Assessment Number: 1983-435-00-NPCC-20090924
Project: 1983-435-00 - Umatilla Hatchery Satellite Facilities Operations and Maintenance (O&M)
Review: FY07-09 Solicitation Review
Approved Date: 10/23/2006
Recommendation: Fund
Comments: The project sponsors are to work with the Council and others to structure an ISRP/Council review of the coordinated subbasin activities in the Umatilla at some point in the next two years.. The budget adjustment reflects that the original proposal had embedded in its budget a contract to Little White Hatchery for $147,000 to produce 210k spring chinook. This production will shift to the Umatilla Hatchery. However, a $40,000 contract is required to finish production on hand in FY07.