Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 96143: 2009-003-00 EXP UC HABITAT PROJECTS - DESIGN & CONSTRUCT
Project Number:
Title:
Upper Columbia Habitat Restoration
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Cascade Entiat 20.00%
Methow 40.00%
Wenatchee 40.00%
Contract Number:
96143
Contract Title:
2009-003-00 EXP UC HABITAT PROJECTS - DESIGN & CONSTRUCT
Contract Continuation:
Previous: Next:
56662 REL 300: 2009-003-00 EXP YN - UC HABITAT RESTORATION
Contract Status:
Issued
Contract Description:
This contract will fund the Yakama Nation Fisheries Upper Columbia Habitat Restoration Project to seek, design and implement fish habitat restoration projects throughout the Methow, Entiat, and Wenatchee subbasins for the Calendar Year 2025 performance period.  Administrative tasks related to this SOW, such as reporting and inventory management, are provided under BPA Contract CA 94920 (through 5/31/25, then tasks will transfer to the subsequent FY25 release).

This contract details salmon habitat restoration work being designed or implemented in the Upper Columbia Spring Chinook Salmon and Steelhead recovery area under the guidance of the Upper Columbia Spring Chinook Salmon and Steelhead Recovery Plan and the 2021 Habitat Restoration Prioritization.  Yakama Nation Fisheries uses project and ecological concern prioritizations contained within the 2021 Habitat Restoration Prioritization and within Habitat and Geomorphic Reach Assessments reviewed by the Upper Columbia Regional Technical Team to determine which project action types and locations to pursue.  At the project level, Yakama Nation Fisheries subcontracts with technical consultants to develop salmon habitat restoration actions that best address prioritized ecological concerns limiting salmon and steelhead productivity and abundance.  

Work Element actions in 2025 include:

REACH ASSESSMENT PROJECTS (2024/25 HABITAT ASSESSMENTS)

Methow Subbasin:
Methow River-Thompson Creek and Methow River-Fawn Creek Assessment Units - Methow River Reach Assessment Update (Weeman Bridge to Twisp)

Wenatchee Subbasin:
Middle and Lower Icicle Assessment Units - Icicle River Reach Assessment
Lower Nason Creek Assessment Unit - Nason Creek Reach Assessment Update
Chiwaukum Creek Assessment Unit - Chiwaukum Creek Reach Assessment
Lower White River Assessment Unit - Lower White River Reach Assessment

Entiat Subbasin:
Entiat River-Preston Creek and Entiat River-Potato Creek Assessment Units - Middle Entiat Reach Assessment Update

DESIGN PROJECTS (2025 ENGINEERING AND DESIGN PROJECTS)

Methow Subbasin:
Methow River-Fawn Creek Assessment Unit - Methow Basin EWD Instream Flow Project
Methow River-Thompson Creek Assessment Unit - W2 Foghorn Reach, 1890s Outlet, and Two Channels Project

Wenatchee Subbasin:
Lower Nason Creek Assessment Unit - Nason Creek N1 DOT Project, Upper Nason Phase 3, and Nason Creek Gill Creek
Lower Chiwawa River Assessment Unit - Lower Chiwawa Big Meadow
Lower White River Assessment Unit - White River CDLT

Entiat Subbasin:
Entiat River-Preston Creek - Assessment Unit - Entiat 3D CDLT
Mad River Assessment Unit - Mad River (USFS) Projects, Mad River Outlet, MRO Instream Flow Project

RESTORATION ACTIONS (2024 CONSTRUCTION ACTIONS)

Methow Subbasin:
Lower Twisp Assessment Unit - Newby Narrows Phase 2

Entiat Subbasin:
Nothing Planned in 2025

Wenatchee Subbasin:
Wenatchee River-Nahahum Canyon Assessment Unit - Lower Wenatchee River Reach 3
Lower Chiwawa River Assessment Unit - Lower Chiwawa USFS Phase 2

For all three subbasins, this contract also details a scope of work for continuing to partner with the United States Forest Service to implement salmon recovery actions on USFS managed lands.  Through a cooperative agreement with the USFS, the Yakama Nation provides some cost reimbursement coverage to the USFS for federal staff costs on conducting NEPA and environmental compliance review on Yakama Nation sponsored projects.
Account Type(s):
Expense
Contract Start Date:
01/01/2025
Contract End Date:
12/31/2025
Current Contract Value:
$4,216,238
Expenditures:

* Expenditures data includes accruals and are based on data through 31-Dec-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Shannon Adams Yakama Confederated Tribes No Supervisor adas@yakamafish-nsn.gov (509) 945-0754
Brenda Aguirre Bonneville Power Administration Yes Env. Compliance Lead baguirre@bpa.gov (503) 230-5928
James Albani Yakama Confederated Tribes Yes Technical Contact albj@yakamafish-nsn.gov (651) 341-3211
Victoria Bohlen Bonneville Power Administration Yes COR vlbohlen@bpa.gov (503) 230-3506
Chris Butler Yakama Confederated Tribes Yes Technical Contact butlerc@yakamafish-nsn.gov (509) 449-8215
Annet Dillman Yakama Confederated Tribes Yes Administrative Contact dila@yakamafish-nsn.gov (509) 865-2255
Madeleine Eckmann Yakama Confederated Tribes Yes Technical Contact eckm@yakamafish-nsn.gov (509) 449-2091
Timothy Hanrahan Bonneville Power Administration Yes F&W Approver TPHanrahan@bpa.gov (503) 230-3938
Lindsay Henning Yakama Confederated Tribes Yes Technical Contact henl@yakamafish-nsn.gov (509) 860-5351
Tana Hoptowit (Admin Lead) Yakama Confederated Tribes Yes Administrative Contact hopt@yakamafish-nsn.gov (509) 865-5121x6318
Tamera Hoptowit Yakama Confederated Tribes Yes Administrative Contact Hopta@yakamafish-nsn.gov (509) 865-5121x6354
James Hudson Yakama Confederated Tribes Yes Technical Contact hudj@yakamafish-nsn.gov (509) 907-0538
Jarred Johnson Yakama Confederated Tribes Yes Technical Contact johj@yakamafish-nsn.gov (509) 881-1462
Jessica Power Bonneville Power Administration Yes CO Assistant jdpower@bpa.gov (503) 230-4023
Brandon Rogers Yakama Confederated Tribes Yes Supervisor rogb@yakamafish-nsn.gov (509) 949-4109
Hans Smith Yakama Confederated Tribes Yes Contract Manager h.smith@methownet.com (509) 449-2750
Elizabeth Witkowski Yakama Confederated Tribes Yes Technical Contact wite@yakamafish-nsn.gov (509) 881-7091
Karen Wolfe Bonneville Power Administration Yes Contracting Officer ktwolfe@bpa.gov (503) 230-3448
Benjamin Woodworth Yakama Confederated Tribes Yes Technical Contact woob@yakamafish-nsn.gov (360) 920-9544


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Effective implementation management and timely contract administration B: 119. Perform project management and administrative duties 12/31/2025
USFS Environmental Compliance on Yakama Nation Fisheries Projects D: 165. FY25 USFS NEPA 2017-164 12/31/2025
Confidential Water Rights Evaluation E: 154. Methow Basin EWD Instream Flow Project - Water Rights Assessment 2015-152 12/31/2025
Permit Level and Final Designs for the Methow Basin EWD Instream Flow Project F: 175. Methow Basin EWD Instream Flow Project - Eng. and Design Phase 3 & 4 - 2015-152 12/31/2025
Permit Level and Final Designs and Report for the W2 Foghorn Project Area G: 175. W2 Foghorn Reach Design Phases 3 and 4 - 2023-219 12/31/2025
Conceptual Designs and Report for the 1890s Outlet Project H: 175. 1890s Outlet Conceptual Design - 2011-65 12/31/2025
Conceptual Designs and Report for the Two Channels Area I: 175. Two Channels Conceptual Design - 2011-89 12/31/2025
Final Reach Assessment Report Completed J: 115. Methow River Reach Assessment Updates (Big Valley & M2) - 2023-220 12/31/2025
Nason Creek N1 DOT Permit and Construction Level Designs K: 175. Nason Creek N1 DOT Design Phase 3 and 4 - 2018-198 12/31/2025
Draft and Final Construction Plan for the Upper Nason Phase 3 Project L: 175. Upper Nason Creek Side Channel Redesign Phases 3 & 4 2020-207 12/31/2025
Lower Chiwawa Big Meadow Permit and Construction Level Designs M: 175. Lower Chiwawa Big Meadow (Areas B and C) Phases 3 and 4 - 2021-214 12/31/2025
Complete Groundwater Testing N: 208. Lower Chiwawa Big Meadow (Areas B and C) Groundwater Testing 2021-214 12/31/2025
Conceptual Designs Report for the Nason Creek Gill Creek Reconnection Project O: 175. Nason Creek Gill Creek Reconnection Conceptual Design - 2024-223 12/31/2025
Conceptual Designs Report for the White River Conceptual Design (CDLT) Project P: 175. White River CDLT Conceptual Design - 2024-224 12/31/2025
Nason Creek, Icicle Creek, Chiwaukum Creek, and White River reports completed Q: 115. Wenatchee Subbasin Reach Assessments (Nason Creek, Icicle, White River, Chiwaukum) - 2023-221 12/31/2025
Permit and Construction Level Designs for the Mad River Outlet Project Area R: 175. Mad River Outlet Design Phases 3 & 4 - 2021-215 12/31/2025
Confidential Water Rights Evaluation S: 154. Entiat Basin MRO Instream Flow Project - Water Rights Consulting 2022-217 12/31/2025
Alternative Water Delivery Feasibility Assessment T: 175. Entiat Basin MRO Instream Flow Project - Eng. Feasibility Assessment 2022-217 12/31/2025
Complete Groundwater Testing U: 208. Entiat Basin MRO Instream Flow Project Groundwater Testing 2022-217 12/31/2025
Draft Construction Plan for the Entiat 3D CDLT Project Area V: 175. Entiat 3D CDLT Design Phase 3 - 2019-210 12/31/2025
Complete Groundwater Testing W: 208. Entiat 3D CDLT Design Phase 3 Groundwater Testing - 2024-225 12/31/2025
Final Reach Assessment Report Completed X: 115. Middle Entiat Reach Assessment Updates (Grey, Stormy, Preston Reaches) - 2023-222 12/31/2025
Construction Management Complete Y: 100. Newby Narrows Oversight 2015-153 12/31/2025
Side Channel Restoration and Large Wood Habitat added into 0.3 miles of the Twisp River. Z: 30. Newby Narrows Construction 2015-153 12/31/2025
Complete Side Channel Adaptive Management Activities AA: 186. Methow Side Channels Adaptive Management (Chewuch WDFW & Newby) 2024-225 09/01/2025
Construction Management Complete AB: 100. Lower Wenatchee River Reach 3 Oversight - 2017-186 12/31/2025
Construction Management Complete AD: 100. Lower Chiwawa USFS (Area G) Phase 2 Oversight 2021-214 12/31/2025
Side Channel Restoration and Large Wood Habitat added into 0.7 miles of the Chiwawa River AE: 30. Lower Chiwawa USFS (Area G) Phase 2 Construction 2021-214 12/31/2025

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 2 instances of WE 30 Realign, Connect, and/or Create Channel
  • 3 instances of WE 115 Produce Inventory or Assessment
  • 12 instances of WE 175 Produce Design
  • 2 instances of WE 154 Develop and Negotiate Water Right Transaction
  • 3 instances of WE 100 Construction Management
  • 3 instances of WE 208 Irrigation Infrastructure Construction or Replacement
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 175 Produce Design
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 2 instances of WE 30 Realign, Connect, and/or Create Channel
  • 3 instances of WE 115 Produce Inventory or Assessment
  • 10 instances of WE 175 Produce Design
  • 2 instances of WE 154 Develop and Negotiate Water Right Transaction
  • 3 instances of WE 100 Construction Management
  • 3 instances of WE 208 Irrigation Infrastructure Construction or Replacement
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA
B 119 Perform project management and administrative duties
C 132 No deliverable - Annual report is provided under partner contract
D 165 FY25 USFS NEPA 2017-164
E 154 Methow Basin EWD Instream Flow Project - Water Rights Assessment 2015-152
F 175 Methow Basin EWD Instream Flow Project - Eng. and Design Phase 3 & 4 - 2015-152
G 175 W2 Foghorn Reach Design Phases 3 and 4 - 2023-219
H 175 1890s Outlet Conceptual Design - 2011-65
I 175 Two Channels Conceptual Design - 2011-89
J 115 Methow River Reach Assessment Updates (Big Valley & M2) - 2023-220
K 175 Nason Creek N1 DOT Design Phase 3 and 4 - 2018-198
L 175 Upper Nason Creek Side Channel Redesign Phases 3 & 4 2020-207
M 175 Lower Chiwawa Big Meadow (Areas B and C) Phases 3 and 4 - 2021-214
N 208 Lower Chiwawa Big Meadow (Areas B and C) Groundwater Testing 2021-214
O 175 Nason Creek Gill Creek Reconnection Conceptual Design - 2024-223
P 175 White River CDLT Conceptual Design - 2024-224
Q 115 Wenatchee Subbasin Reach Assessments (Nason Creek, Icicle, White River, Chiwaukum) - 2023-221
R 175 Mad River Outlet Design Phases 3 & 4 - 2021-215
S 154 Entiat Basin MRO Instream Flow Project - Water Rights Consulting 2022-217
T 175 Entiat Basin MRO Instream Flow Project - Eng. Feasibility Assessment 2022-217
U 208 Entiat Basin MRO Instream Flow Project Groundwater Testing 2022-217
V 175 Entiat 3D CDLT Design Phase 3 - 2019-210
W 208 Entiat 3D CDLT Design Phase 3 Groundwater Testing - 2024-225
X 115 Middle Entiat Reach Assessment Updates (Grey, Stormy, Preston Reaches) - 2023-222
Y 100 Newby Narrows Oversight 2015-153
Z 30 Newby Narrows Construction 2015-153
AA 186 Methow Side Channels Adaptive Management (Chewuch WDFW & Newby) 2024-225
AB 100 Lower Wenatchee River Reach 3 Oversight - 2017-186
AC 29 Lower Wenatchee River Reach 3 Construction - 2017-186
AD 100 Lower Chiwawa USFS (Area G) Phase 2 Oversight 2021-214
AE 30 Lower Chiwawa USFS (Area G) Phase 2 Construction 2021-214