2002-035-00 EXP GILLIAM COUNTY RIPARIAN BUFFERS
Contract Start Date:
7/1/2018
Contract End Date:
6/30/2019
Title:
D: 40 - New CCRP/CREP Agreement with Landowners, NRCS, SWCD & FSA
Description:
A new CREP agreement will be developed and signed resulting in new riparian fence exclosure funded through the FSA. BPA funding is utilized only to cover CREP technician time for conducting outreach, preparing the conservation plan, and providing technical assistance prior to and during implementation. Fencing installation and other management actions are funded by the FSA through a contract with the landowner. The landowner is responsible for all implementation.

A completed water survey form will be uploaded if water rights are associated with the CREP buffer.
WE Agreement Type:
Contracted
Deliverable Specification:
A CREP Plan detailing new riparian fence enclosures is completed and approved for funding. Funding is provided by FSA.

Under this CREP Conservation Plan approximately .5 miles of stream will be protected on Ferry Canyon Creek for 15 years. This project does not enroll anadromous fish habitat. However, it is above critical habitat The District and ODFW believe that this project will have cumulative effects on downstream habitat by reducing sediment inputs and shading surface water. Thereby improving water quality.
WSE Effective Budget:
$5,024
% of Total WSE Effective Budget:
6.75%
WSE Start:
07/01/2018
WSE End:
06/30/2019
WSE Completion:
WSE Progress:
Other
WSE ID Continued From:
[Unassigned]
WSE ID Continued To:
[Unassigned]
Finite or Recurring:
Finite

SOWRevision Planned Updated Contractor Comments (optional) BPA Comments (optional)
Work Element Budget (Current Performance Period) $5,024 $5,024

12 Milestones
Sort Type Title Start End Status Modified By Modified Date
A EC Environmental compliance requirements complete 7/1/2018 7/30/2018 Concluded Jesse Wilson 4/16/2018 3:14:18 PM
Description: On-the-ground work associated with this work element cannot proceed until this milestone is complete. Milestone is complete when final documentation is received from BPA environmental compliance staff.
B Landowner Eligibility Assessed 7/1/2018 6/30/2019 Concluded Jesse Wilson 6/15/2018 1:04:01 PM
Description: Determine eligibility for program based on confirmation of anadromous species presence or direct benefit as confirmed by ODFW district biologist. Forms detailing andromous species presence or direct benefits to downstream habitats will be uploaded to the contract documents or included in the annual report.
C Obtain Landowner Sign Up 7/1/2018 6/30/2019 Concluded Jesse Wilson 6/15/2018 1:04:01 PM
Description: Landowner signs onto the program via completion of a USDA CRP2 form.
D Obtain Services Of Cultural Resource Specialist 7/1/2018 6/30/2019 Concluded Jesse Wilson 6/15/2018 1:04:01 PM
Description: Follow USDA NRCS procedures in requesting cultural resource specialist review of proposed buffer sites. USDA approved Cultural Resource Specialists will be used for these reviews.
E Prepare Inventories & Assessments 7/1/2018 6/30/2019 Concluded Jesse Wilson 6/15/2018 1:04:01 PM
Description: Prepare inventory assessments for landowners site.
F Prepare Biological Evaluation 7/1/2018 6/30/2019 Concluded Jesse Wilson 6/15/2018 1:04:01 PM
Description: Follow USDA NRCS procedures in developing a biological evaluation for each buffer plan.
G Complete & Submit NRCS Environmental Checklists 7/1/2018 6/30/2019 Concluded Jesse Wilson 6/15/2018 1:04:01 PM
Description: NRCS Environmental Checklists completed by CREP technician.
H Develop Conservation Plan 7/1/2018 6/30/2019 Concluded Jesse Wilson 6/15/2018 1:04:01 PM
Description: Prepare designs and specifications for planting prescriptions, fencing design, off stream water development or other conservation practice elements.
I Conservation Plan Approved and Contract Executed 7/1/2018 6/30/2019 Active Jesse Wilson 6/15/2018 1:04:01 PM
Description: The CREP Conservation Plan is approved by the FSA and a contract executed between the FSA and landowner for plan implementation.
J Provide Implementation Technical Assistance 7/1/2018 6/30/2019 Active Jesse Wilson 6/15/2018 1:04:01 PM
Description: Provide technical assistance for implementation of conservation plan.
K Attach a completed water survey form in Pisces 7/1/2018 6/30/2019 Active Jesse Wilson 6/15/2018 1:04:01 PM
Description: Attach a completed water survey form for projects that have water rights associated with the CREP buffer. If no water rights are associated with the CREP buffer a survey from is not required. The water survey form is located at: https://www.cbfish.org/EfwDocument.mvc/DownloadFile/17.
L DELIV CREP Plan Developed and Approved 6/30/2019 Active Jesse Wilson 6/15/2018 1:06:30 PM
Description: A CREP Plan detailing new riparian fence enclosures is completed and approved for funding. Funding is provided by FSA. Under this CREP Conservation Plan approximately .5 miles of stream will be protected on Ferry Canyon Creek for 15 years. This project does not enroll anadromous fish habitat. However, it is above critical habitat The District and ODFW believe that this project will have cumulative effects on downstream habitat by reducing sediment inputs and shading surface water. Thereby improving water quality.

Work Site ID Latitude Longitude State County Province Subbasin
93923 45.272935 -120.311469 Oregon Gilliam Columbia Plateau John Day

Primary Focal Species:
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
Secondary Focal Species:
Trout, Interior Redband (O. mykiss gairdnerii)

This work element does not require RM&E metadata