Province | Subbasin | % |
---|---|---|
Mountain Snake | Clearwater | 100.00% |
Previous: | Next: |
---|---|
n/a |
|
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Environmental compliance documentation submitted to BPA | A: 165. Provide Environmental Compliance Documentation to BPA | 06/01/2007 | 06/01/2007 | |
Design Culvert Replacements | B: 175. Design up to five culvert replacements | 05/30/2008 | 05/30/2008 | |
Decommission 12 miles of road in Red River Watershed | C: 33. Red Pines Road Decommissioning Phase III | 10/31/2007 | 10/31/2007 | |
12 miles of erosion control on decommissioned roads. | D: 55. Erosion Control on Decommissioned Roads | 10/31/2007 | 10/31/2007 | |
Seed & Fertilize Decommissioned Roads | E: 47. Seed Decommissioned Roads | 10/31/2007 | 10/31/2007 | |
FY 07 SOW package and accrual estimate | F: 119. Management, Coordination and Communication | 11/30/2007 | 11/23/2007 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | Provide Environmental Compliance Documentation to BPA | 02/09/2007 | ||||||
B | 175 | Design up to five culvert replacements | 02/09/2007 | ||||||
C | 33 | Red Pines Road Decommissioning Phase III | 03/30/2007 | ||||||
D | 55 | Erosion Control on Decommissioned Roads | 03/30/2007 | ||||||
E | 47 | Seed Decommissioned Roads | 03/30/2007 | ||||||
F | 119 | Management, Coordination and Communication | 02/09/2007 | ||||||
G | 185 | Periodic Status Reports for BPA | 02/09/2007 |