This page provides details of the selected work element.
SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
1. 52672 (04/15/2011 - 12/31/2011) | $24,150 | $6,800 | ||
Work Element Budget (Current Performance Period) | $24,150 | $6,800 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | Integration design, workflow procedures, and wireframes for RBT interaction | 5/15/2011 | 8/30/2011 | Concluded | Sharon Grant (Inactive) | 5/27/2011 9:03:04 AM | |
Description: The integration design will specify how the CHaMP data system will call RBT and format of all data that must be sent to RBT. The workflow procedures will define required tasks, define which system is responsible for each task, order of tasks, and inputs, outputs, and constraints for each task. The wireframe diagrams will define the specifics of form layout, interaction design, and logic constraints for web forms. These specifications direct the work of the technical architect and application engineers. These specifications will be produced by the EDS business analyst and Sitka engagement manager. | |||||||
B | DELIV | Scripts to run River Bathymetry Tool (RBT) | 11/30/2011 | Concluded | Sharon Grant (Inactive) | 5/27/2011 9:03:04 AM | |
Description: - Database and file structure to store derived site-level metrics - Scripts to summarize auxiliary field data - Scripts to call RBT through an advanced programming interface (API) and point RBT to the appropriate digital elevation model and summary metrics for auxiliary data |