Contract 95684: 1992-026-01 EXP UPPER GRANDE RONDE COMPLEX PH I ROAD RELOCATE
Project Number:
Title:
Grande Ronde Model Watershed
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Blue Mountain Grande Ronde 100.00%
Contract Number:
95684
Contract Title:
1992-026-01 EXP UPPER GRANDE RONDE COMPLEX PH I ROAD RELOCATE
Contract Continuation:
Previous: Next:
n/a
Contract Status:
Issued
Contract Description:
The Upper Grande Ronde River BSR UGR-20 is a critical and priority reach for ESA-listed spring-summer Chinook salmon and other aquatic resources and has been a focal restoration reach with multiple historic and recent actions implemented to enhance and restore habitat. The Confederated Tribes of the Umatilla Indian Reservation (CTUIR) and Wallowa-Whitman National Forest (WWNF) continue to collaborative in partnership to enhance and restore fishery resources and achieve River Vison and First Foods objectives in the Upper Grande Ronde basin.

The goal of project sponsors is to protect, enhance, and restore functional floodplain, channel, and watershed processes to provide sustainable and healthy habitat for aquatic First Food species.

Objectives are a means of achieving stated goals and include 1. Habitat protection and conservation, 2. Floodplain connectivity, 3. Channel morphology, 4. Instream structure and complexity, 5. Riparian restoration, 6. Water Quality, and 7. Fish passage.  

Realignment of sections of the USFS roads 5125/5138 along the Grande Ronde River supports future, broader restoration strategies that promote floodplain connectivity, expand wetland and riparain habitat, and promote alluvial processes that create and maintain quality spawning and rearing habitat.

1.07 miles of road (0.47 mi of NFSR 5125, 0.60 mi of NFSR 5138) will be relocated from the floodplain to locations above and/or at the toe of the historical floodplain to restore approximately 12 acres of the Grande Ronde River's floodplain.

The decommissioning of existing draw bottom road segments will not occur within this contract. They will remain in place to support future habitat restoration and enhancements and then decommissioned once those actions are complete.
Account Type(s):
Expense
Contract Start Date:
09/30/2024
Contract End Date:
12/31/2025
Current Contract Value:
$144,751
Expenditures:
$27,100

* Expenditures data includes accruals and are based on data through 31-Dec-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Iaa
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Environmental Compliance Completed A: 165. Environmental Compliance 08/01/2025
Road Relocated from Floodplain B: 33. Upper Grande Ronde River (RM 148.3 - 149.6): Relocation of USFS Roads 5125 & 5138 12/01/2025
Effective implementation management and timely contract administration C: 119. Project/Contract Administration 12/31/2025
Project Completion Report D: 132. Upper Grande Ronde Complex Phase 1 Road Relocate Completion report 12/31/2025

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 33 Decommission Road/Relocate Road
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 33 Decommission Road/Relocate Road
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 33 Decommission Road/Relocate Road

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Environmental Compliance
B 33 Upper Grande Ronde River (RM 148.3 - 149.6): Relocation of USFS Roads 5125 & 5138 07/23/2024
C 119 Project/Contract Administration
D 132 Upper Grande Ronde Complex Phase 1 Road Relocate Completion report
E 185 Quarterly Status Reports