Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 95187: 1992-026-01 EXP WILLOW CREEK FISH PASSAGE FINAL DESIGN
Project Number:
Title:
Grande Ronde Model Watershed
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Blue Mountain Grande Ronde 100.00%
Contract Number:
95187
Contract Title:
1992-026-01 EXP WILLOW CREEK FISH PASSAGE FINAL DESIGN
Contract Continuation:
Previous: Next:
n/a
Contract Status:
Issued
Contract Description:
The Royes Dam project is part of a larger effort called the Free Willow, Lower Willow Creek Fish Passage project and is intended to improve passage for adult Chinook Salmon and steelhead. The project will allow adult Chinook salmon passage into the Willow basin for the first time in over 70 years. In addition, this project will allow juvenile salmonids both upstream and downstream passage for large portions of the year while stream temperatures allow.

The construction of the Royes and Huber irrigation dams in the 1950's created physical obstructions for salmonid migration into the Willow Creek Watershed. Anecdotal information from early fishing reports indicate that Chinook were abundant in the watershed. Passage of adult salmonids upstream and juvenile salmonids downstream is potentially completely blocked as early as March of each year. Although some adult steelhead pass through the dam prior to the installation of flashboards, Chinook salmon adults moving into Willow Creek in the early summer months are completely blocked from upstream migration. Chinook have not been documented in the Willow Creek basin since the construction of the Huber and Royes dams.

Fish passage at these lower Willow Creek irrigation diversions has been a high priority identified as a significant limiting factor for the recovery of endangered Chinook and steelhead populations in the Upper Grande Ronde basin. The District has installed a concrete fishway at the lower Huber Dam during the summer of 2022. The Royes Dam is a flashboard weir that generally functions from April to October each year. When the flashboards are in the structure, an 8- to 10-foot barrier is created without a jump pool. During the season of operation this structure eliminates all salmonid migration. The District has secured the support of the 5 irrigators relying on the backwater from the Royes diversion dam to construct a rock ramp to back water up and eliminating the need for the dam structure. District staff and project partners have worked on fish passage at these sites for the past 20 years. For the first time in that span, the water users are on board to make fish passage a reality.

Fish passage design has focused on collecting data to inform the creation of individual pump sites at four different locations above the Royes Dam and eliminate the need for flashboard installation. The primary path of investigation is a roughened channel alternative. Survey data was collected at each site and hydraulic analysis performed to assure channel modifications will not lead to increased flooding and channel instability. Funding provided by ODFW allowed the District to complete project design to the 80% level. Funding deliverables for this Technical Assistance grant project will include final designs and all required permitting.
Account Type(s):
Expense
Contract Start Date:
07/01/2024
Contract End Date:
06/30/2025
Current Contract Value:
$64,659
Expenditures:
$26,071

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Project completed permitting A: 165. Environmental Compliance for Willow Creek Fish Passage design 06/30/2025
Implementation ready final designs B: 175. Willow Creek Fish Passage Final Design 06/30/2025
Effective implementation management and timely contract administration C: 119. Oversight of Design Contractor 06/30/2025

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 175 Produce Design
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 175 Produce Design
Lamprey, Pacific (Entosphenus tridentata)
  • 1 instance of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Environmental Compliance for Willow Creek Fish Passage design
B 175 Willow Creek Fish Passage Final Design 06/25/2024
C 119 Oversight of Design Contractor
D 132 Report - N/A
E 185 Quarterly Status Reports