Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 90071: 1992-026-01 EXP WILSON-HAUN WALLOWA RIVER RESTORATION
Project Number:
Title:
Grande Ronde Model Watershed
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Blue Mountain Grande Ronde 100.00%
Contract Number:
90071
Contract Title:
1992-026-01 EXP WILSON-HAUN WALLOWA RIVER RESTORATION
Contract Continuation:
Previous: Next:
n/a
Contract Status:
Closed
Contract Description:
The Wilson-Haun Wallowa River Project will take place in a high priority salmon and steelhead stream - Grande Ronde Basin. The restoration effort will occur on the mainsteam Wallowa River (RM 31.1-31.7). This reach includes critical spawning and rearing habitat for ESA Threatened Snake River Steelhead (Oncorhynchus mykiss), ESA-Threatened Bull trout (Salvelinus confluentus), and ESA-Threatened Snake River spring Chinook (Oncorhynchus tshawytscha).

The river's floodplain habitats are not in proper functioning geophysical and ecological condition (hydrologic, geomorphic, and vegetative composition), due to historic anthropogenic influences including beaver trapping, overgrazing, logging (floodplain clearing and headwater), dams, altered vegetative regime, and dewatering for irrigation. The overall project goal is to set the system on a trajectory towards achieving proper geophysical and ecological form and function, and thereby improve spawning and rearing habitat for several listed fish populations, and ecosystem function for other focal aquatic and terrestrial species.

The project team worked with Wolfe Water Resources and other partners to develop the project design over the past year. The project will use a mix of conventional and new restoration approaches backed by scientific and expert knowledge. This includes floodplain grading, channel fill, large wood placement, low-tech process based restoration, riparian planting, and other techniques.

Trout Unlimited (TU) in partnership with the Grande Ronde Model Watershed Council (GRMW), the landowners, funders, the design firm, and local partners (Nez Perce, ODFW) will implement the project under this contract with Bonneville Power Administration.
Account Type(s):
Expense
Contract Start Date:
05/01/2022
Contract End Date:
04/30/2024
Current Contract Value:
$1,244,468
Expenditures:
$1,244,468

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

Contract(s):

90071

Dimensions: 4032 x 3024


Full Name Organization Write Permission Contact Role Email Work Phone
Lindsey Arotin Bonneville Power Administration Yes Env. Compliance Lead ldarotin@bpa.gov (503) 230-4039
Amanda Coffman Grande Ronde Model Watershed Foundation No Interested Party amanda@grmw.org (541) 663-0570
Darien Gibson Trout Unlimited (TU) No Administrative Contact darien.gibson@tu.org (406) 595-7547
Tracy Hauser Bonneville Power Administration Yes COR tlhauser@bpa.gov (503) 230-4296
Noel March Trout Unlimited (TU) Yes Administrative Contact noel.march@tu.org (541) 786-8936
Anna Neuzil Bonneville Power Administration No Interested Party aaneuzil@bpa.gov (503) 230-4642
Levi Old Trout Unlimited (TU) Yes Contract Manager Levi.Old@tu.org (541) 408-3770
Aaron Penvose Trout Unlimited (TU) No Supervisor apenvose@tu.org (509) 888-0970
Jenna Peterson Bonneville Power Administration Yes Interested Party jepeterson@bpa.gov (503) 230-3018
Jessica Power Bonneville Power Administration Yes CO Assistant jdpower@bpa.gov (503) 230-4023
Jesse Steele Grande Ronde Model Watershed Foundation No Interested Party jesse@grmw.org (541) 663-0570
Connar Stone Grande Ronde Model Watershed Foundation No Interested Party connar@grmw.org (541) 663-0570
Alexandra Towne Grande Ronde Model Watershed Foundation No Interested Party alex@grmw.org (541) 663-0570
Sean Welch Bonneville Power Administration Yes F&W Approver spwelch@bpa.gov (503) 230-7691
Ian Wilson Grande Ronde Model Watershed Foundation Yes Technical Contact ian@grmw.org (541) 426-0389
Karen Wolfe Bonneville Power Administration Yes Contracting Officer ktwolfe@bpa.gov (503) 230-3448


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
EC Requirements Met A: 165. Environmental Compliance 07/07/2022 07/07/2022
Complete large wood additions to mainstem channel and floodplain habitats B: 29. Large wood additions, Boulder placements, Beaver dam Analogue and Post-Assisted Log Structure Placements 03/31/2024 09/01/2022
Completed channel construction, floodplain grading, and floodplain habitat creation C: 30. Floodplain reconnection activities - pond/alcove creation, side channel creation, and floodplain grading/channel fill. 03/15/2024 09/01/2023
Finish riparian planting and rehab D: 47. Riparian, wetland and floodplain area rehab and long-term recovery actions 04/30/2024 09/01/2023
Finish herbivory protection fence installation. E: 40. Riparian recovery and browse protection fence for floodplain plant communities 04/30/2024 03/20/2024
Construction Management Complete F: 100. Construction Oversight 02/28/2024 09/01/2023
Effective implementation management and timely contract administration G: 119. Project/Contract Administration 04/30/2024 04/30/2024
Complete Wilson Haun Wallowa River Habitat Restoration Completion Report H: 132. Completion Report - Wilson Haun Wallowa River Restoration 04/30/2024 04/30/2024

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 100 Construction Management
Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed)
  • 1 instance of WE 40 Install Fence
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 40 Install Fence
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 100 Construction Management
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 100 Construction Management

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Environmental Compliance
B 29 Large wood additions, Boulder placements, Beaver dam Analogue and Post-Assisted Log Structure Placements 06/08/2022
C 30 Floodplain reconnection activities - pond/alcove creation, side channel creation, and floodplain grading/channel fill. 06/08/2022
D 47 Riparian, wetland and floodplain area rehab and long-term recovery actions 06/08/2022
E 40 Riparian recovery and browse protection fence for floodplain plant communities 06/08/2022
F 100 Construction Oversight
G 119 Project/Contract Administration
H 132 Completion Report - Wilson Haun Wallowa River Restoration
I 185 Quarterly Status Reports