A | 165 | Complete and/or initiate Environmental Permitting for Project Activities | No | 09/01/2019 | 12/31/2020 | No | No | No | No | No | No | No | |
B | 30 | Construct main channel and side channels activate swale networks | Yes | 09/01/2019 | 11/30/2021 | Yes | Yes | Yes | Yes | Yes | No | No | 07/22/2020 |
C | 29 | Construct main channel, side channels, and floodplain features | Yes | 09/01/2019 | 11/30/2021 | Yes | Yes | Yes | Yes | Yes | No | No | 07/22/2020 |
D | 47 | Plant native trees, shrubs, and grasses on the Longley Meadows Project | Yes | 09/01/2019 | 11/30/2021 | Yes | Yes | Yes | Yes | Yes | No | No | 07/22/2020 |
E | 40 | Install fences on the Longley Meadows Project | Yes | 09/01/2019 | 11/30/2021 | Yes | Yes | Yes | Yes | Yes | No | No | 07/22/2020 |
F | 119 | Project Contract Administration | No | 09/01/2019 | 11/30/2021 | Yes | No | No | No | No | No | No | |
G | 132 | Longley Meadows Completion Report | No | 12/31/2021 | Yes | No | No | No | No | No | No | ||
H | 185 | Quarterly Status Reports | No | 01/01/2020 | 12/31/2021 | Yes | No | No | No | No | No | No |