Show new navigation
On
Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program

Environmental Compliance Summary

Contract 57842: 1994-015-00 EXP IDAHO FISH SCREENING IMPROVEMENT
Viewing 16 of 16 Work Statement Elements
Sort
WE ID
WE Title
EC Required
WE Start
WE End
NEPA
Public Involvement
NOAA
USFWS
NHPA
Has Provisions
Inadvertent Discovery
Completed
A119Routine Administration of Contract and all Related ProjectsNo07/01/201206/30/2013YesNoNoNoNoNoNo07/01/2012
B165Complete Environmental ComplianceNo07/01/201206/30/2013YesNoNoNoNoNoNo07/01/2012
C114Conduct meetingsNo07/01/201206/30/2013YesNoNoNoNoNoNo07/01/2012
D191Agency Project CoordinationNo07/01/201206/30/2013YesNoNoNoNoNoNo07/01/2012
E115Stream Investigations & Habitat AssessmentsYes07/01/201206/30/2013YesNoYesYesNoNoNo02/14/2013
F55Hydro-seed BPA Funded Sulfur Creek Culvert Replacement ProjectYes07/01/201211/15/2012YesNoNoNoNoNoNo07/01/2012
G55Hydro-seed BPA Funded Bohannon Creek Culvert Replacement ProjectYes07/01/201211/01/2012YesNoNoNoNoNoNo07/01/2012
H55Hydro-seed BPA Funded Kenney Creek Culvert Preplacement ProjectYes07/01/201211/01/2012YesNoNoNoNoNoNo07/01/2012
I55Hydro-seed BPA Funded Agency Creek Culvert ReplacementYes07/01/201211/01/2012YesNoNoNoNoNoNo07/01/2012
J84LBC-08 Diversion RemovalYes07/01/201204/15/2013YesNoYesYesYesNoNo02/14/2013
K84SIC-07 Diversion InstallationYes07/01/201206/20/2013YesNoYesYesYesNoNo02/14/2013
L122Technical Review and Recommendations for Fisheries ProjectsNo07/01/201206/30/2013YesNoNoNoNoNoNo07/01/2012
M175Topographic SurveysYes07/01/201206/30/2013YesNoNoNoNoNoNo07/01/2012
N175Feasibility Preliminary Design WorkYes07/01/201206/30/2013YesNoNoNoNoNoNo07/01/2012
O185Periodic Status Reports for BPANo10/01/201206/30/2013YesNoNoNoNoNoNo07/01/2012
P132Submit Progress Report for the period July 2012 to June 2013No07/01/201203/31/2013YesNoNoNoNoNoNo07/01/2012