Contract 93578: 1988-115-35 CAP SCHNABEL ENGINEERING SUPPORT
Project Number:
Title:
Klickitat River Design and Construction-Yakima/Klickitat Fisheries Project (YKFP)
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Gorge Klickitat 100.00%
Contract Number:
93578
Contract Title:
1988-115-35 CAP SCHNABEL ENGINEERING SUPPORT
Contract Continuation:
Previous: Next:
n/a
Contract Status:
Issued
Contract Description:
Bonneville Power Administration (BPA) will be contracting with SCHNABEL ENGINEERING, LLC for engineering services during construction of the Klickitat Hatchery Spring Chinook Upgrades Project for the Yakama Nation.

The project includes construction of new circular rearing units to bring spring Chinook production up to 800,000 yearlings, new adult holding raceways and spawning facilities, new spring water supply piping, and pollution abatement facilities in addition to a number of optional facility improvements to the site’s administration building and residences.

Following the completion of NEPA permitting, the project is expected to be bid in 2023 and begin construction later that year. The administration of the construction contract is expected to be led by a team of BPA staff with Schnabel providing supplemental services, with key deliverable of
finalizing record drawings that meet technical specifications and intent of design.

While Schnabel will not serve as construction managers, as this will be a BPA role, they will serve as technical consultants and support throughout construction as itemized and described in the SOW.

It is expected that construction will occur over an 18–24-month duration.  
Account Type(s):
Capital
Contract Start Date:
10/18/2023
Contract End Date:
10/10/2025
Current Contract Value:
$279,359
Expenditures:
$76,760

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract
Pricing Method:
Time and Materials
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Lisa Dexter Bonneville Power Administration Yes Contracting Officer lldexter@bpa.gov (503) 230-3893
Mary Haight Bonneville Power Administration Yes COR mthaight@bpa.gov (503) 230-3112
William Kozsey Jr Bonneville Power Administration Yes CO Assistant WPKozsey@bpa.gov (503) 230-3280
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Dennis Petross Bonneville Power Administration No Backup COR dwpetross@bpa.gov (503) 230-4718
Jessica Power Bonneville Power Administration No CO Assistant jdpower@bpa.gov (503) 230-4023


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Engineering support during construction A: 171. Schnabel Engineering Support During Construction 10/10/2025

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 171 Schnabel Engineering Support During Construction
B 185 Periodic Status Reports for BPA