Environmental Compliance Summary

Contract 74017 REL 26: 2007-127-00 EXP E FORK OF S FORK SALMON PASSAGE RESTORATION
Viewing 15 of 15 Work Statement Elements
Sort
WE ID
WE Title
EC Required
WE Start
WE End
NEPA
Public Involvement
NOAA
USFWS
NHPA
Has Provisions
Inadvertent Discovery
Completed
A185Periodic Status Reports for BPANo07/01/201803/31/2019YesNoNoNoNoNoNo04/01/2018
B119Project Management, Coordination, and AdministrationNo04/01/201803/31/2019YesNoNoNoNoNoNo04/01/2018
C165Provide Environmental Compliance Documentation to BPANo04/01/201803/31/2019YesNoNoNoNoNoNo04/01/2018
D99Public outreach and educationNo04/01/201803/31/2019YesNoNoNoNoNoNo04/01/2018
E198Maintain Riparian plantings at Wapiti and Burgdorf MeadowsYes04/01/201810/31/2018YesYesYesYesYesNoNo06/01/2018
F199Remove Reed Canary GrassYes04/01/201811/30/2018YesYesYesYesYesNoNo06/01/2018
G38Improving road failure on the old SFSR roadYes04/01/201801/10/2019YesYesYesYesYesYesNo06/01/2018
H33Dollar Creek Road Decommission 14-16 Miles of Forest RoadsYes04/01/201811/30/2018YesYesYesYesYesYesNo07/20/2018
I38Dollar Creek road (495) failure repairYes04/01/201810/31/2018YesYesYesYesYesYesNo07/19/2018
J38Ice Hole Campground RestorationYes04/01/201811/30/2018YesYesYesYesYesNoNo07/20/2018
K33Big Creek Road DecomissioningYes04/01/201810/31/2018YesYesYesYesYesYesNo06/01/2018
L38Big Creek Road ImprovementYes04/01/201810/31/2018YesYesYesYesYesYesNo06/01/2018
M115GRAIP road inventory surveysYes04/01/201811/30/2018YesYesYesYesYesNoNo03/21/2018
N132Submit Progress Report for the period 4/17 thru 3/18No04/01/201803/31/2019YesNoNoNoNoNoNo04/01/2018
O114Identify and Select FY19 Restoration ProjectsNo04/01/201803/31/2019YesNoNoNoNoNoNo04/01/2018