Show new navigation
On
Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
Select a work element:
Contract Number:
Contract Title:
2003-017-00 EXP RM&E PILOT PROJECT - NOAA FISHERIES (PROJ MGT)
Contract Start Date:
11/1/2005
Contract End Date:
9/30/2006
Title:
G: 160 - Compile GIS data layers - John Day
Description:
In addition to the coordination of the design work described above, the PI will also have the primary responsibility for coordinating any data collection efforts necessary to support the development of RME project design(s). Data collection during Phase I, that that precedes the implementation of the RME project design, will be of two basic types: preliminary data collection necessary to scope program design issues, and critical ongoing baseline data collection. The PI will identify the possibilities and needs for data collection during Phase I, and will work with the TOC and coordinator(s) to develop statements-of-work and budgets for implementation contracts with relevant individuals and agencies.
--Compilation of GIS data layers for pilot subbasins
Compile existing GIS data layers for pilot subbasins by working w/ all participating Agencies and individuals as defined by the PI, TOC and coordinator. The data layers to be compiled will be identified by the PI, TOC and coordinator. These data layers are those necessary to perform the statistical sampling site selection process in each subbasin, as well as, the data layers necessary to stratify / classify the monitoring data collection efforts.
WE Agreement Type:
Contracted
Deliverable Specification:
For each pilot subbasin this subtask will produce a data set consisting of all available GIS data layers required for the monitoring program design and initial implementation.
WSE Effective Budget:
$15,121
% of Total WSE Effective Budget:
2.46%
WSE Start:
11/01/2005
WSE End:
09/30/2006
WSE Completion:
09/30/2006
WSE Progress:
Concluded
WSE ID Continued From:
n/a
WSE ID Continued To:
n/a
Finite or Recurring:
Recurring

SOWRevision Planned Updated Contractor Comments (optional) BPA Comments (optional)
Work Element Budget (Current Performance Period) $15,121 $15,121

2 Milestones
Sort Type Title Start End Status Modified By Modified Date
A DELIV Develop GIS data layers or John Day Basin 9/30/2006 Concluded 11/2/2005 7:08:48 AM
Description: For each pilot subbasin this subtask will produce a data set consisting of all available GIS data layers required for the monitoring program design and initial implementation.
B Deliver GIS data layers for John Day River Basin 11/1/2005 9/30/2006 Concluded 11/2/2005 7:08:49 AM
Description: Make GIS data layers developed for John Day River basin available on project or BPA web site. For each pilot subbasin this subbask will produce a data set consisting of all available GIS data layers required for the monitoring program design and initial implementation.

Implementation Metrics
None

This work element does not require Focal Species