Province | Subbasin | % |
---|---|---|
Columbia Plateau | Walla Walla | 100.00% |
* Expenditures data includes accruals and are based on data through 31-Dec-2024.
Full Name | Organization | Write Permission | Contact Role | Work Phone | |
---|---|---|---|---|---|
Joshua Ashline | Bonneville Power Administration | Yes | COR | jdashline@bpa.gov | (503) 230-3862 |
Brian Burns | Tri-State Steelheaders | Yes | Contract Manager | brian.burns@tristatesteelheaders.com | (509) 529-3543 |
Jay Chong | Bonneville Power Administration | Yes | Contracting Officer | jxchong@bpa.gov | (503) 230-4007 |
Michael Lambert | Umatilla Confederated Tribes (CTUIR) | Yes | Supervisor | mikelambert@ctuir.org | (541) 429-7240 |
Morgan Morris | Tri-State Steelheaders | Yes | Contract Manager | morgan@tristatesteelheaders.com | (509) 529-3543 |
Jessica Power | Bonneville Power Administration | No | CO Assistant | jdpower@bpa.gov | (503) 230-4023 |
Jacquelyn Schei | Bonneville Power Administration | No | Env. Compliance Lead | jlschei@bpa.gov | (503) 230-5893 |
John Skidmore | Bonneville Power Administration | Yes | F&W Approver | jtskidmore@bpa.gov | (503) 230-5494 |
David Talkington | Tri-State Steelheaders | No | Interested Party | david@tristatesteelheaders.com | (509) 529-3543 |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Effective implementation management and timely contract administration | A: 119. Project Administration will be completed in a timely manner | 04/30/2024 | 06/30/2024 | |
Environmental Compliance Coordination | B: 165. Environmental Compliance Documentation | 04/30/2024 | 06/30/2024 | |
Plans and cost estimate | C: 175. Mill Creek Gose Street Fish Passage Design | 07/31/2024 | 07/31/2024 | |
Project Expenses to complete fish passage improvements to 2,100 feet of the concrete channel | D: 184. Mill Creek Concrete Flume Passage Project | 04/30/2024 | 02/11/2024 | |
Construction Management Complete | E: 100. Mill Creek Concrete Flume Passage Project | 04/01/2024 | 06/30/2024 | |
Completed Annual Report | G: 132. Submit Progress Report for the period (May 1, 2023 to April 30, 2024) | 07/31/2024 | 07/31/2024 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (Oncorhynchus tshawytscha) - All Populations |
|
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened) |
|
Trout, Bull (S. confluentus) (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 119 | Project Administration will be completed in a timely manner | |||||||
B | 165 | Environmental Compliance Documentation | |||||||
C | 175 | Mill Creek Gose Street Fish Passage Design | 01/10/2024 | ||||||
D | 184 | Mill Creek Concrete Flume Passage Project | 01/10/2024 | ||||||
E | 100 | Mill Creek Concrete Flume Passage Project | |||||||
F | 185 | Periodic Status Reports for BPA | |||||||
G | 132 | Submit Progress Report for the period (May 1, 2023 to April 30, 2024) |