Province | Subbasin | % |
---|---|---|
Blue Mountain | Grande Ronde | 100.00% |
Previous: | Next: |
---|---|
n/a |
* Expenditures data includes accruals and are based on data through 31-Oct-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Comply with all project permitting and HIP 4. | A: 165. Environmental Compliance for Catherine Creek Elmer Dam Passage & Flow Project | 10/01/2024 | ||
Elmer Dam Existing fishway removal | B: 85. Remove existing fishway and install 6 ft wide fishway - Elmer Dam - Catherine Creek RM 13.1 | 12/31/2026 | ||
Complete the new fishway | C: 184. Create new fish ladder the meets both state and federal standards - Elmer Fishway - Catherine Creek RM 13.1 | 12/31/2026 | ||
Complete erosion and sediment control | D: 55. Erosion and Sediment control | 12/31/2026 | ||
Construction Management Complete | E: 100. Construction Oversight/Management - Elmer Dam - Catherine Creek RM 13.1 | 12/31/2026 | ||
Effective implementation management and timely contract administration | F: 119. Habitat Implementation Contract Administration | 12/31/2026 | ||
Upload Elmer Dam Completion Report | G: 132. Elmer Dam Fishway, Dam modification and pump station Completion Report | 12/31/2026 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | Environmental Compliance for Catherine Creek Elmer Dam Passage & Flow Project | |||||||
B | 85 | Remove existing fishway and install 6 ft wide fishway - Elmer Dam - Catherine Creek RM 13.1 | 10/08/2024 | ||||||
C | 184 | Create new fish ladder the meets both state and federal standards - Elmer Fishway - Catherine Creek RM 13.1 | 10/08/2024 | ||||||
D | 55 | Erosion and Sediment control | 10/08/2024 | ||||||
E | 100 | Construction Oversight/Management - Elmer Dam - Catherine Creek RM 13.1 | |||||||
F | 119 | Habitat Implementation Contract Administration | |||||||
G | 132 | Elmer Dam Fishway, Dam modification and pump station Completion Report | |||||||
H | 185 | Quarterly Status Reports |