Description | Latitude | Longitude |
---|---|---|
From river mile 3 to 12 on the Birch Cr., river mile 1 on W. Fk. Birch Cr., headwaters of E. F,. Birch Cr., and river miles 2.7-20.2, Meacham Cr., Umatilla County | 45 37 | 118 45 |
From river miles 80-89 of the upper Umatilla River, Umatilla County | 45 43 | 118 15 |
Short Objective | Detailed Objective | Strategy | Subbasin Plan |
---|---|---|---|
Increase the no. of steelhead in Birch Cr. | Identify, coordinate, and manage at least six new habitat iprovement projects for the Umatilla River Subbasin... | 2) Facilitate landowners leasing of water rights for instream purposes. 3) Increase water conservation & irrigation efficiency. 5) Place LWD & boulders. 6) Fence & plant riparian 13) Increae ... | Umatilla |
Increase the no. of steelhead in Meacham Cr. | Increase the number of summer steelhead spawning redds in the Meacham Creek watershed by 20% by 2010 | 5) Place LWD & boulders 6) Plant riparian zones. 7) Modify channel & flood-plain function 9) Eliminate dikes in ripararian areas. 10) Increase protective status of habitats. 12) Restore headwa... | Umatilla |
Determine haitat improvements in upper Umatilla R. | Determine the location and type of needed habitat improvement in Umatilla River RM 80-90 by 2009 | 7) Modify channel flood-plain function; 10) Increase protective status of priority habitats; 12)Restore headwater attributes to improve downstream conditions... | Umatilla |
Maintain previously implemented habitat improvemen | Repair fences, maintain vegetative plantings, control weeds, and clear debris from previously implemented improvements on 55 easements.... | Maintain fences & replant riparian zones; Modify detrimental land use activities, e.g., weed control; Maintain passage dfficiency through ongoing )&M activities.... | None |
Conduct environmental monitoring | Monitor during and after project implementation to comply with permit terms and to evaluate project long-term effects.... | For implementation monitoring of new projects, select parameters & periodicity to comply with env'r permit terms. For effectiveness monitoring select sites and parameters for previous projects tha... | Umatilla |
[BO Title left blank] | [BO Description left blank] | [Strategy left blank] | None |
Line Item | Notes | FY07 Cost | FY08 Cost | FY09 Cost |
---|---|---|---|---|
Personnel | Includes 5 percent merit increase annually during the project period. | $144,200 | $151,410 | $158,980 |
Fringe Benefits | 35 percent of salary. | $50,470 | $52,994 | $55,643 |
Supplies | Includes 2.5 percent inflation factor. | $9,000 | $9,225 | $9,455 |
Travel | Reflects anticipated 5 percent increase each project year. | $11,000 | $11,550 | $12,125 |
Capital Equipment | Reflects 2.5 inflation factor. | $5,000 | $5,125 | $5,250 |
Overhead | Reflects rate of 0.3946 | $86,682 | $87,241 | $95,277 |
Other | Professional services with 2.5 percent inflation factor | $12,000 | $12,300 | $12,610 |
Other | Subcontracts with 2.5 percent inflation factor | $53,893 | $55,240 | $56,620 |
WE ID | WE Name | Title | Budget | Start Date | End Date | Objectives | Metrics |
---|---|---|---|---|---|---|---|
92 | Lease Land | Consummate Easements with Private Landowners | $50,000 | 02/01/2007 | 02/01/2009 | * # of riparian miles protected: 2 * # of acres of new lease: 40 | |
22 | Maintain Vegetation | Maintain Zones 1 & 2 Shrub and Tree Plantings | $30,000 | 07/01/2007 | 09/15/2009 | ||
34 | Develop Alternative Water Source | B & G Resources Wells/Troughs | $20,000 | 05/01/2007 | 08/01/2009 | ||
47 | Plant Vegetation | Plant Native Grasses on B & G Easement | $10,000 | 02/01/2007 | 03/15/2009 | * # of acres of planted: 100 * # of acres of planted: 100 acres | |
53 | Remove vegetation | Control Weeds on Existing and New Easements | $75,000 | 04/01/2007 | 05/15/2009 | * # of acres treated: 500 acres | |
99 | Outreach and Education | Participation with Other Entities in Advisory and Educational Activities | $30,000 | 02/01/2007 | 09/30/2009 | * # of students reached: 300 | |
114 | Identify and Select Projects | Identify, Prioritize, and Select Projects | $21,000 | 10/01/2007 | 09/30/2009 | ||
118 | Coordination | Coordination with Other Agencies and Organizations | $30,000 | 10/01/2007 | 09/30/2009 | ||
119 | Manage and Administer Projects | Administrative Activities for Project Support | $81,074 | 10/01/2007 | 09/30/2009 | ||
122 | Provide Technical Review | Review of Plans and Proposals | $15,000 | 10/01/2007 | 09/30/2009 | ||
132 | Produce Annual Report | Draft and Finalize Annual Report | $30,000 | 01/15/2008 | 09/30/2009 | ||
141 | Produce Status Report | Status Reports | $15,000 | 05/30/2007 | 09/30/2009 | ||
157 | Collect/Generate/Validate Field and Lab Data | Collect Temperature, Suspended Solids, and Benthic Data | $12,000 | 05/01/2007 | 09/30/2009 | Focal Area: 10 tributaries | |
162 | Analyze/Interpret Data | Analyze/Interpret Temperature, SS, and Benthic Data | $6,000 | 09/01/2007 | 09/30/2009 | Focal Area: 10 tributaries | |
165 | Produce Environmental Compliance Documentation | Historical Preservation Clearance | $24,000 | 01/01/2007 | 01/01/2009 | ||
165 | Produce Environmental Compliance Documentation | Prepare NEPA Checklist and Biological Assessment (BA) | $35,000 | 01/01/2007 | 05/01/2009 | ||
165 | Produce Environmental Compliance Documentation | State Lands Department Permit | $15,000 | 01/01/2007 | 05/01/2009 | ||
165 | Produce Environmental Compliance Documentation | USCE Section 404 Permits for instream improvements. | $35,000 | 01/01/2007 | 05/01/2009 | ||
174 | Produce Plan | Improvement Plans for new Birch, Meacham, and upper Umatilla R. sites. | $60,000 | 01/01/2007 | 03/15/2008 | ||
174 | Produce Plan | Plan for McKay Creek Property (Cunningham Sheep Property) | $5,000 | 01/01/2007 | 04/01/2007 | ||
85 | Remove/Modify Dam | Remove diversion dam on mainstem Birch Cr. | $30,000 | 07/01/2008 | 09/01/2008 | * # of miles of habitat accessed: 80 miles | |
85 | Remove/Modify Dam | Remove or modify fish passage barrier | $45,000 | 07/15/2008 | 07/15/2009 | * # of miles of habitat accessed: 80 miles | |
85 | Remove/Modify Dam | Remove irrigation diversion dam | $42,000 | 07/15/2007 | 09/15/2007 | ||
85 | Remove/Modify Dam | Remove rock or other barriers to salmonid fish passage | $60,000 | 08/01/2007 | 08/01/2009 | * # of miles of habitat accessed: 15 miles | |
29 | Increase Instream Habitat Complexity | Install large woody debris | $100,000 | 06/01/2007 | 08/31/2009 | * # of structures installed: 60 | |
40 | Install Fence | Install fencing for livestock exclusion on three easements. | $84,000 | 04/01/2007 | 08/01/2009 | * # of miles of fence: 22 miles | |
34 | Develop Alternative Water Source | Install wells/pumps to replace irrigation dam diversions. | $60,000 | 08/01/2007 | 08/31/2009 | ||
47 | Plant Vegetation | Plant riparian vegetation on new and existing easements. | $92,216 | 02/15/2007 | 02/28/2009 | * # of acres of planted: 200 acres | |
186 | Operate and Maintain Habitat/Passage | Maintain salmonid passage facilities by debris removal as needed. | $10,000 | 03/01/2007 | 04/30/2009 | ||
98 | Other | Maintain fencing on existing easements | $21,000 | 03/15/2007 | 04/30/2009 | ||
174 | Produce Plan | Conduct assessment and prepare plan for habitat improvements in the upper Umatilla River. | $20,000 | 02/01/2008 | 01/31/2009 |
Date | Reviewer | Short Recommendation | Comments | FY07 | FY08 | FY09 | |
---|---|---|---|---|---|---|---|
06/02/2006 | ISRP | Response requested | This proposal is an improvement over past proposals. Nonetheless, the proposal is deficient in a number of areas. The various tasks and objectives need to be considered individually. Not much priorit... More | N/A | N/A | N/A | |
08/31/2006 | ISRP | Not fundable (Qualified) | Because of the high level of management intervention (pumping, trucking, hatchery releases), the Umatilla projects need to be reviewed as an integrated program. This program is not currently scientif... More | N/A | N/A | N/A | |
09/15/2006 | NPCC | $326,000.00 | $326,000.00 | $326,000.00 | |||
10/23/2006 | NPCC | Fund | See decision memo discussion of the Umatilla subbasin projects. | $326,000.00 | $326,000.00 | $326,000.00 |