A | 119 | Manage and Administer Project | No | 07/01/2024 | 06/30/2025 | Yes | No | No | No | No | No | No | |
B | 175 | Habitat design for Pond Series 4 reconnect project. Coordinate with BPA, SBT, and other Yankee Fork ID team members on review of 15%, 30%, 80%, and Final Design Iteration. | Yes | 07/01/2024 | 06/30/2025 | Yes | No | No | No | No | No | No | |
C | 165 | Environmental Compliance | No | 07/01/2024 | 06/30/2025 | Yes | No | No | No | No | No | No | |
D | 114 | Coordinate with BPA, SBT, and other Yankee Fork ID team members on feasibility analysis for tributary reconnect/side-channel projects at Jerry's and Silver creeks | No | 07/01/2024 | 06/30/2025 | No | No | No | No | No | No | No | |
E | 183 | Yankee Fork Capacity Estimate: Short Report and Potential Journal Article | No | 04/01/2025 | 06/30/2025 | No | No | No | No | No | No | No | |
F | 185 | Periodic Status Reports for BPA | No | 10/01/2024 | 06/30/2025 | No | No | No | No | No | No | No | |
G | 132 | Submit Final Progress Report for the period July 2024 to June 2025 | No | 01/01/2025 | 06/30/2025 | Yes | No | No | No | No | No | No |