Title | Link |
---|---|
NONE - No data repository or not electronically available | N/A |
This page provides details of the selected work element.
SOWRevision | Planned | Updated | Contractor Comments (optional) | BPA Comments (optional) |
---|---|---|---|---|
Work Element Budget (Current Performance Period) | $7,961 | $6,873 |
Sort | Type | Title | Start | End | Status | Modified By | Modified Date |
---|---|---|---|---|---|---|---|
A | Update current inventory | 7/1/2012 | 6/30/2013 | Concluded | Janet Hohle (Inactive) | 3/14/2012 3:34:11 PM | |
Description: Update and amend existing inventory as appropriate. Interview agencies staffs for information on restoration work and review relative to subbasin plans. | |||||||
B | Update monitoring information | 7/1/2012 | 6/30/2013 | Concluded | Janet Hohle (Inactive) | 3/14/2012 4:56:44 PM | |
Description: Update monitoring information in inventory to include: type of monitoring, location, duration of data collection and agency conducting the work. This is not intended to be a collection of monitoring data. | |||||||
C | DELIV | Updated Clearwater Subbasin Inventory | 6/30/2013 | Concluded | Janet Hohle (Inactive) | 3/14/2012 3:33:49 PM | |
Description: Survey agencies and organizations that implement habitat restoration projects and conduct monitoring in the subbasin to update the subbasin inventory database. Information collected may include the following: project title and location, sponsor, funding source(s), population group for steelhead, management plan objectives addressed by action, BiOp/recovery plan connection, and Bonneville project number if applicable. |
Title | Link |
---|---|
NONE - No data repository or not electronically available | N/A |