Show new navigation
On
Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
RSS Feed for updates to Project 2007-127-00 - East Fork of South Fork Salmon River Passage Restoration Follow this via RSS feed. Help setting up RSS feeds?

View 2007-2009 Proposal

Project 2007-127-00 - East Fork of South Fork Salmon River Passage Restoration
Project Number:
2007-127-00
Agency, Institution or Organization:
Nez Perce Tribe DFRM Watershed Division
Short Description:
This project will reestablish fish passage through a 30-foot tall cascade using natural channel design and rehabilitate one mile of fish habitat through an anthropogenically degraded reach of the upper mainstem East Fork of the South Fork Salmon River.
Status:
Finalized
Province:
Mountain Snake
Subbasin:
Salmon
Contact Name:
Kent Werlin
Contact Organization:
Nez Perce Tribe DFRM - Watershed Division
Contact Email:
kentw@nezperce.org
Contact Address:
PO Box 365
Contact City, State, Zip:
Lapawai, ID, 83540
Contact Role(s):
Project Lead
Information Transfer:
Reports and presentations at professional conferences and public outreach

Description Latitude Longitude
The project reach is on the mainstem EFSFSR between Meadow Creek (upstream) and Sugar Creek (downstream) 44.925095408978580 -115.333815722123550

Name Primary Secondary
Trout
Trout
Chinook
Steelhead
Cutthroat Trout
Whitefish

Short Objective Detailed Objective Strategy Subbasin Plan
Reduce instream sedimentation Problem 10, Objective 10A - Starting in important habitats, reduce instream sedimentation to levels meeting applicable water standards (e.g., TMDLs) and measures, with an established upward trend i... 10A4 - �identify and treat legacy effects from mining-related sedimentation,� 10A8 - �conduct implementation and effectiveness monitoring of projects designed to reduce sediment delivery to streams... Salmon
Reduce concentrations of non-organic chemicals Problem 11, Objective 11A - Reduce concentrations of non-organic chemicals to levels consistent with IDEQ beneficial use criteria. The Stibnite Mine is expressly mentioned as a ?priority area,? an... 11A1 - �clean up and stabilize (through planting) ... tailings piles at active (and) inactive...sites,� 11A3 - �ensure adequate riparian areas exist both upstream and down stream of the affected si... Salmon
Rehabilitate connectivity & improve fish passage Problem 12, Objective 12A - ?Rehabilitate connectivity where it will benefit native fish populations, with emphasis on bull trout.? The Salmon Subbasin Plan states ?disconnection of tributaries fro... 12A1 - �reconnect waterways�define which structural barriers should be removed or modified first,� 12A2 - Use information obtained from implementation to obtain a better understanding of the ecolog... Salmon
Revegetate tributaries and improve bank stability Problem 43, Objective 43A - "Localized riparian issues exist in the South Fork Watershed." Revegetate tributary reaches in areas not dominated by rip-rap or road beds and improve bank stability alo... 8C1 - Stabilize problem areas through riparian plantings, 8C2 - Ensure revegetation efforts succeed by protecting them from grazing and development, 8C3 - Perform M&E on project actions, 8D1,55B4,9... Salmon
Restore degraded riparian areas Problem 51, Objective 51B - The Subbasin Plan states "restore 50% of degraded riparian areas to proper functioning condition by 2019." Riparian area PFC provides: shade, LWM recruitment, habitat p... 51B1 - Identify and prioritize riparian habitats for restoration, 51B2 - Restore riparian habitats, 51B3, 51B4 - Encourage landowners to replant native vegetation along degraded reaches, 51B8, 8A2,... Salmon
Increase number of pieces of LWD Problem 8, Objective 8A - Increase the number of pieces of LWD in reaches currently deficient, to volumes consistent with PFC ratings (> 20 pieces/mi.)... 8A2 - "Enhance and rehabilitate riparian ecosystems," 8A3 - Artificially recruit LWD to stream channel if neccesary, 8A4 - Provide M&E for passive and active protection and rehabilitation efforts,4... Salmon
Protect cultural uses of natural resources Socioeconomic Prob. 65, Objective 65 - Protect and foster both Indian and non-Indian cultural uses of natural resources in the Salmon subbasin.... 65A1- Integrate information and education on important indian and non-indian culture, treaty rights, and historic and current resource use into project selection and implementation... Salmon
Improve bank stability to PFC standards Problem 8, Objective 8C - Improve bank stability to properly functioning condition 8C1 - stabilize problem areas through riparian plantings, 8C2 - protect plantings from grazing and development, 8C3 - monitor and evaluate... Salmon

Line Item Notes FY07 Cost FY08 Cost FY09 Cost
Personnel Project Lead, Support Staff, and Technical Staff Salaries $71,000 $58,700 $71,000
Fringe Benefits Nez Perce Tribe Employee Fringe $21,300 $17,600 $21,300
Supplies Supplies, materials, equipment, etc. $41,000 $5,200 $28,200
Travel to and from work site, BPA meetings, coordination meetings, GSA Vehicle, etc. $13,000 $11,000 $11,000
Other Training $1,000 $1,000 $1,000
Other Consultants and Contracts $128,000 $365,000 $155,000
Overhead Nez Perce Tribe Indirect Rate $43,700 $27,700 $39,300
Other Office Space Rental $6,000 $3,000 $6,000

Provision Funding Source Type FY07 Value FY08 Value FY09 Value
Water chemistry analysis IDEQ In-Kind $10,000 $10,000 $10,000
Volunteer planting and riparian restoration work IDFG In-Kind $0 $10,000 $20,000
Project M&E, fish salvage, substrate/temp M&E, NEPA & ESA documentation, smelter stack removal, etc. USDA-Forest Service In-Kind $550,000 $150,000 $150,000

WE ID WE Name Title Budget Start Date End Date Objectives Metrics
47 Plant Vegetation Revegetate degraded riparian area $90,000 08/01/2008 11/01/2009 Improve bank stability to PFC standards Reduce concentrations of non-organic chemicals Revegetate tributaries and improve bank stability * # of riparian miles treated: 2
180 Enhance Floodplain Recontour, construct/ammend soils, and revegetate floodplain $32,000 08/01/2008 11/01/2009 Restore degraded riparian areas * # of acres treated: 50
30 Realign, Connect, and/or Create Channel Perform stream channel and streambank restoration $250,000 06/01/2008 11/01/2008 Reduce instream sedimentation * # of stream miles before treatment: 1
29 Increase Instream Habitat Complexity Install Large Woody Debris as needed $20,000 06/01/2008 11/01/2008 Increase number of pieces of LWD * # of stream miles treated: 1
175 Produce Design and/or Specifications Produce final project designs $115,000 03/01/2007 03/01/2008 Rehabilitate connectivity & improve fish passage
184 Install Fish Passage Structure Reestablish connectivity and fish passage $335,000 06/01/2008 11/01/2008 Rehabilitate connectivity & improve fish passage * Does the structure remove or replace a fish passage barrier?: yes * Was barrier Full or Partial?: Full for primary focal species * # of miles of habitat accessed: 13.9
118 Coordination Coordinate project activities $100,000 03/01/2007 02/28/2010
119 Manage and Administer Projects Manage and administer project $120,000 03/01/2007 02/28/2010
99 Outreach and Education Provide outreach and education for the public $35,000 05/01/2007 12/01/2009 Protect cultural uses of natural resources * # of general public reached: 50 * # of students reached: 50 * # of teachers reached: 5
157 Collect/Generate/Validate Field and Lab Data Collect data for project implementation and efficacy analysis $20,000 03/01/2007 02/28/2010 Rehabilitate connectivity & improve fish passage Primary R, M, and E Type: Project Implementation/ Compliance Monitoring
28 Trap and Haul Perform fish salvage during implementation $0 07/01/2008 11/01/2008 Rehabilitate connectivity & improve fish passage * # of fish: as needed
158 Mark/Tag Animals Tag fish to analyze project efficacy $15,000 03/01/2008 02/28/2010 Rehabilitate connectivity & improve fish passage
162 Analyze/Interpret Data Perform project implementation and efficacy analysis $0 03/01/2009 02/28/2010 Rehabilitate connectivity & improve fish passage Primary R, M, and E Type: Action Effectiveness Research
185 Produce Pisces Status Report Produce PICES status reports $5,000 03/01/2007 02/28/2010
132 Produce Annual Report Produce annual reports $5,000 03/01/2007 02/28/2010
165 Produce Environmental Compliance Documentation Provide NEPA, ESA compliance, and cultural clearance documentation as well as obtain relevant USACE 404 and State of Idaho 401permits $5,000 03/01/2007 08/01/2008

Date Reviewer Short Recommendation Comments FY07 FY08 FY09
06/02/2006 ISRP Fundable This project is to provide fish passage for steelhead, chinook and bull trout past an old mine site. This seems like heroic engineering, but that may be what is required in this instance. Future M&E... More N/A N/A N/A
08/31/2006 ISRP Fundable This project is to provide fish passage for steelhead, chinook and bull trout past an old mine site. This seems like heroic engineering, but that may be what is required in this instance. Future M&E... More N/A N/A N/A
09/15/2006 NPCC $0.00 $0.00 $0.00
10/23/2006 NPCC Do Not Fund $0.00 $0.00 $0.00