SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
Work Element Budget (Current Performance Period) | $8,709 | $8,709 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | EC | Environmental compliance requirements complete | 3/1/2008 | 3/1/2008 | Concluded | Pamela Nelle | 12/3/2007 3:07:44 PM |
Description: On-the-ground work associated with this work element cannot proceed until this milestone is complete. Milestone is complete when final documentation is received from BPA environmental compliance staff (completion can be based on pre-existing environmental documentation from BPA). | |||||||
B | Landowner contacts for landowner permission | 5/1/2008 | 2/28/2009 | Concluded | Pamela Nelle | 12/3/2007 3:07:45 PM | |
Description: Secure permission for access, establishment of habitat monitoring sites and on going monitoring. | |||||||
C | Planning Unit Information sharing/meeting | 10/5/2008 | 10/5/2008 | Concluded | Pamela Nelle | 12/3/2007 3:07:47 PM | |
Description: Utilize quarterly Entiat Watershed Planning Unit meetings to provide information and monitoring updates | |||||||
D | Informational mailings and newsletter articles | 6/1/2008 | 2/28/2009 | Concluded | Pamela Nelle | 12/3/2007 3:07:50 PM | |
Description: Prepare and disseminate monitoring projects information and updates | |||||||
E | Technical Coordination Meetings | 6/1/2008 | 2/28/2009 | Concluded | Pamela Nelle | 12/3/2007 3:07:51 PM | |
Description: Attend 3 technical coordination meetings with Upper Columbia Salmon Recovery Board (UCSRB) Regional Technical Team (RTT) members and partners monitoring agency staff to review progress and results. Meetings will likely be held in either Chelan and Wenatchee. | |||||||
F | DELIV | Coordination of Entiat habitat restoration project monitoring | 2/28/2009 | Concluded | Pamela Nelle | 12/3/2007 3:22:05 PM | |
Description: Deliverables will include: - landowner access agreement forms - copies of newsletter articles and mailings - meeting agendas and minutes, as appropriate |
Metric | Planned | Actual | Contractor Comments | Measures | HLIs |
---|---|---|---|---|---|
1464. Primary R, M, and E Focal Strategy [Population Status, Hydrosystem, Tributary Habitat, Estuary/Ocean, Harvest, Hatchery, Predation, Multiple Strategies] | Tributaries | Tributary Habitat | |||
1472. Primary R, M, and E Type [Status and Trend Monitoring, Action Effectiveness Research, Uncertainties Research, Project Implementation/ Compliance Monitoring] | Action Effectiveness Monitoring | Action Effectiveness Monitoring | |||
1478. Secondary R, M, and E Type [Status and Trend Monitoring, Action Effectiveness Research, Uncertainties Research, Project Implementation/ Compliance Monitoring] | Action Effectiveness Monitoring | Action Effectiveness Monitoring |
Work Site ID | Latitude | Longitude | State | County | Province | Subbasin |
---|---|---|---|---|---|---|
13180 | 47.668865 | -120.296696 | Washington | Chelan | Columbia Cascade | Entiat |
Study Plan Name | Study Plan Owner | Protocol State | Sample Design Name |
---|---|---|---|
BPA Fish and Wildlife Program Monitoring v1.0 | Russell Scranton | Draft | Entiat habitat restoration project monitoring - Cascadia Conservation District 1 v1.0 |