual progress report for FY 20 work |