SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
Work Element Budget (Current Performance Period) | $16,117 | $16,117 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | Schedule/Hold periodic conference calls between contractors | 12/1/2009 | 11/30/2010 | Concluded | Nick Bouwes (Inactive) | 10/7/2009 10:51:11 AM | |
Description: ELR will schedule periodic conference calls between ODFW and other contractors to ensure consistent communication and project implementation. ELR will provide meeting minutes for each call to cooperators. | |||||||
B | Participate in Middle Fork and Bridge Creek IMW workgroup meetings. | 12/1/2009 | 11/30/2010 | Concluded | Nick Bouwes (Inactive) | 10/7/2009 10:51:12 AM | |
Description: Scheduled periodic meetings will be conducted to ensure cooperators and other interested agencies in the John Day River subbasin are kept up to date on project administration, technical issues, analysis, and project reporting. Members of this workgroup will include ISEMP contractors, collaborating projects, and other land management and regulatory agencies that are within the John Day River subbasin. ELR will provide meeting minutes to all cooperators. | |||||||
C | Produce ISEMP Field/Laboratory Protocol Guidelines | 12/1/2009 | 5/1/2010 | Concluded | Nick Bouwes (Inactive) | 10/7/2009 10:51:12 AM | |
Description: ELR with assistance from other contractors will produce a consistent field and laboratory protocol set for all sampling programs used by the ISEMP John Day subbasin project. | |||||||
D | DELIV | ISEMP John Day Subbasin Coordination (ELR) | 11/30/2010 | Concluded | Nick Bouwes (Inactive) | 10/6/2009 6:39:41 PM | |
Description: ELR staff will organize and participate in periodic conference calls and meetings to coordinate the John Day Subbasin project. These meetings will be either electronic (phone or email) or in locations throughout Oregon specific to the Projects cooperators including, Portland, Corvallis, John Day, Pendleton and other locations as necessary in the state. ELR staff will also produce standard field/laboratory protocols for all subbasin cooperators. |